BOQAgent
AED · ADDRESS RESIDENCES ZABEEL

04 BOQ T2 — GR1, 2 - Main, 3 - Ext, Bill 4

04 BOQ T2 — GR1, 2 - Main, 3 - Ext, Bill 4.xlsxNeeds review
Bill total
2,715,670,000.00
+0.02 vs qty×rate
Needs review
605
92%
0 errors · 605 to acknowledge
Reconciliation
Does not reconcile
LINEPAGESECTIONZONEBILLSUMMARY
Source verification
8/12
independent proofs against the raw file
Size
7,323
533 collection blocks · 4 sheets

1 block does not add up to the collection total its own page prints

error

Both figures are shown — neither is corrected to the other.

503 lines print words where a figure belongs

to answer

Accept the wording as a class, or put it to the bidder.

  • References hereunder to the Schedule of Project Requirements (SOPR) are intended solely to direct the Contractor to the specific requirements of the Schedule of Project Requirements in respect of a particular item and do not in any way limit the scope of such item to the requirements of the Schedule of Project Requirements.
  • 2 Advance Payment Guarantee
  • 4 Contractor's All Risk Policy
16,478 units measuredlargest: 3,267 Nr. 2/R/129 E

100 lines carry no rate, so nothing reaches the totals

to answer

Say why the bidder left them unpriced, or ask them to price them.

  • The rates and prices in these Bills of Quantities are fixed for the duration of the Contract and shall not be subject to any adjustment in respect of rise or fall in the cost of labour, materials, plant, equipment, transport or any other matters affecting the cost of execution of the Contract.
  • 1 As per Emaar standard CoC
  • 3 Performance Bond

1 line restarts its lettering without a new heading

to answer

Usually a heading the page prints that was not picked up.

  • Coupling beams
812 units measured399,171.08 carriedlargest: 399,171.08 2/C/3 A

1 line has no heading above it while its neighbours do

to answer

A governing heading may have been missed when the page was read.

  • Allow for planting edging
1 unit measured61,349.65 carriedlargest: 61,349.65 3/B/4 L
ItemDescriptionQtyUnitRateAmountState
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/1
0/2 clear
0.00 Σ lines
Generally
The rates and prices in these Bills of Quantities are fixed for the duration of the Contract and shall not be subject to any adjustment in respect of rise or fall in the cost of labour, materials, plant, equipment, transport or any other matters affecting the cost of execution of the Contract.
REVIEWThe source prints neither a quantity nor a rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
ItemNeeds review
Generally
References hereunder to the Schedule of Project Requirements (SOPR) are intended solely to direct the Contractor to the specific requirements of the Schedule of Project Requirements in respect of a particular item and do not in any way limit the scope of such item to the requirements of the Schedule of Project Requirements.
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/2
0/9 clear
0.00 Σ lines 0.00 printed
A1.1- Schedule of Clauses
1 As per Emaar standard CoC
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A1.1- Schedule of Clauses
2 Advance Payment Guarantee
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
3 Performance Bond
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A1.1- Schedule of Clauses
4 Contractor's All Risk Policy
REVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemBy EmployerNeeds review
A1.1- Schedule of Clauses
5 Workmen's Compensation Insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
6 Professional Indemnity insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
7 Third Party liability insurance
REVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemBy EmployerNeeds review
A1.1- Schedule of Clauses
8 Plant and Contractor's Equipment Insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
9 Motor Vehicle Third Party and Passenger Liability Insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/3
0/1 clear
0.00 Σ lines 0.00 printed
A1.1- Schedule of Clauses
The Contractor shall price hereunder any special requirements related to the specification clauses
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/4
0/5 clear
0.00 Σ lines 0.00 printed
A3 - Restrictions
1 Access for and Possession or use of the Site
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A3 - Restrictions
2 Limitations of working space
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A3 - Restrictions
3 Limitations of working hours
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A3 - Restrictions
4 The Maintenance of existing services on, under or over the Site
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A3 - Restrictions
5 The Execution of the Works in the required specific order, sections or phases
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/5
0/7 clear
0.00 Σ lines 0.00 printed
1 Office for the Contract administrators
i. Establishment
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
ii. Maintenance
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
iii. Removal
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
2 Supervision
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
1 Office for the Contract administrators
3 Security
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
4 Safety, health and welfare of workpeople
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
5 Transport of workpeople
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/6
0/16 clear
0.00 Σ lines 0.00 printed
1 Small plant and tools
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Small plant and tools
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Small plant and tools
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 Scaffoldings
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 Scaffoldings
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 Scaffoldings
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
3 Cranes and lifting plant
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
3 Cranes and lifting plant
ii. Maintenance (Time Related Charges)
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
3 Cranes and lifting plant
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Plant required for specific trades
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Plant required for specific trades
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Plant required for specific trades
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Site Transport
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Site Transport
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Site Transport
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Site Transport
6 Other plant not listed above but necessary for the completion of the Works
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/7
0/11 clear
0.00 Σ lines 0.00 printed
1 - Temporary fully functional site facilities
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 - Temporary fully functional site facilities
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 - Temporary fully functional site facilities
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Telephones, including costs of calls
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Telephones, including costs of calls
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Telephones, including costs of calls
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Telephones, including costs of calls
3 - Attendance of staff (for example, drivers, laboratory assistants)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 - Equipment (for example surveying equipment, laboratory equipment)
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 - Equipment (for example surveying equipment, laboratory equipment)
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 - Equipment (for example surveying equipment, laboratory equipment)
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 - Equipment (for example surveying equipment, laboratory equipment)
5 - Special requirements for programmes or progress charts
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/8
0/4 clear
0.00 Σ lines 0.00 printed
6 Any other facilities (for example, progress photographs).
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Any other facilities (for example, progress photographs).
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Any other facilities (for example, progress photographs).
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
Signboard
Existing signboard to be taken over from Enabling Works contractor and Main Works contractor to update the names, maintain as required, remove after completion of the Works
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/9
0/11 clear
0.00 Σ lines
1 - Contractor's Facilities, including offices, toilets, laboratories, compounds, stores, mess rooms
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 - Contractor's Facilities, including offices, toilets, laboratories, compounds, stores, mess rooms
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Temporary fencing, hoardings
i. Existing temporary site perimeter hoarding to be taken over from Enabling Works contractor and Main Works contractor to move / remove / adjust, maintain as required
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Temporary fencing, hoardings
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Temporary fencing, hoardings
ii. Final Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
3 Screens and guardrails
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
3 Screens and guardrails
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
3 Screens and guardrails
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Temporary roads, hard standings and crossings
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Temporary roads, hard standings and crossings
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Temporary roads, hard standings and crossings
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/10
0/9 clear
0.00 Σ lines 0.00 printed
5 Water for the Works
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Water for the Works
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Water for the Works
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Lighting and power for the Works
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Lighting and power for the Works
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Lighting and power for the Works
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
7 Temporary telephones, electronic mail and facsimile
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
7 Temporary telephones, electronic mail and facsimile
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
7 Temporary telephones, electronic mail and facsimile
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/11
0/3 clear
0.00 Σ lines 0.00 printed
A8.1 An item shall be given for temporary works including design, which shall include:
1 Traffic diversion
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A8.1 An item shall be given for temporary works including design, which shall include:
2 Access roads
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A8.1 An item shall be given for temporary works including design, which shall include:
3 Pumping
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/12
0/14 clear
0.00 Σ lines 0.00 printed
A9.1 An item shall be given for temporary works, which shall include:
1 - Testing of materials
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
2 - Testing of the Works
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
3 - Protecting the Works from inclement weather
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
4 - Removing rubbish, protective casings and coverings and cleaning the Works at completion
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
5 - Traffic regulations
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
6 - Maintenance of public and private roads
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
7 - Drying the Works
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
8 - Control of noise and pollution
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
9 - All Statutory obligations
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
1 - Coordination with the Works by Others
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
2 - Surveys, Setting-out and Levels
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
3 - Dust Control, Pest Control and Lightning Protection
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
4 - Off site storage
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
5 - Packing, marking, storage, handling and unpacking
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/13
0/17 clear
0.00 Σ lines 0.00 printed
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
6 - Specialist Third Party Testing, Commissioning and Certification
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
7 - Shop Drawings
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
8 - Submittal program, drawings and revisions
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
9 - Method Statements
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
10 - Operation and Maintenance Manuals
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
11 - Building Information Modelling (BIM) System
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
12 - Project Management System - Unifier
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
12 - Internet connection requirements on site
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
13 - Precautions against Fire
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
15 - Project Health, Safety, Environment and Security Guidelines
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
16 - General cleaning and waste disposal during construction
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
17 - Final Cleaning for Project Handover
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
18 - Provision of Handover Documentation
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
19 - Contract Spares/Attic stock
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
20 - As-built drawings
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
21 - Design of the Works to the extent provided for in the Contract
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
22 - Warranties
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/14
0/1 clear
0.00 Σ lines 0.00 printed
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
23 - All mock-ups, prototypes and samples required by the Specification, the Drawings and the Schedule of Project Requirements
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/15
0/1 clear
0.00 Σ lines 0.00 printed
Additional Items
Any items that may not be covered elsewhere in the Bills of Quantities which the Tenderer deemed to be necessary in order to carry out the works in full compliance with the SOPR must be itemised and price below
REVIEWThe source prints neither a quantity nor a rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
ItemNeeds review
2/C · 2/C/3 · POURED CONCRETE · 2 - Main/6
0/1 clear
399,171.08 Σ lines
Reinforced concrete; concrete grade C56/70
Coupling beams
REVIEWReference sequence restarts at "A" on 2 - Main/6 without a heading change — a governing heading may have been missed above it.
812m3491.59399,171.08Needs review
2/D · 2/D/2 · SUNDRIES · 2 - Main/16
0/2 clear
0.00 Σ lines
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Dowelled control joints
REVIEWAmount column prints "Included in item A-L" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1Item0.000.00Included in item A-LNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Isolation joints
REVIEWAmount column prints "Included in item A-L" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1Item0.000.00Included in item A-LNeeds review
2/F · 2/F/12 · COMPOSITE ITEMS · 2 - Main/40
0/9 clear
0.00 Σ lines
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 1; base unit; size 3395 x 640 x 900mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
2Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 1; wall unit; size 2540 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
143Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 1040 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
143Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 1; full unit; size 630 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
2Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 1; full unit; size 1080 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
141Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 2; wall unit; size (2520+1750) x 350 x 1100mm high; L-shaped
REVIEWAmount column prints "Included in Item-L&M" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
328Nr.0.000.00Included in Item-L&MNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 2; wall unit; size (2650+1480) x 350 x 1100mm high; L-shaped
REVIEWAmount column prints "Included in Item-L&M" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
192Nr.0.000.00Included in Item-L&MNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 330 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-L&M" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1,040Nr.0.000.00Included in Item-L&MNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 2; full unit; size 600 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-L&M" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
520Nr.0.000.00Included in Item-L&MNeeds review
2/F · 2/F/13 · COMPOSITE ITEMS · 2 - Main/41
0/12 clear
0.00 Σ lines
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 3; wall unit; size 560 1375 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-C" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
364Nr.0.000.00Included in Item-CNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 3; wall unit; size 1690 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-C" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
364Nr.0.000.00Included in Item-CNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 880 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-C" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
364Nr.0.000.00Included in Item-CNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 3; full unit; size 600 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-C" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
364Nr.0.000.00Included in Item-CNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 4; wall unit; size (3190+1140) x 350 x 1100mm high; L-shaped
REVIEWAmount column prints "Included in Item-J&K" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
49Nr.0.000.00Included in Item-J&KNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 590 x 350 x 1070mm high
REVIEWAmount column prints "Included in Item-J&K" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
49Nr.0.000.00Included in Item-J&KNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 4; full unit; size 600 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-J&K" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
49Nr.0.000.00Included in Item-J&KNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 5; wall unit; size 3660 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-P" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
736Nr.0.000.00Included in Item-PNeeds review
loading more… 150 of 605 lines rendered
ItemDescriptionQtyUnitRateAmountState
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS
0/111 clear
0.00 Σ lines
Generally
The rates and prices in these Bills of Quantities are fixed for the duration of the Contract and shall not be subject to any adjustment in respect of rise or fall in the cost of labour, materials, plant, equipment, transport or any other matters affecting the cost of execution of the Contract.
REVIEWThe source prints neither a quantity nor a rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
ItemNeeds review
Generally
References hereunder to the Schedule of Project Requirements (SOPR) are intended solely to direct the Contractor to the specific requirements of the Schedule of Project Requirements in respect of a particular item and do not in any way limit the scope of such item to the requirements of the Schedule of Project Requirements.
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
1 As per Emaar standard CoC
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A1.1- Schedule of Clauses
2 Advance Payment Guarantee
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
3 Performance Bond
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A1.1- Schedule of Clauses
4 Contractor's All Risk Policy
REVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemBy EmployerNeeds review
A1.1- Schedule of Clauses
5 Workmen's Compensation Insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
6 Professional Indemnity insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
7 Third Party liability insurance
REVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemBy EmployerNeeds review
A1.1- Schedule of Clauses
8 Plant and Contractor's Equipment Insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
9 Motor Vehicle Third Party and Passenger Liability Insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
The Contractor shall price hereunder any special requirements related to the specification clauses
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A3 - Restrictions
1 Access for and Possession or use of the Site
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A3 - Restrictions
2 Limitations of working space
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A3 - Restrictions
3 Limitations of working hours
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A3 - Restrictions
4 The Maintenance of existing services on, under or over the Site
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A3 - Restrictions
5 The Execution of the Works in the required specific order, sections or phases
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
i. Establishment
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
ii. Maintenance
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
iii. Removal
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
2 Supervision
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
1 Office for the Contract administrators
3 Security
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
4 Safety, health and welfare of workpeople
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Office for the Contract administrators
5 Transport of workpeople
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Small plant and tools
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Small plant and tools
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 Small plant and tools
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 Scaffoldings
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 Scaffoldings
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 Scaffoldings
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
3 Cranes and lifting plant
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
3 Cranes and lifting plant
ii. Maintenance (Time Related Charges)
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
3 Cranes and lifting plant
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Plant required for specific trades
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Plant required for specific trades
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Plant required for specific trades
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Site Transport
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Site Transport
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Site Transport
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Site Transport
6 Other plant not listed above but necessary for the completion of the Works
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 - Temporary fully functional site facilities
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 - Temporary fully functional site facilities
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 - Temporary fully functional site facilities
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Telephones, including costs of calls
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Telephones, including costs of calls
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Telephones, including costs of calls
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Telephones, including costs of calls
3 - Attendance of staff (for example, drivers, laboratory assistants)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 - Equipment (for example surveying equipment, laboratory equipment)
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 - Equipment (for example surveying equipment, laboratory equipment)
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 - Equipment (for example surveying equipment, laboratory equipment)
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 - Equipment (for example surveying equipment, laboratory equipment)
5 - Special requirements for programmes or progress charts
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Any other facilities (for example, progress photographs).
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Any other facilities (for example, progress photographs).
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Any other facilities (for example, progress photographs).
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
Signboard
Existing signboard to be taken over from Enabling Works contractor and Main Works contractor to update the names, maintain as required, remove after completion of the Works
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 - Contractor's Facilities, including offices, toilets, laboratories, compounds, stores, mess rooms
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
1 - Contractor's Facilities, including offices, toilets, laboratories, compounds, stores, mess rooms
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Temporary fencing, hoardings
i. Existing temporary site perimeter hoarding to be taken over from Enabling Works contractor and Main Works contractor to move / remove / adjust, maintain as required
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Temporary fencing, hoardings
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
2 - Temporary fencing, hoardings
ii. Final Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
3 Screens and guardrails
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
3 Screens and guardrails
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
3 Screens and guardrails
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Temporary roads, hard standings and crossings
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Temporary roads, hard standings and crossings
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
4 Temporary roads, hard standings and crossings
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Water for the Works
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Water for the Works
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
5 Water for the Works
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Lighting and power for the Works
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Lighting and power for the Works
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
6 Lighting and power for the Works
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
7 Temporary telephones, electronic mail and facsimile
i. Establishment (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
7 Temporary telephones, electronic mail and facsimile
ii. Maintenance (Time Related Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
7 Temporary telephones, electronic mail and facsimile
iii. Removal (Fixed Charges)
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A8.1 An item shall be given for temporary works including design, which shall include:
1 Traffic diversion
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A8.1 An item shall be given for temporary works including design, which shall include:
2 Access roads
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A8.1 An item shall be given for temporary works including design, which shall include:
3 Pumping
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
1 - Testing of materials
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
2 - Testing of the Works
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
3 - Protecting the Works from inclement weather
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
4 - Removing rubbish, protective casings and coverings and cleaning the Works at completion
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
5 - Traffic regulations
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
6 - Maintenance of public and private roads
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
7 - Drying the Works
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
8 - Control of noise and pollution
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.1 An item shall be given for temporary works, which shall include:
9 - All Statutory obligations
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
1 - Coordination with the Works by Others
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
2 - Surveys, Setting-out and Levels
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
3 - Dust Control, Pest Control and Lightning Protection
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
4 - Off site storage
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
5 - Packing, marking, storage, handling and unpacking
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
6 - Specialist Third Party Testing, Commissioning and Certification
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
7 - Shop Drawings
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
8 - Submittal program, drawings and revisions
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
9 - Method Statements
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
10 - Operation and Maintenance Manuals
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
11 - Building Information Modelling (BIM) System
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
12 - Project Management System - Unifier
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
12 - Internet connection requirements on site
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
13 - Precautions against Fire
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
15 - Project Health, Safety, Environment and Security Guidelines
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
16 - General cleaning and waste disposal during construction
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
17 - Final Cleaning for Project Handover
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
18 - Provision of Handover Documentation
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
19 - Contract Spares/Attic stock
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
20 - As-built drawings
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
21 - Design of the Works to the extent provided for in the Contract
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
22 - Warranties
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
Item0.00Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
23 - All mock-ups, prototypes and samples required by the Specification, the Drawings and the Schedule of Project Requirements
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
Additional Items
Any items that may not be covered elsewhere in the Bills of Quantities which the Tenderer deemed to be necessary in order to carry out the works in full compliance with the SOPR must be itemised and price below
REVIEWThe source prints neither a quantity nor a rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
ItemNeeds review
POURED CONCRETE
0/1 clear
399,171.08 Σ lines
Reinforced concrete; concrete grade C56/70
Coupling beams
REVIEWReference sequence restarts at "A" on 2 - Main/6 without a heading change — a governing heading may have been missed above it.
812m3491.59399,171.08Needs review
SUNDRIES
0/48 clear
61,349.65 Σ lines
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Dowelled control joints
REVIEWAmount column prints "Included in item A-L" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1Item0.000.00Included in item A-LNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Isolation joints
REVIEWAmount column prints "Included in item A-L" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1Item0.000.00Included in item A-LNeeds review
Allow for providing shop drawings, as built drawings and material submittal approvals
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Allow for providing catalogues, operation and maintenance manuals
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Allow for labeling, tagging of equipment with their related control panel and components as specified
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Allow for testing and commissioning the complete installation
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Allow for all connections to existing services mains
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for earthing and bonding as specified; in particular all ductwork systems shall be provided with earth continuity protection at all joints
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for all supports, fixings, anchors, insulating blocks and anti-vibration devices where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for all identification including painting, marking and labeling, including labeling all valves
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for flushing, cleaning, sterilization and chlorination of the completed installations as necessary
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for inspection, testing and commissioning including all off-site and factory testing; inspections to demonstrate compliance with relevant specifications and standards; operating the completed installations; submitting all relevant test record sheets at the completion of the installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for vibration and noise control where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for all supports, fixings, anchors and insulating blocks where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for all identification including painting, marking and labeling
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for inspection, testing and commissioning including all off-site and factory testing; inspections to demonstrate compliance with relevant specifications and standards; operating the completed installations; submitting all relevant test record sheets at the completion of the installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed installation
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for planting edging
REVIEW"Allow for planting edging" has no heading context while other items on 3 - Ext/4 do — a governing heading may have been missed.
1Item61,349.6561,349.65Needs review
Allow for all supports, fixings, anchors and insulating blocks where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for all identification including painting, marking and labelling
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for inspection, testing and commissioning including all off-site and factory testing; inspections to demonstrate compliance with relevant specifications and standards; operating the completed installations; submitting all relevant test record sheets at the completion of the installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed installation
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for planning and coordinating with relevant statutory authorities and with all other trades
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for liaison with obtaining approvals and attendance on approved Authorities, other statutory bodies and service providers as required
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for all incidental work including factory finishing, fixing to all backgrounds by appropriate means and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for supplying and fixing all brackets, clamps and other fixing devices including building in or cutting and pinning and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for training the Employer's Staff to operate and maintain the Mechanical Engineering Installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for all incidental work to the Mechanical Engineering Installations where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Builders work in connection (BWIC) with Mechanical Engineering Installations
Allow for all BWIC with Mechanical Engineering Installations where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for earthing and bonding as specified; in particular all metal containments shall be
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for all supports, fixings, anchors and insulating blocks where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
loading more… 150 of 605 lines rendered
ItemDescriptionQtyUnitRateAmountState
Section 2/C · SECTION C - CONCRETE WORKS · Page 2/C/1 - 2/C/12
0/1 clear
399,171.08 Σ lines
Reinforced concrete; concrete grade C56/70
Coupling beams
REVIEWReference sequence restarts at "A" on 2 - Main/6 without a heading change — a governing heading may have been missed above it.
812m3491.59399,171.08Needs review
Section 2/D · SECTION D - MASONRY · Page 2/D/1 - 2/D/4
0/2 clear
0.00 Σ lines
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Dowelled control joints
REVIEWAmount column prints "Included in item A-L" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1Item0.000.00Included in item A-LNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Isolation joints
REVIEWAmount column prints "Included in item A-L" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1Item0.000.00Included in item A-LNeeds review
Section 2/F · SECTION F - WOOD WORK · Page 2/F/1 - 2/F/25
0/59 clear
0.00 Σ lines
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 1; base unit; size 3395 x 640 x 900mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
2Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 1; wall unit; size 2540 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
143Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 1040 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
143Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 1; full unit; size 630 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
2Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 1; full unit; size 1080 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
141Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 2; wall unit; size (2520+1750) x 350 x 1100mm high; L-shaped
REVIEWAmount column prints "Included in Item-L&M" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
328Nr.0.000.00Included in Item-L&MNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 2; wall unit; size (2650+1480) x 350 x 1100mm high; L-shaped
REVIEWAmount column prints "Included in Item-L&M" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
192Nr.0.000.00Included in Item-L&MNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 330 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-L&M" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1,040Nr.0.000.00Included in Item-L&MNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 2; full unit; size 600 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-L&M" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
520Nr.0.000.00Included in Item-L&MNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 3; wall unit; size 560 1375 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-C" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
364Nr.0.000.00Included in Item-CNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 3; wall unit; size 1690 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-C" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
364Nr.0.000.00Included in Item-CNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 880 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-C" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
364Nr.0.000.00Included in Item-CNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 3; full unit; size 600 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-C" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
364Nr.0.000.00Included in Item-CNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 4; wall unit; size (3190+1140) x 350 x 1100mm high; L-shaped
REVIEWAmount column prints "Included in Item-J&K" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
49Nr.0.000.00Included in Item-J&KNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 590 x 350 x 1070mm high
REVIEWAmount column prints "Included in Item-J&K" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
49Nr.0.000.00Included in Item-J&KNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 4; full unit; size 600 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-J&K" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
49Nr.0.000.00Included in Item-J&KNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 5; wall unit; size 3660 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-P" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
736Nr.0.000.00Included in Item-PNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 460 x 350 x 1070mm high
REVIEWAmount column prints "Included in Item-P" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
738Nr.0.000.00Included in Item-PNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 5; full unit; size 600 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-P" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
2Nr.0.000.00Included in Item-PNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 5; full unit; size 1050 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-P" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
367Nr.0.000.00Included in Item-PNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 6; base unit; size 1895 x 630 x 900mm high
REVIEWAmount column prints "Included in Item-V" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
2Nr.0.000.00Included in Item-VNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 6; wall unit; size 1635 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-V" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
2Nr.0.000.00Included in Item-VNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 6; full unit; size 600 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-V" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
2Nr.0.000.00Included in Item-VNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 7; wall unit; size 2610 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-E&F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
5Nr.0.000.00Included in Item-E&FNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 7; wall unit; size 2640 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-E&F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
194Nr.0.000.00Included in Item-E&FNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 485 x 350 x 1070mm high
REVIEWAmount column prints "Included in Item-E&F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
398Nr.0.000.00Included in Item-E&FNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 7; full unit; size 600 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-E&F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
194Nr.0.000.00Included in Item-E&FNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 7; full unit; size 1050 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-E&F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
5Nr.0.000.00Included in Item-E&FNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 8; base unit; size 2830 x 630 x 900mm high
REVIEWAmount column prints "Included in Item-P" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
46Nr.0.000.00Included in Item-PNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 8; wall unit; size 1480 x 350 x 1100mm high
REVIEWAmount column prints "Included in Item-P" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
92Nr.0.000.00Included in Item-PNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 8; full unit; size 630 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-P" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
46Nr.0.000.00Included in Item-PNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 9; wall unit; size (2440+1835) x 350 x 1100mm high; L-shaped
REVIEWAmount column prints "Included in Item-B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
5Nr.0.000.00Included in Item-BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 640 x 350 x 1070mm high
REVIEWAmount column prints "Included in Item-B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
5Nr.0.000.00Included in Item-BNeeds review
Kitchen cabinets; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 9; full unit; size 1080 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
5Nr.0.000.00Included in Item-BNeeds review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 10; base unit; size 2255 x 630 x 900mm high
REVIEWAmount column prints "Included in Item-G,H&J" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-G,H&JNeeds review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 10; base unit; size 2400 x 630 x 900mm high
REVIEWAmount column prints "Included in Item-G,H&J" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-G,H&JNeeds review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 10; full unit; size 660 x 615 x 2700mm high
REVIEWAmount column prints "Included in Item-G,H&J" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
20Nr.0.000.00Included in Item-G,H&JNeeds review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 10; wall unit; size 2255 x 350 x 1210mm high
REVIEWAmount column prints "Included in Item-G,H&J" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-G,H&JNeeds review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 10; wall unit; size 2440 x 350 x 1210mm high
REVIEWAmount column prints "Included in Item-G,H&J" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-G,H&JNeeds review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 570 x 350 x 1170mm high
REVIEWAmount column prints "Included in Item-G,H&J" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-G,H&JNeeds review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 640 x 350 x 1170mm high
REVIEWAmount column prints "Included in Item-G,H&J" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
30Nr.0.000.00Included in Item-G,H&JNeeds review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 890 x 350 x 1170mm high
REVIEWAmount column prints "Included in Item-G,H&J" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-G,H&JNeeds review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 10; full unit; size 640 x 615 x 2600mm high
REVIEWAmount column prints "Included in Item-G,H&J" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
10Nr.0.000.00Included in Item-G,H&JNeeds review
Kitchen cabinets; to dirty kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 13; wall unit; size 2360 x 615 350 x 825mm high
REVIEWAmount column prints "Included in Item-F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-FNeeds review
Kitchen cabinets; to dirty kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 13; wall unit; size 3285 x 615 350 x 825mm high
REVIEWAmount column prints "Included in Item-F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-FNeeds review
Kitchen cabinets; to dirty kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 13; wall unit; size 2360 x 615 350 x 825mm high
REVIEWAmount column prints "Included in Item-F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-FNeeds review
Kitchen cabinets; to dirty kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 13; wall unit; size 3285 x 615 350 x 825mm high
REVIEWAmount column prints "Included in Item-F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-FNeeds review
Kitchen cabinets; to dirty kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 460 x 350 x 1180mm high
REVIEWAmount column prints "Included in Item-F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-FNeeds review
Kitchen cabinets; to dirty kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 475 x 350 x 1180mm high
REVIEWAmount column prints "Included in Item-F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-FNeeds review
Kitchen cabinets; to dirty kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 780 x 350 x 1180mm high
REVIEWAmount column prints "Included in Item-F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-FNeeds review
Kitchen cabinets; to dirty kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 900 x 350 x 1180mm high
REVIEWAmount column prints "Included in Item-F" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
4Nr.0.000.00Included in Item-FNeeds review
Kitchen cabinets; to back kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 14; base unit; size 575 x 630 x 900mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; to back kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 14; wall unit; size 1325 x 615 x 825mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; to back kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 14; wall unit; size 2435 x 350 x 1210mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; to back kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Type 14; wall unit; size 3485 x 350 x 1210mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; to back kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 865 x 350 x 1180mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; to back kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 900 x 350 x 1180mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; to back kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 1000 x 350 x 1180mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-A&BNeeds review
Kitchen cabinets; to back kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
Extra over for glass unit; size 1085 x 350 x 1180mm high
REVIEWAmount column prints "Included in Item-A&B" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
26Nr.0.000.00Included in Item-A&BNeeds review
Section 2/K · SECTION K - ACCESSORIES · Page 2/K/1 - 2/K/14
0/4 clear
0.00 Σ lines
Glass partition; 10mm thick fully tempered and hear soak tested clear glass; including fixings, finishes, accessories and all ancillary works as necessary
Extra over for single glazed pivot door; size 1150 x 2200mm high
REVIEWAmount column prints "Included in item L" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1Nr.0.000.00Included in item LNeeds review
Shower and toilet glass partition; fixed glass with doors; frosted glass; 10mm thick; including ironmongery, fixings, accessories and all ancillary works as necessary
Extra over doors; overall size; 700mm x 2100mm high
REVIEWAmount column prints "Included in item A,B&C" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
12Nr.0.000.00Included in item A,B&CNeeds review
Clear Glass
Extra over doors; overall size; 700mm x 2000mm high
REVIEWAmount column prints "Included in Item E to U" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1,778Nr.0.000.00Included in Item E to UNeeds review
Fluted Tinted Glass
Extra over doors; overall size; 700mm x 2000mm high
REVIEWAmount column prints "Included in Item A to J" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
983Nr.0.000.00Included in Item A to JNeeds review
Section 2/P · SECTION P - CONVEYING SYSTEMS · Page 2/P/1 - 2/P/8
0/21 clear
0.00 Σ lines
Marble; laid on levelling screed; including adhesive mortar, grout, joint and edge treatment sealer, accessories and all ancillary works as necessary
Type ST-102; 20mm thick
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
84m20.000.00Included in Lift PriceNeeds review
Metal skirting; including adhesive, accessories and all ancillary works as necessary
Type MT-109; 100mm high
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
144m0.000.00Included in Lift PriceNeeds review
Metal insert; including finishes, fixings, accessories and all ancillary works as necessary
Type MT-115; to floor fins
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
160m0.000.00Included in Lift PriceNeeds review
Metal insert; including finishes, fixings, accessories and all ancillary works as necessary
Type MT-113; to wall fins
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
640m0.000.00Included in Lift PriceNeeds review
Grid ceiling; in metal finish; including ceiling suspension system, shadows gaps, trims, corner protection profile, accessories and all ancillary works as necessary
Type WD-102; with MT-109
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
76m20.000.00Included in Lift PriceNeeds review
Grid ceiling; in metal finish; including ceiling suspension system, shadows gaps, trims, corner protection profile, accessories and all ancillary works as necessary
Extra over for access panel; size 600 x 600mm
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
24Nr.0.000.00Included in Lift PriceNeeds review
Mirror; tinted mirror with frame; including, backing, supports, finishes, accessories and all ancillary works as necessary
Type GL-108; 6mm thick
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
168m20.000.00Included in Lift PriceNeeds review
Wall cladding; in high pressure laminate finish; including, backing, supports, finishes, accessories and all ancillary works as necessary
Type LP-105; 20mm thick
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
144m20.000.00Included in Lift PriceNeeds review
Metal finish; including adhesive, finishes, brackets, fixings, accessories and all ancillary works as necessary
Type MT-109
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
92m20.000.00Included in Lift PriceNeeds review
Metal finish; including adhesive, finishes, brackets, fixings, accessories and all ancillary works as necessary
Type MT-112
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
64m20.000.00Included in Lift PriceNeeds review
Hand grab bar; in metal finish; fixed on bracket; including finishes, brackets, fixings, accessories and all ancillary works as necessary
1070mm length
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
48Nr.0.000.00Included in Lift PriceNeeds review
Hand grab bar; in metal finish; fixed on bracket; including finishes, brackets, fixings, accessories and all ancillary works as necessary
1200mm length
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
24Nr.0.000.00Included in Lift PriceNeeds review
Allow for providing shop drawings, as built drawings and material submittal approvals
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Allow for providing catalogues, operation and maintenance manuals
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Allow for labeling, tagging of equipment with their related control panel and components as specified
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Allow for testing and commissioning the complete installation
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Generally
Allow for cutting or forming all holes, mortices, chases and the like and making good finishes for conveying systems
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Generally
Allow for fixing all sleeves, frames and built-in firestop system and making good finishes for conveying systems
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Generally
Allow for firestopping for all holes and making good finishes for conveying systems
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Generally
Allow for building in or cutting and pinning brackets or the like and making good finishes for conveying systems
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Generally
Allow connection to elevator monitoring system (EMS) at BMS room
REVIEWAmount column prints "Included in Lift Price" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Included in Lift PriceNeeds review
Section 2/Q · SECTION Q - MECHANICAL ENGINEERING INSTALLATIONS · Page 2/Q/1 - 2/Q/190
0/34 clear
0.00 Σ lines
Common Areas
Type SAN-204; sensor flush plate
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
30Nr.0.000.00IncludedNeeds review
Sundries
Allow for all supports, fixings, anchors and insulating blocks where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Sundries
Allow for all identification including painting, marking and labelling
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Sundries
Allow for inspection, testing and commissioning including all off-site and factory testing; inspections to demonstrate compliance with relevant specifications and standards; operating the completed installations; submitting all relevant test record sheets at the completion of the installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Sundries
Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed installation
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Sundries
Allow for providing spares for the Mechanical Engineering Installation
REVIEWAmount column prints "Deleted as per Add - 07" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00Deleted as per Add - 07Needs review
Sundries
Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for planning and coordinating with relevant statutory authorities and with all other trades
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for liaison with obtaining approvals and attendance on approved Authorities, other statutory bodies and service providers as required
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for all incidental work including factory finishing, fixing to all backgrounds by appropriate means and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for supplying and fixing all brackets, clamps and other fixing devices including building in or cutting and pinning and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for training the Employer's Staff to operate and maintain the Mechanical Engineering Installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for all incidental work to the Mechanical Engineering Installations where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Builders work in connection (BWIC) with Mechanical Engineering Installations
Allow for all BWIC with Mechanical Engineering Installations where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for all connections to existing services mains
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for earthing and bonding as specified; in particular all ductwork systems shall be provided with earth continuity protection at all joints
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for all supports, fixings, anchors, insulating blocks and anti-vibration devices where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for all identification including painting, marking and labeling, including labeling all valves
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for flushing, cleaning, sterilization and chlorination of the completed installations as necessary
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for inspection, testing and commissioning including all off-site and factory testing; inspections to demonstrate compliance with relevant specifications and standards; operating the completed installations; submitting all relevant test record sheets at the completion of the installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Allow for vibration and noise control where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for planning and coordinating with relevant statutory authorities and with all other trades
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for liaison with obtaining approvals and attendance on DEWA, other statutory bodies and service providers as required
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for marking the positions of and cutting or forming holes, mortices, chases or the like and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for supplying and fixing all sleeves, frames and built-in fire stoppers for building into concrete structures and masonry walls
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for supplying and fixing all brackets, clamps and other fixing devices including building in or cutting and pinning and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for fire stopping all pipes, ducts and the like at penetrations through fire walls and other structures and making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for all incidental work including factory finishing, fixing to all backgrounds by appropriate means and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for all protective painting including removing protective coatings or wrappings and cleaning exposed surfaces for Mechanical installations.
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for all decorative painting including removing protective coatings or wrappings and cleaning and polishing exposed surfaces for Mechanical installations.
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for training the Employer's Staff to operate and maintain the Mechanical Engineering Installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for all incidental work to the Mechanical Engineering Installations where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Section 2/R · SECTION R - ELECTRICAL INSTALLATIONS · Page 2/R/1 - 2/R/177
0/270 clear
0.00 Σ lines
4C x 16mm² XLPE/SWA/LSOH + 1C x 16mm² ECC
From SMDB-T1-GF-LV01 to 40A TP isolator for signage (ISO-T1-GF-SIGNAGE)
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
4C x 16mm² XLPE/SWA/LSOH + 1C x 16mm² ECC
From SMDB-T1-GF-LV01 to 40A TP isolator for signage (ISO-T3-GF-SIGNAGE)
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
4C x 16mm² XLPE/SWA/LSOH + 1C x 16mm² ECC
From SMDB-T4-02-LL01 to DB-T4-02-GYM
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00IncludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to 40A TP isolator at water feature pump room
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to MCC-T1-B1-LL01
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to MCC-T3-B1-LL01
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to MCC-T4-B1-LL01
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to MCC-T2-B2-LL01
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to MCC-T4-B2-LL01
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to SMDB-T3-B1-LL01
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to SMDB-T3-B2-LL01
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to DB-T2-GF-SS-01
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to DB-T3-GF-LL02
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to DB-T2-03-KDCB
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to EDB-T2-GF-ETS
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to EDB-T2-GF-LL02
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to EMCC-T2-GF-FAN-02
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to 40A TP isolator
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to 63A TP isolator
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to SP isolator
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to TPN isolator
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
Cables; including fixings, supports, terminations, accessories and all ancillary works as necessary
From power supply to SMDB-T3-GF-LL01
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0Item0.000.00ExcludedNeeds review
loading more… 150 of 605 lines rendered

What the bidder did with the line

Read from the source. Every line sits in exactly one of these.
StateLinesMeasuredMoney
PricedA rate in the source and money in the amount.6,5327,145,276.232,710,720,000.00
UnpricedNo rate given, nothing carried into the totals.100
Prints words, not a figure“By Others”, “Included” — counted as nil, as the bidder's own page total does.50716,478
Priced as a wholeMoney on the line with no rate behind it — a lump or provisional sum.44,950,000.00

Where your review stands

Your review of those same lines — a line can be in more than one.
StateLinesMeasuredMoney
Still openCarries a question nobody has answered yet.60517,291460,520.73
ConfirmedYou checked it; the finding stands and left the queue.0
RuledA recorded determination answers it — reversible at any time.0
Does not reconcileAn error on the line itself, not on its block.0

Collection blocks

Σ of each block’s line amounts against the total the source itself prints.
BlockSectionLinesΣ linesSource printsTies
GR1/1GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS30.000.00
GR1/2GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS90.000.00
GR1/3GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS10.000.00
GR1/4GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS50.000.00
GR1/5GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS70.000.00
GR1/6GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS160.000.00
GR1/7GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS110.000.00
GR1/8GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS40.000.00
GR1/9GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS12324,986,009.87324,986,009.87
GR1/10GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS90.000.00
GR1/11GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS30.000.00
GR1/12GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS140.000.00
GR1/13GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS170.000.00
GR1/14GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS10.000.00
GR1/15GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS10.000.00
2 - Main/1SITE PREPARATION64,694,535.104,694,535.10
2 - Main/2BORED PILING62,760,886.932,760,886.93
2 - Main/3GENERALLY10.000.00
2 - Main/4POURED CONCRETE1914,630,648.0114,630,648.01
2 - Main/5POURED CONCRETE2028,966,030.0728,966,030.07
2 - Main/6POURED CONCRETE2342,482,847.8842,482,847.88
2 - Main/7POURED CONCRETE6384,028.76384,028.76
2 - Main/8REINFORCEMENT22212,851,833.88212,851,833.88
2 - Main/9REINFORCEMENT61,194,050.761,194,050.76
2 - Main/10SHUTTERING2089,097,434.5689,097,434.56
2 - Main/11SHUTTERING41,930,331.411,930,331.41
2 - Main/12PRESTRESSED CONCRETE4121,983,430.62121,983,430.62
2 - Main/13SUNDRIES56,446,426.826,446,426.82
2 - Main/14GENERALLY10.000.00
2 - Main/15WALL AND PIERS1137,543,197.8437,543,197.84
2 - Main/16SUNDRIES40.000.00
2 - Main/17GENERALLY10.000.00
2 - Main/18STRUCTURAL METALWORK183,370,022.663,370,022.66
2 - Main/19STRUCTURAL METALWORK51,532,761.571,532,761.57
2 - Main/20NON-STRUCTURAL METALWORK571,495,384.7171,495,384.71
2 - Main/21NON-STRUCTURAL METALWORK1410,887,649.8810,887,649.88
2 - Main/22NON-STRUCTURAL METALWORK1677,999,377.2877,999,377.28
2 - Main/23NON-STRUCTURAL METALWORK2064,513,628.2164,513,628.21
2 - Main/24NON-STRUCTURAL METALWORK1575,013,752.3775,013,752.37
2 - Main/25NON-STRUCTURAL METALWORK124,164,955.344,164,955.34
2 - Main/26NON-STRUCTURAL METALWORK9948,552.05948,552.05
2 - Main/27NON-STRUCTURAL METALWORK122,522,676.602,522,676.60
2 - Main/28GENERALLY27,333,454.487,333,454.48
2 - Main/29COMPOSITE ITEMS125,196,859.855,196,859.85
2 - Main/30COMPOSITE ITEMS142,785,344.772,785,344.77
2 - Main/31COMPOSITE ITEMS131,401,510.441,401,510.44
2 - Main/32COMPOSITE ITEMS204,012,755.104,012,755.10
2 - Main/33COMPOSITE ITEMS163,471,753.713,471,753.71
2 - Main/34COMPOSITE ITEMS182,655,633.842,655,633.84
2 - Main/35COMPOSITE ITEMS181,374,998.081,374,998.08
2 - Main/36COMPOSITE ITEMS19965,532.16965,532.16
2 - Main/37COMPOSITE ITEMS1724,678,538.8424,678,538.84
2 - Main/38COMPOSITE ITEMS1621,315,257.1721,315,257.17
2 - Main/39COMPOSITE ITEMS91,721,713.981,721,713.98
2 - Main/40COMPOSITE ITEMS1641,182,223.0741,182,223.07
2 - Main/41COMPOSITE ITEMS2148,367,012.7248,367,012.72
2 - Main/42COMPOSITE ITEMS1815,308,044.0515,308,044.05
2 - Main/43COMPOSITE ITEMS182,168,330.922,168,330.92
2 - Main/44COMPOSITE ITEMS16567,561.44567,561.44
2 - Main/45COMPOSITE ITEMS132,533,199.742,533,199.74
2 - Main/46COMPOSITE ITEMS1554,574.9454,574.94
2 - Main/47COMPOSITE ITEMS12169,928.36169,928.36
2 - Main/48COMPOSITE ITEMS14565,053.77565,053.77
2 - Main/49COMPOSITE ITEMS91,542,323.641,542,323.64
2 - Main/50COMPOSITE ITEMS14862,548.77862,548.77
2 - Main/51COMPOSITE ITEMS13454,605.63454,605.63
2 - Main/52GENERALLY10.000.00
2 - Main/53COVERS AND LININGS920,756,773.0720,756,773.07
2 - Main/54DAMP-PROOF COURSES41,331,955.011,331,955.01
2 - Main/55INSULATION47,325,817.567,325,817.56
2 - Main/56GENERALLY10.000.00
2 - Main/57DOORS1336,287,754.8836,287,754.88
2 - Main/58DOORS168,020,178.058,020,178.05
2 - Main/59DOORS1617,819,916.4717,819,916.47
2 - Main/60DOORS203,067,847.043,067,847.04
2 - Main/61SCREENS161,721,885.531,721,885.53
2 - Main/62EXTERNAL DOORS12221,254.93221,254.93
2 - Main/63EXTERNAL DOORS121,401,325.441,401,325.44
2 - Main/64SCREENS18105,403,018.11105,403,018.11
2 - Main/65SCREENS184,210,676.704,210,676.70
2 - Main/66SCREENS1618,171,691.0418,171,691.04
2 - Main/67SCREENS131,654,722.981,654,722.98
2 - Main/68SCREENS1443,636,222.6343,636,222.63
2 - Main/69LOUVERS147,364,189.657,364,189.65
2 - Main/70IRONMONGERY21691,637.90691,637.90
2 - Main/71IRONMONGERY14158,817.26158,817.26
2 - Main/72GENERALLY10.000.00
2 - Main/73BACKGROUNDS1753,017,306.1453,017,306.14
2 - Main/74BACKGROUNDS63,433,401.483,433,401.48
2 - Main/75FLOOR FINISHES14113,728,384.32113,728,384.32
2 - Main/76FLOOR FINISHES142,029,098.842,029,098.84
2 - Main/77FLOOR FINISHES9705,281.33705,281.33
2 - Main/78FLOOR FINISHES87,656,271.967,656,271.96
2 - Main/79WALL FINISHES1428,123,980.7328,123,980.73
2 - Main/80WALL FINISHES119,312,354.609,312,354.60
2 - Main/81CEILING FINISHES61,616,507.241,616,507.24
2 - Main/82SUNDRIES72,295,427.332,295,427.33
2 - Main/83SUSPENDED CEILING1612,723,276.6912,723,276.69
2 - Main/84SUSPENDED CEILING166,157,676.126,157,676.12
2 - Main/85SUSPENDED CEILING185,835,876.015,835,876.01
2 - Main/86DECORATIONS1226,708,376.2126,708,376.21
2 - Main/87DECORATIONS1217,996,861.2517,996,861.25
2 - Main/88SIGNWRITING143,149,593.243,149,593.24
2 - Main/89GENERALLY43,507,301.353,507,301.35
2 - Main/90TOILET ACCESSORIES20150,969.21150,969.21
2 - Main/91TOILET ACCESSORIES213,572,412.203,572,412.20
2 - Main/92KITCHEN ACCESSORIES71,083,007.141,083,007.14
2 - Main/93SIGNAGE AND WAYFINDING201,745,459.191,745,459.19
2 - Main/94SIGNAGE AND WAYFINDING221,669,070.361,669,070.36
2 - Main/95PARKING ACCESSORIES13553,728.17553,728.17
2 - Main/96PARKING ACCESSORIES3279,068.34279,068.34
2 - Main/97PARTITIONS1526,925,215.5126,925,215.51
2 - Main/98PARTITIONS126,004,024.976,004,024.97
2 - Main/99TOILET PARTITION206,069,383.146,069,383.14
2 - Main/100TOILET PARTITION123,434,462.473,434,462.47
2 - Main/101WASTE CHUTES104,413,199.214,413,199.21
2 - Main/102GENERALLY10.000.00
2 - Main/103WHITE GOODS1818,525,978.0018,525,978.00
2 - Main/104GYM EQUIPMENT250.000.00
2 - Main/105BUILDING MANAGEMENT UNIT (BMU)310,726,004.9910,726,004.99
2 - Main/106BUILDING MANAGEMENT UNIT (BMU)81,794,248.701,794,248.70
2 - Main/107BUILDING MANAGEMENT UNIT (BMU)81,470,428.351,470,428.35
2 - Main/108GENERALLY10.000.00
2 - Main/109LOOSE FF&E220.000.00
2 - Main/110LOOSE FF&E210.000.00
2 - Main/111LOOSE FF&E240.000.00
2 - Main/112LOOSE FF&E200.000.00
2 - Main/113LOOSE FF&E15650,477.25650,477.25
2 - Main/114GENERALLY10.000.00
2 - Main/115LIFTS80.000.00
2 - Main/116LIFTS823,652,280.4823,652,280.48
2 - Main/117LIFTS629,305,752.3829,305,752.38
2 - Main/118LIFTS23,230,555.383,230,555.38
2 - Main/119SUNDRIES40.000.00
2 - Main/120BWIC61,123,771.761,123,771.76
2 - Main/121GENERALLY10.000.00
2 - Main/122SANITARY FIXTURES & FITTINGS162,331,889.002,331,889.00
2 - Main/123SANITARY FIXTURES & FITTINGS1610,087,556.0010,087,556.00
2 - Main/124SANITARY FIXTURES & FITTINGS153,072,907.123,072,907.12
2 - Main/125SANITARY FIXTURES & FITTINGS122,909,787.002,909,787.00
2 - Main/126SANITARY FIXTURES & FITTINGS80.000.00
2 - Main/127DRAINAGE INSTALLATION183,255,545.003,255,545.00
2 - Main/128DRAINAGE INSTALLATION161,859,642.281,859,642.28
2 - Main/129DRAINAGE INSTALLATION9970,960.00970,960.00
2 - Main/130DRAINAGE INSTALLATION171,200,868.001,200,868.00
2 - Main/131DRAINAGE INSTALLATION157,395,391.007,395,391.00
2 - Main/132DRAINAGE INSTALLATION173,126,322.003,126,322.00
2 - Main/133DRAINAGE INSTALLATION151,791,616.001,791,616.00
2 - Main/134DRAINAGE INSTALLATION10214,245.81214,245.81
2 - Main/135DRAINAGE INSTALLATION10210,803.00210,803.00
2 - Main/136DRAINAGE INSTALLATION11366,346.77366,346.77
2 - Main/137DRAINAGE INSTALLATION2159,253.00159,253.00
2 - Main/138WATER INSTALLATION196,284,720.006,284,720.00
2 - Main/139WATER INSTALLATION152,364,103.002,364,103.00
2 - Main/140WATER INSTALLATION123,509,187.603,509,187.60
2 - Main/141WATER INSTALLATION18877,503.00877,503.00
2 - Main/142WATER INSTALLATION16210,365.00210,365.00
2 - Main/143WATER INSTALLATION153,238,943.003,238,943.00
2 - Main/144WATER INSTALLATION82,111,683.002,111,683.00
2 - Main/145WATER INSTALLATION7702,945.00702,945.00
2 - Main/146WATER INSTALLATION8467,030.00467,030.00
2 - Main/147WATER INSTALLATION5161,357.00161,357.00
2 - Main/148FIRE PROTECTION SYSTEM59,185,815.009,185,815.00
2 - Main/149FIRE PROTECTION SYSTEM1717,754,337.0017,754,337.00
2 - Main/150FIRE PROTECTION SYSTEM215,196,104.005,196,104.00
2 - Main/151FIRE PROTECTION SYSTEM112,711,841.002,711,841.00
2 - Main/152FIRE PROTECTION SYSTEM75,407,910.005,407,910.00
2 - Main/153FIRE PROTECTION SYSTEM101,729,692.001,729,692.00
2 - Main/154FIRE PROTECTION SYSTEM958,060.0058,060.00
2 - Main/155FIRE PROTECTION SYSTEM101,647,932.001,647,932.00
2 - Main/156FIRE PROTECTION SYSTEM5580,168.00580,168.00
2 - Main/157HVAC INSTALLATION1613,942,116.0013,942,116.00
2 - Main/158HVAC INSTALLATION163,820,783.003,820,783.00
2 - Main/159HVAC INSTALLATION1810,518,883.0010,518,883.00
2 - Main/160HVAC INSTALLATION136,454,809.006,454,809.00
2 - Main/161HVAC INSTALLATION79,756,634.009,756,634.00
2 - Main/162HVAC INSTALLATION72,947,775.002,947,775.00
2 - Main/163HVAC INSTALLATION13730,856.00730,856.00
2 - Main/164HVAC INSTALLATION914,592,063.8014,592,063.80
2 - Main/165HVAC INSTALLATION22122,621.00122,621.00
2 - Main/166HVAC INSTALLATION21120,785.00120,785.00
2 - Main/167HVAC INSTALLATION21811,787.00811,787.00
2 - Main/168HVAC INSTALLATION22271,272.00271,272.00
2 - Main/169HVAC INSTALLATION17166,869.00166,869.00
2 - Main/170HVAC INSTALLATION21505,706.00505,706.00
2 - Main/171HVAC INSTALLATION2264,033.0064,033.00
2 - Main/172HVAC INSTALLATION20168,877.00168,877.00
2 - Main/173HVAC INSTALLATION22381,127.00381,127.00
2 - Main/174HVAC INSTALLATION2229,979.0029,979.00
2 - Main/175HVAC INSTALLATION15629,020.00629,020.00
2 - Main/176HVAC INSTALLATION21748,272.00748,272.00
2 - Main/177HVAC INSTALLATION20733,897.00733,897.00
2 - Main/178HVAC INSTALLATION14474,471.00474,471.00
2 - Main/179HVAC INSTALLATION1446,016.0046,016.00
2 - Main/180HVAC INSTALLATION1458,340.0058,340.00
2 - Main/181HVAC INSTALLATION1436,413.0036,413.00
2 - Main/182HVAC INSTALLATION1441,640.0041,640.00
2 - Main/183HVAC INSTALLATION1438,546.0038,546.00
2 - Main/184HVAC INSTALLATION14355,812.00355,812.00
2 - Main/185HVAC INSTALLATION14757,416.00757,416.00
2 - Main/186HVAC INSTALLATION14212,346.00212,346.00
2 - Main/187HVAC INSTALLATION1435,720.0035,720.00
2 - Main/188HVAC INSTALLATION1433,372.0033,372.00
2 - Main/189HVAC INSTALLATION1432,945.0032,945.00
2 - Main/190HVAC INSTALLATION14431,779.00431,779.00
2 - Main/191HVAC INSTALLATION14525,719.00525,719.00
2 - Main/192HVAC INSTALLATION1435,827.0035,827.00
2 - Main/193HVAC INSTALLATION14132,590.00132,590.00
2 - Main/194HVAC INSTALLATION14113,659.00113,659.00
2 - Main/195HVAC INSTALLATION1445,804.0045,804.00
2 - Main/196HVAC INSTALLATION1482,731.0082,731.00
2 - Main/197HVAC INSTALLATION1432,038.0032,038.00
2 - Main/198HVAC INSTALLATION1439,720.0039,720.00
2 - Main/199HVAC INSTALLATION1448,791.0048,791.00
2 - Main/200HVAC INSTALLATION1449,220.0049,220.00
2 - Main/201HVAC INSTALLATION14708,395.00708,395.00
2 - Main/202HVAC INSTALLATION14689,784.00689,784.00
2 - Main/203HVAC INSTALLATION1433,586.0033,586.00
2 - Main/204HVAC INSTALLATION1434,495.0034,495.00
2 - Main/205HVAC INSTALLATION1434,438.0034,438.00
2 - Main/206HVAC INSTALLATION1440,096.0040,096.00
2 - Main/207HVAC INSTALLATION14512,624.00512,624.00
2 - Main/208HVAC INSTALLATION14333,826.00333,826.00
2 - Main/209HVAC INSTALLATION1432,999.0032,999.00
2 - Main/210HVAC INSTALLATION1431,132.0031,132.00
2 - Main/211HVAC INSTALLATION1442,336.0042,336.00
2 - Main/212HVAC INSTALLATION1443,087.0043,087.00
2 - Main/213HVAC INSTALLATION1436,787.0036,787.00
2 - Main/214HVAC INSTALLATION1432,787.0032,787.00
2 - Main/215HVAC INSTALLATION1439,346.0039,346.00
2 - Main/216HVAC INSTALLATION1436,093.0036,093.00
2 - Main/217HVAC INSTALLATION1442,599.0042,599.00
2 - Main/218HVAC INSTALLATION1441,374.0041,374.00
2 - Main/219HVAC INSTALLATION1447,883.0047,883.00
2 - Main/220HVAC INSTALLATION1452,311.0052,311.00
2 - Main/221HVAC INSTALLATION14250,022.00250,022.00
2 - Main/222HVAC INSTALLATION1448,364.0048,364.00
2 - Main/223HVAC INSTALLATION1433,692.0033,692.00
2 - Main/224HVAC INSTALLATION1437,053.0037,053.00
2 - Main/225HVAC INSTALLATION1451,882.0051,882.00
2 - Main/226HVAC INSTALLATION1434,920.0034,920.00
2 - Main/227HVAC INSTALLATION14693,607.00693,607.00
2 - Main/228HVAC INSTALLATION14585,813.00585,813.00
2 - Main/229HVAC INSTALLATION1433,159.0033,159.00
2 - Main/230HVAC INSTALLATION1431,131.0031,131.00
2 - Main/231HVAC INSTALLATION1432,303.0032,303.00
2 - Main/232HVAC INSTALLATION1428,997.0028,997.00
2 - Main/233HVAC INSTALLATION14482,543.00482,543.00
2 - Main/234HVAC INSTALLATION14701,116.00701,116.00
2 - Main/235HVAC INSTALLATION1450,128.0050,128.00
2 - Main/236HVAC INSTALLATION1430,812.0030,812.00
2 - Main/237HVAC INSTALLATION1438,814.0038,814.00
2 - Main/238HVAC INSTALLATION1436,199.0036,199.00
2 - Main/239HVAC INSTALLATION1456,741.0056,741.00
2 - Main/240HVAC INSTALLATION1436,360.0036,360.00
2 - Main/241HVAC INSTALLATION1443,080.0043,080.00
2 - Main/242HVAC INSTALLATION1439,881.0039,881.00
2 - Main/243HVAC INSTALLATION1443,989.0043,989.00
2 - Main/244HVAC INSTALLATION1437,054.0037,054.00
2 - Main/245HVAC INSTALLATION14358,930.00358,930.00
2 - Main/246HVAC INSTALLATION14818,928.00818,928.00
2 - Main/247HVAC INSTALLATION14256,948.00256,948.00
2 - Main/248HVAC INSTALLATION14203,760.00203,760.00
2 - Main/249HVAC INSTALLATION1426,171.0026,171.00
2 - Main/250HVAC INSTALLATION1438,973.0038,973.00
2 - Main/251HVAC INSTALLATION14225,511.00225,511.00
2 - Main/252HVAC INSTALLATION14480,208.00480,208.00
2 - Main/253HVAC INSTALLATION1497,189.0097,189.00
2 - Main/254HVAC INSTALLATION1429,906.0029,906.00
2 - Main/255HVAC INSTALLATION1440,414.0040,414.00
2 - Main/256HVAC INSTALLATION1435,987.0035,987.00
2 - Main/257HVAC INSTALLATION1437,481.0037,481.00
2 - Main/258HVAC INSTALLATION1444,788.0044,788.00
2 - Main/259HVAC INSTALLATION1442,654.0042,654.00
2 - Main/260HVAC INSTALLATION111,360,500.001,360,500.00
2 - Main/261HVAC INSTALLATION1211,977,935.4011,977,935.40
2 - Main/262HVAC INSTALLATION18239,819.00239,819.00
2 - Main/263HVAC INSTALLATION2224,220.0024,220.00
2 - Main/264HVAC INSTALLATION2225,959.0025,959.00
2 - Main/265HVAC INSTALLATION2220,528.0020,528.00
2 - Main/266HVAC INSTALLATION21164,437.00164,437.00
2 - Main/267HVAC INSTALLATION2224,420.0024,420.00
2 - Main/268HVAC INSTALLATION2221,872.0021,872.00
2 - Main/269HVAC INSTALLATION2219,799.0019,799.00
2 - Main/270HVAC INSTALLATION2018,730.0018,730.00
2 - Main/271HVAC INSTALLATION17164,717.00164,717.00
2 - Main/272HVAC INSTALLATION2053,548.0053,548.00
2 - Main/273HVAC INSTALLATION1815,789.0015,789.00
2 - Main/274HVAC INSTALLATION58,439.008,439.00
2 - Main/275HVAC INSTALLATION835,610.0035,610.00
2 - Main/276HVAC INSTALLATION1514,204,629.0014,204,629.00
2 - Main/277HVAC INSTALLATION20383,142.00383,142.00
2 - Main/278HVAC INSTALLATION21335,287.00335,287.00
2 - Main/279HVAC INSTALLATION22133,747.00133,747.00
2 - Main/280HVAC INSTALLATION20240,549.00240,549.00
2 - Main/281HVAC INSTALLATION14823,209.00823,209.00
2 - Main/282HVAC INSTALLATION17174,059.00174,059.00
2 - Main/283HVAC INSTALLATION12907,037.00907,037.00
2 - Main/284HVAC INSTALLATION13910,502.00910,502.00
2 - Main/285HVAC INSTALLATION13944,146.00944,146.00
2 - Main/286HVAC INSTALLATION11226,151.00226,151.00
2 - Main/287HVAC INSTALLATION13118,100.00118,100.00
2 - Main/288HVAC INSTALLATION14249,675.00249,675.00
2 - Main/289HVAC INSTALLATION12161,940.00161,940.00
2 - Main/290HVAC INSTALLATION769,465.0069,465.00
2 - Main/291LPG INSTALLATION11,135,848.001,135,848.00
2 - Main/292LPG INSTALLATION10971,914.00971,914.00
2 - Main/293LPG INSTALLATION142,903,254.002,903,254.00
2 - Main/294LPG INSTALLATION5384,681.00384,681.00
2 - Main/295SUNDRIES90.000.00
2 - Main/296SUNDRIES10.000.00
2 - Main/297WORK INCIDENTAL AND BWIC90.000.00
2 - Main/298WORK INCIDENTAL AND BWIC313,389,780.1213,389,780.12
2 - Main/299GENERALLY31,184,253.001,184,253.00
2 - Main/300POWER INSTALLATION647,646.0047,646.00
2 - Main/301POWER INSTALLATION16107,264.00107,264.00
2 - Main/302POWER INSTALLATION1379,630.0079,630.00
2 - Main/303POWER INSTALLATION15351,348.00351,348.00
2 - Main/304POWER INSTALLATION16478,860.00478,860.00
2 - Main/305POWER INSTALLATION10113,790.00113,790.00
2 - Main/306POWER INSTALLATION10232,947.00232,947.00
2 - Main/307POWER INSTALLATION13498,754.00498,754.00
2 - Main/308POWER INSTALLATION11304,274.00304,274.00
2 - Main/309POWER INSTALLATION1423,128.0023,128.00
2 - Main/310POWER INSTALLATION1233,852.0033,852.00
2 - Main/311POWER INSTALLATION1576,132.0076,132.00
2 - Main/312POWER INSTALLATION2191,437.0091,437.00
2 - Main/313POWER INSTALLATION2261,439.0061,439.00
2 - Main/314POWER INSTALLATION2277,787.0077,787.00
2 - Main/315POWER INSTALLATION2250,183.0050,183.00
2 - Main/316POWER INSTALLATION21112,292.00112,292.00
2 - Main/317POWER INSTALLATION14334,665.00334,665.00
2 - Main/318POWER INSTALLATION1579,998.0079,998.00
2 - Main/319POWER INSTALLATION17179,024.00179,024.00
2 - Main/320POWER INSTALLATION17232,021.00232,021.00
2 - Main/321POWER INSTALLATION15290,244.00290,244.00
2 - Main/322POWER INSTALLATION15200,799.00200,799.00
2 - Main/323POWER INSTALLATION16131,052.00131,052.00
2 - Main/324POWER INSTALLATION16241,267.00241,267.00
2 - Main/325POWER INSTALLATION19111,287.00111,287.00
2 - Main/326POWER INSTALLATION14308,535.00308,535.00
2 - Main/327POWER INSTALLATION17129,243.00129,243.00
2 - Main/328POWER INSTALLATION16155,172.00155,172.00
2 - Main/329POWER INSTALLATION14274,097.00274,097.00
2 - Main/330POWER INSTALLATION18104,520.00104,520.00
2 - Main/331POWER INSTALLATION14276,241.00276,241.00
2 - Main/332POWER INSTALLATION18210,648.00210,648.00
2 - Main/333POWER INSTALLATION16267,062.00267,062.00
2 - Main/334POWER INSTALLATION14151,877.00151,877.00
2 - Main/335POWER INSTALLATION14102,330.00102,330.00
2 - Main/336POWER INSTALLATION1272,810.0072,810.00
2 - Main/337POWER INSTALLATION11140,580.00140,580.00
2 - Main/338POWER INSTALLATION13127,530.00127,530.00
2 - Main/339POWER INSTALLATION14104,490.00104,490.00
2 - Main/340POWER INSTALLATION1488,290.0088,290.00
2 - Main/341POWER INSTALLATION15114,834.00114,834.00
2 - Main/342POWER INSTALLATION15118,762.00118,762.00
2 - Main/343POWER INSTALLATION13158,137.00158,137.00
2 - Main/344POWER INSTALLATION14154,155.00154,155.00
2 - Main/345POWER INSTALLATION13384,856.00384,856.00
2 - Main/346POWER INSTALLATION14273,944.00273,944.00
2 - Main/347POWER INSTALLATION11452,888.00452,888.00
2 - Main/348POWER INSTALLATION1441,933.0041,933.00
2 - Main/349POWER INSTALLATION1436,099.0036,099.00
2 - Main/350POWER INSTALLATION1437,737.0037,737.00
2 - Main/351POWER INSTALLATION1760,251.0060,251.00
2 - Main/352POWER INSTALLATION2149,704.0049,704.00
2 - Main/353POWER INSTALLATION2079,876.0079,876.00
2 - Main/354POWER INSTALLATION2098,876.0098,876.00
2 - Main/355POWER INSTALLATION2096,368.0096,368.00
2 - Main/356POWER INSTALLATION1669,776.0069,776.00
2 - Main/357POWER INSTALLATION19172,700.00172,700.00
2 - Main/358POWER INSTALLATION1389,900.0089,900.00
2 - Main/359POWER INSTALLATION1588,500.0088,500.00
2 - Main/360POWER INSTALLATION14445,920.00445,920.00
2 - Main/361POWER INSTALLATION13895,074.00895,074.00
2 - Main/362POWER INSTALLATION101,064,396.001,064,396.00
2 - Main/363POWER INSTALLATION104,799,464.004,799,464.00
2 - Main/364POWER INSTALLATION152,132,897.002,132,897.00
2 - Main/365POWER INSTALLATION220.000.00
2 - Main/366POWER INSTALLATION170.000.00
2 - Main/367POWER INSTALLATION170.000.00
2 - Main/368POWER INSTALLATION160.000.00
2 - Main/369POWER INSTALLATION160.000.00
2 - Main/370POWER INSTALLATION180.000.00
2 - Main/371POWER INSTALLATION15804,950.00804,950.00
2 - Main/372POWER INSTALLATION1416,085,880.0016,085,880.00
2 - Main/373POWER INSTALLATION1611,307,939.0011,307,939.00
2 - Main/374POWER INSTALLATION182,142,426.002,142,426.00
2 - Main/375POWER INSTALLATION22207,626.00207,626.00
2 - Main/376POWER INSTALLATION22202,361.00202,361.00
2 - Main/377POWER INSTALLATION22247,736.00247,736.00
2 - Main/378POWER INSTALLATION22201,723.00201,723.00
2 - Main/379POWER INSTALLATION22190,128.00190,128.00
2 - Main/380POWER INSTALLATION22183,915.00183,915.00
2 - Main/381POWER INSTALLATION20188,760.00188,760.00
2 - Main/382POWER INSTALLATION22207,157.00207,157.00
2 - Main/383POWER INSTALLATION22159,666.00159,666.00
2 - Main/384POWER INSTALLATION22207,636.00207,636.00
2 - Main/385POWER INSTALLATION22205,987.00205,987.00
533 blocks · 1 do not tie2,715,670,000.00

Source verification

Independent checks of the imported result against the raw workbook.
item count
Independent re-count matches on all 4 sheets (7323 items).
qty integrity
Quantity sums match the raw cells on every sheet.
amount integrity
Amount sums match the raw cells on every sheet.
row coverage
1 unaccounted row: Bill 4 row 16: 10000 "Builders work for Workforce Productivity"
mirror
Cell-for-cell fidelity: descriptions, codes, and the number/text/empty state of every qty, rate and amount match the raw cells (29292 cells compared).
summary map
2 summary sheets, 2 entries: 2 matched to imported totals · imported but absent from every summary: 2 - Main, 3 - Ext, Bill 4
summary self check
The workbook's own summaries are internally consistent (5 checks across 3 sheets).
section tie
25/27 declared sections tie to the cent · declared but not in this import: 1/GR “GENERAL REQUIREMENTS FOR THE WHOLE OF TH” declared 324986009.87; 4/PS “PROVISIONAL SUMS” declared 4960000.00 · 117 lines carry no section reference
zone tie
band identified arithmetically as BASEMENTS · GF & PODIUM · TOWER 1 · TOWER 2 · TOWER 3 · TOWER 4 (the identity held on 385/385 sampled priced rows) · 150/150 declared zone cells tie · the bidder keeps their own check on 7194 rows: we agree on 6696, differ on 2 (493 not comparable because the Amount cell prints words — their formula compares a number against text, which Excel makes FALSE whatever the arithmetic; 3 because a zone cell prints words)
tender tie
Declared tender 2715680000.00 − this import 2715670000.00 = 10000.00. Declared scopes absent from this import come to 329946009.87 (1/GR, 4/PS), so this import holds 329936009.87 MORE than the summary declares — imported sheets the summary never names: Bill 4.
amount in words
The words say 1715680000.00 but the sheet prints 2715680000.00: “…TWO BILLION SEVEN HUNDRED AND FIFTEEN MILLION SIX HUNDRED AND EIGHTY THOUSAND DIRHAMS ONL”
summary echo
3/4 sheet totals re-stated verbatim by the workbook's own summary sheets (missing: Bill 4)
3 unresolved errors7,323 lines · 533 blocks · 2,715,670,000.00 AED
/ find move editEsc close