Bill total
2,537,676,914.00
+0.01 vs qty×rate
Needs review
807
90%
1 error · 806 to acknowledge
Reconciliation
Totals reconcile
LINEPAGESECTIONZONEBILLSUMMARY
Source verification
12/12
independent proofs against the raw file
Size
8,256
533 collection blocks · 4 sheets
1 line carries no item reference, though every other line on its page does
errorEither the reference was missed in the source, or the row is not an item.
SECTION L - EQUIPMENT 1
- Supply and installation by Others: Contractor to allow for Co-ordination, attendance and builders work
586 lines print words where a figure belongs
to answerAccept the wording as a class, or put it to the bidder.
SECTION R - ELECTRICAL INSTALLATIONS 264SECTION N - SPECIAL CONSTRUCTION 150SECTION Q - MECHANICAL ENGINEERING INSTALLATIONS 96— 32+9 more sections
- Where any item, clause or sub-clause of the General Requirements has not been priced, it will be deemed that the value of such item, clause or sub-clause is included in the rates for measured items elsewhere in the Bills of Quantities.
- The rates and prices in these Bills of Quantities are fixed for the duration of the Contract and shall not be subject to any adjustment in respect of rise or fall in the cost of labour, materials, plant, equipment, transport or any other matters affecting the cost of execution of the Contract.
- References hereunder to the Schedule of Project Requirements (SOPR) are intended solely to direct the Contractor to the specific requirements of the Schedule of Project Requirements in respect of a particular item and do not in any way limit the scope of such item to the requirements of the Schedule of Project Requirements.
209 lines carry no rate, so nothing reaches the totals
to answerSay why the bidder left them unpriced, or ask them to price them.
SECTION M - FURNISHING 101SECTION L - EQUIPMENT 40SECTION R - ELECTRICAL INSTALLATIONS 10SECTION F - WOOD WORK 9+22 more sections
- Any items that may not be covered elsewhere in the Bills of Quantities which the Tenderer deemed to be necessary in order to carry out the works in full compliance with the SOPR must be itemised and price below
- Allow for any other works which are not included above and which are required to complete the Site Work in accordance with the Specification and the Drawings (Tenderer to list below):
- Columns
8 lines repeat an item letter already used under the same heading
to answerKept exactly as printed — confirm which line the bidder meant.
SECTION E - METALWORK 8
- Primary Structural Steel (Non Fire Rated) to inaccessible areas on façade (Dummy Balconies) and Canopies Provisional Qty
- Columns; UB 533 x 210 x 82
- Columns; UC 203 x 203 x 60
7 lines have no heading above them while their neighbours do
to answerA governing heading may have been missed when the page was read.
SECTION F - WOOD WORK 3SECTION K - ACCESSORIES 3SECTION B - SITE WORKS 1
- To powder room
- To powder room
- To powder room
1 line restarts its lettering without a new heading
to answerUsually a heading the page prints that was not picked up.
SECTION C - CONCRETE WORKS 1
- Coupling beams
| Item | Description | Qty | Unit | Rate | Amount | State |
|---|---|---|---|---|---|---|
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/1 0/3 clear0.00 Σ lines✓ 0.00 printed | ||||||
Generally Where any item, clause or sub-clause of the General Requirements has not been priced, it will be deemed that the value of such item, clause or sub-clause is included in the rates for measured items elsewhere in the Bills of Quantities.REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
Generally The rates and prices in these Bills of Quantities are fixed for the duration of the Contract and shall not be subject to any adjustment in respect of rise or fall in the cost of labour, materials, plant, equipment, transport or any other matters affecting the cost of execution of the Contract.REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
Generally References hereunder to the Schedule of Project Requirements (SOPR) are intended solely to direct the Contractor to the specific requirements of the Schedule of Project Requirements in respect of a particular item and do not in any way limit the scope of such item to the requirements of the Schedule of Project Requirements.REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/2 0/5 clear0.00 Σ lines | ||||||
A1.1- Schedule of Clauses 4 Contractor's All Risk PolicyREVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —By Employer | Needs review | |
A1.1- Schedule of Clauses 6 Professional Indemnity insuranceREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
A1.1- Schedule of Clauses 7 Third Party liability insuranceREVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —By Employer | Needs review | |
A1.1- Schedule of Clauses 8 Plant and Contractor's Equipment InsuranceREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
A1.1- Schedule of Clauses 9 Motor Vehicle Third Party and Passenger Liability InsuranceREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/3 0/1 clear0.00 Σ lines✓ 0.00 printed | ||||||
A1.1- Schedule of Clauses The Contractor shall price hereunder any special requirements related to the specification clausesREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/4 0/2 clear0.00 Σ lines | ||||||
A3 - Restrictions 4 The Maintenance of existing services on, under or over the SiteREVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Excluded | Needs review | |
A3 - Restrictions 5 The Execution of the Works in the required specific order, sections or phasesREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/5 0/4 clear0.00 Σ lines | ||||||
1 Office for the Contract administrators i. EstablishmentREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
1 Office for the Contract administrators ii. MaintenanceREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
1 Office for the Contract administrators iii. RemovalREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
1 Office for the Contract administrators 5 Transport of workpeopleREVIEWAmount column prints "Included in A5.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A5.1 | Needs review | |
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/9 0/3 clear0.00 Σ lines | ||||||
3 Screens and guardrails i. Establishment (Fixed Charges)REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A4.1 | Needs review | |
3 Screens and guardrails ii. Maintenance (Time Related Charges)REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A4.1 | Needs review | |
3 Screens and guardrails iii. Removal (Fixed Charges)REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A4.1 | Needs review | |
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/11 0/1 clear0.00 Σ lines | ||||||
A8.1 An item shall be given for temporary works including design, which shall include: 3 PumpingREVIEWAmount column prints "Included in Site Works (Bill Nr 2)" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in Site Works (Bill Nr 2) | Needs review | |
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/12 0/5 clear0.00 Σ lines | ||||||
A9.1 An item shall be given for temporary works, which shall include: 5 - Traffic regulationsREVIEWAmount column prints "Included in A8.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A8.1 | Needs review | |
A9.1 An item shall be given for temporary works, which shall include: 7 - Drying the WorksREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
A9.1 An item shall be given for temporary works, which shall include: 8 - Control of noise and pollutionREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
A9.1 An item shall be given for temporary works, which shall include: 9 - All Statutory obligationsREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 4 - Off site storageREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/13 0/8 clear0.00 Σ lines | ||||||
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 6 - Specialist Third Party Testing, Commissioning and CertificationREVIEWAmount column prints "Included in A9.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A9.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 12 - Internet connection requirements on siteREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 13 - Precautions against FireREVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A4.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 15 - Project Health, Safety, Environment and Security GuidelinesREVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A4.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 16 - General cleaning and waste disposal during constructionREVIEWAmount column prints "Included in A9.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A9.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 19 - Contract Spares/Attic stockREVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Excluded | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 20 - As-built drawingsREVIEWAmount column prints "Included in BIM" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in BIM | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 22 - WarrantiesREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/15 0/1 clear0.00 Σ lines✓ 0.00 printed | ||||||
Additional Items Any items that may not be covered elsewhere in the Bills of Quantities which the Tenderer deemed to be necessary in order to carry out the works in full compliance with the SOPR must be itemised and price belowREVIEWThe source prints neither a quantity nor a rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | Item | — | — | Needs review | |
2/B · 2/B/3 · VARIANCE IN QUANTITY · 2 - Main/3 0/1 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Site Work in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
2/C · 2/C/2 · POURED CONCRETE · 2 - Main/5 0/1 clear0.00 Σ lines | ||||||
Reinforced concrete; concrete grade C50/60 ColumnsREVIEW2,734 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2,734 | m3 | — | 0.00 | Needs review | |
2/C · 2/C/3 · POURED CONCRETE · 2 - Main/6 0/2 clear443,352.00 Σ lines | ||||||
Reinforced concrete; concrete grade C56/70 Coupling beamsREVIEWReference sequence restarts at "A" on 2 - Main/6 without a heading change — a governing heading may have been missed above it. | 812 | m3 | 546.00 | 443,352.00 | Needs review | |
Reinforced concrete; concrete grade C70/85 Blade wall; 400mm thickREVIEW1,721 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1,721 | m3 | — | 0.00 | Needs review | |
2/C · 2/C/6 · REINFORCEMENT · 2 - Main/9 0/1 clear0.00 Σ lines | ||||||
Reinforcing steel bars; high yield deformed; grade 60 Planter wallREVIEW8.88 t measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 8.88 | t | — | 0.00 | Needs review | |
2/C · 2/C/9 · PRESTRESSED CONCRETE · 2 - Main/12 0/1 clear0.00 Σ lines | ||||||
Post tensioning (PT) system; comprise of design, approvals including prestressing steel, anchorages, plates, ducts, grouts, protection, accessories and all ancillary works as necessary PT system; to post tensioned slabREVIEWAmount column prints "Please refer ADD items" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 1,425.72 | t | — | —Please refer ADD items | Needs review | |
2/C · 2/C/11 · VARIANCE IN QUANTITY · 2 - Main/14 0/1 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Concrete Work in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
2/D · 2/D/2 · SUNDRIES · 2 - Main/16 0/4 clear0.00 Σ lines✓ 0.00 printed | ||||||
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Dowelled control jointsREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Dowelled control joints (RATE ONLY)REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | m | — | —Rate Only | Needs review | |
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Isolation jointsREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Isolation joints (RATE ONLY)REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | m | — | —Rate Only | Needs review | |
2/D · 2/D/3 · VARIANCE IN QUANTITY · 2 - Main/17 0/1 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Masonry in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
2/E · 2/E/9 · NON-STRUCTURAL METALWORK · 2 - Main/26 0/1 clear0.00 Σ lines | ||||||
Stainless steel ladders to water tanks; type AM-451; wall mounted stainless steel with safety cage; including finishes, frames, supports, fixings, accessories and all ancillary works as necessary Type 2; size 960 x 690 x 10300mm highREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
2/E · 2/E/11 · VARIANCE IN QUANTITY · 2 - Main/28 0/9 clear9,881,318.76 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Metalwork in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | — | Needs review | |
| Primary Structural Steel (Non Fire Rated) to inaccessible areas on façade (Dummy Balconies) and Canopies Provisional Qty REVIEWItem code "ADD" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | 552.04 | t | 19,218.00 | 10,609,104.72 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; UB 533 x 210 x 82REVIEWItem code "A" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -5.69 | t | 21,769.00 | -123,865.61 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; UC 203 x 203 x 60REVIEWItem code "B" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | 4.6 | t | 21,769.00 | 100,137.40 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; CHS 219 x 6.3REVIEWItem code "C" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -0.28 | t | 21,769.00 | -6,095.32 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; SHS 150 x 150 x 6.3REVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -0.44 | t | 21,769.00 | -9,578.36 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; SHS 120 x 120 x 6.3REVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -0.03 | t | 21,769.00 | -653.07 | Needs review | |
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications To ground floor and podium wallsREVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -64 | m2 | 1,133.00 | -72,512.00 | Needs review | |
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications To tower wallsREVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -543 | m2 | 1,133.00 | -615,219.00 | Needs review | |
2/F · 2/F/24 · VARIANCE IN QUANTITY · 2 - Main/52 0/9 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Woodwork in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| Vanity counters; including countertop, forming of holes, front/side panels, drawers, hardware, finishes, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| To powder room REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed. | — | — | — | 0.00 | Needs review | |
| Veneered shelves; including finishes, fixings, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| To powder room REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed. | — | — | — | 0.00 | Needs review | |
| Cabinets with veneered open shelf; including concealed light (measured separately), front/side panels, hardware, finishes, fixings, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| To powder room REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed. | — | — | — | 0.00 | Needs review | |
| Wardrobes; comprising 18mm thick MDF shelving and glass shutter; including MDF backing, carcass, frames, supports, front/side/back panels, doors, shelves, drawers, concealed light (measured separately), hardware, finishes, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
2/G · 2/G/4 · VARIANCE IN QUANTITY · 2 - Main/56 0/1 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Thermal and Moisture Protection in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
2/H · 2/H/16 · VARIANCE IN QUANTITY · 2 - Main/72 0/4 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Doors and Windows in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | — | Needs review | |
| Double glazed vision panel screen; Type V1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | — | Needs review | |
| Double glazed vision panel screen; Type V2; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 8mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | — | Needs review | |
| Double glazed spandrel panel screen; Type S1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, plaster board, insulation, fixings, fittings, accessories and all ancillary works as per drawings and specifications REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | — | Needs review | |
2/J · 2/J/9 · CEILING FINISHES · 2 - Main/81 0/2 clear0.00 Σ lines | ||||||
Gypsum board tile ceiling system; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories Extra over for access panelREVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Not Applicable | Needs review | |
Concealed grid aluminium tile ceiling system; demountable, perforated aluminium tiles; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories Extra over for access panelREVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Not Applicable | Needs review | |
2/J · 2/J/17 · VARIANCE IN QUANTITY · 2 - Main/89 0/1 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Finishes in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
2/K · 2/K/1 · TOILET ACCESSORIES · 2 - Main/90 0/1 clear0.00 Σ lines | ||||||
Common Areas Type SAN-711; toilet paper holderREVIEW9 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 9 | Nr. | — | 0.00 | Needs review | |
2/K · 2/K/5 · SIGNAGE AND WAYFINDING · 2 - Main/94 0/1 clear0.00 Σ lines | ||||||
Internal Signage Retail sign by othersREVIEWAmount column prints "By Others" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 6 | Nr. | — | —By Others | Needs review | |
2/K · 2/K/6 · PARKING ACCESSORIES · 2 - Main/95 0/2 clear0.00 Σ lines | ||||||
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary Type EXH-301; 100mm highREVIEW2,969 m2 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2,969 | m2 | — | 0.00 | Needs review | |
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary 150mm high; to rampsREVIEW609 m measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 609 | m | — | 0.00 | Needs review | |
2/K · 2/K/13 · VARIANCE IN QUANTITY · 2 - Main/102 0/6 clear356,655.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Accessories in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Tempered mirror; type GL-101; 6mm thick clear mirror with metal frame; including, backing, supports, finishes, accessories and all ancillary works as necessary REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | 0.00 | Needs review | |
| Shower glass partition; fixed glass with doors; glass; 10mm thick; including ironmongery, fixings, accessories and all ancillary works as necessary REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | 0.00 | Needs review | |
| Clear Glass REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"Clear Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed. | 0 | — | — | 0.00 | Needs review | |
| Fluted Tinted Glass REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"Fluted Tinted Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed. | 0 | — | — | 0.00 | Needs review | |
| Precast Concrete kerb REVIEW"Precast Concrete kerb" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed. | 2,301 | m | 155.00 | 356,655.00 | Needs review | |
2/L · 2/L/1 · WHITE GOODS · 2 - Main/103 0/9 clear0.00 Σ lines | ||||||
White goods; including accessories and all ancillary works as necessary Type WG-111; freestanding cookerREVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 30 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-112; freestanding fridgeREVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 30 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-113; freestanding freezerREVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 30 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-114; freestanding dishwasherREVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 30 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-116; coffee machineREVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-117; tv screenREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-118; tv screenREVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 5 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-119; water dispenserREVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 8 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-120; tv screenREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
2/L · 2/L/2 · GYM EQUIPMENT · 2 - Main/104 0/26 clear50,850.00 Σ lines✓ 50,850.00 printed1 errors | ||||||
| Supply and installation by Others: Contractor to allow for Co-ordination, attendance and builders work ERRORNo item reference on 2 - Main/104. Every priced line carries a printed reference (A, B, C…) — either the reference was missed, or this row is not an item. | 1 | Item | 50,850.00 | 50,850.00 | Error | |
| Type EQ-101; run 19" excite live REVIEW7 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 7 | Nr. | — | 0.00 | Needs review | |
| Type EQ-102; climb 16" excite live REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-103; synchro ar 16" excite live REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-104; technogym bike REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-105; skillrow REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-106; lower back fitness bench REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
| Type EQ-107; yoga mat REVIEW9 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 9 | Nr. | — | 0.00 | Needs review | |
| Type EQ-108; crunch bench press REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-109; multi-power REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-110; adjustable bench REVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 5 | Nr. | — | 0.00 | Needs review | |
| Type EQ-111; two tier dumbbell rack REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-112; dumbbells (10 pairs) REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-113; dual leg curl/leg extension selection 700 REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-114; lat machine selection 700 REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-115; shoulder press-selection 700 REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-116; chest press-selection 700 REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-117; skill tools storage REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-118; universe wall 2 virtual REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-119; vario 16" excite live REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-120; skill up REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-121; skillmill REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-122; skillrun unity 7000 REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-123; plyobox REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-124; punching bag REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-125; leg press selection 700 REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
2/L · 2/L/3 · BUILDING MANAGEMENT UNIT (BMU) · 2 - Main/105 0/1 clear0.00 Σ lines | ||||||
Galvanized mild steel running track; including galvanized steel base plates, clip ears, stainless steel A4/80 u-bolts, high-strength grout, fixings; complete BMU tracks at 4000mm center to centerREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 183 | m | — | —Included | Needs review | |
| loading more… 150 of 807 lines rendered | ||||||
| Item | Description | Qty | Unit | Rate | Amount | State |
|---|---|---|---|---|---|---|
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS 0/33 clear0.00 Σ lines | ||||||
Generally Where any item, clause or sub-clause of the General Requirements has not been priced, it will be deemed that the value of such item, clause or sub-clause is included in the rates for measured items elsewhere in the Bills of Quantities.REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
Generally The rates and prices in these Bills of Quantities are fixed for the duration of the Contract and shall not be subject to any adjustment in respect of rise or fall in the cost of labour, materials, plant, equipment, transport or any other matters affecting the cost of execution of the Contract.REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
Generally References hereunder to the Schedule of Project Requirements (SOPR) are intended solely to direct the Contractor to the specific requirements of the Schedule of Project Requirements in respect of a particular item and do not in any way limit the scope of such item to the requirements of the Schedule of Project Requirements.REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
A1.1- Schedule of Clauses 4 Contractor's All Risk PolicyREVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —By Employer | Needs review | |
A1.1- Schedule of Clauses 6 Professional Indemnity insuranceREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
A1.1- Schedule of Clauses 7 Third Party liability insuranceREVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —By Employer | Needs review | |
A1.1- Schedule of Clauses 8 Plant and Contractor's Equipment InsuranceREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
A1.1- Schedule of Clauses 9 Motor Vehicle Third Party and Passenger Liability InsuranceREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
A1.1- Schedule of Clauses The Contractor shall price hereunder any special requirements related to the specification clausesREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
A3 - Restrictions 4 The Maintenance of existing services on, under or over the SiteREVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Excluded | Needs review | |
A3 - Restrictions 5 The Execution of the Works in the required specific order, sections or phasesREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
1 Office for the Contract administrators i. EstablishmentREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
1 Office for the Contract administrators ii. MaintenanceREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
1 Office for the Contract administrators iii. RemovalREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
1 Office for the Contract administrators 5 Transport of workpeopleREVIEWAmount column prints "Included in A5.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A5.1 | Needs review | |
3 Screens and guardrails i. Establishment (Fixed Charges)REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A4.1 | Needs review | |
3 Screens and guardrails ii. Maintenance (Time Related Charges)REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A4.1 | Needs review | |
3 Screens and guardrails iii. Removal (Fixed Charges)REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A4.1 | Needs review | |
A8.1 An item shall be given for temporary works including design, which shall include: 3 PumpingREVIEWAmount column prints "Included in Site Works (Bill Nr 2)" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in Site Works (Bill Nr 2) | Needs review | |
A9.1 An item shall be given for temporary works, which shall include: 5 - Traffic regulationsREVIEWAmount column prints "Included in A8.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A8.1 | Needs review | |
A9.1 An item shall be given for temporary works, which shall include: 7 - Drying the WorksREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
A9.1 An item shall be given for temporary works, which shall include: 8 - Control of noise and pollutionREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
A9.1 An item shall be given for temporary works, which shall include: 9 - All Statutory obligationsREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 4 - Off site storageREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 6 - Specialist Third Party Testing, Commissioning and CertificationREVIEWAmount column prints "Included in A9.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A9.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 12 - Internet connection requirements on siteREVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A7.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 13 - Precautions against FireREVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A4.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 15 - Project Health, Safety, Environment and Security GuidelinesREVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A4.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 16 - General cleaning and waste disposal during constructionREVIEWAmount column prints "Included in A9.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in A9.1 | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 19 - Contract Spares/Attic stockREVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Excluded | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 20 - As-built drawingsREVIEWAmount column prints "Included in BIM" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included in BIM | Needs review | |
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor. 22 - WarrantiesREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | Item | — | —Included | Needs review | |
Additional Items Any items that may not be covered elsewhere in the Bills of Quantities which the Tenderer deemed to be necessary in order to carry out the works in full compliance with the SOPR must be itemised and price belowREVIEWThe source prints neither a quantity nor a rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | Item | — | — | Needs review | |
GENERALLY 0/42 clear10,965,759.72 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Site Work in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Concrete Work in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Masonry in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Metalwork in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | — | Needs review | |
| Primary Structural Steel (Non Fire Rated) to inaccessible areas on façade (Dummy Balconies) and Canopies Provisional Qty REVIEWItem code "ADD" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | 552.04 | t | 19,218.00 | 10,609,104.72 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Woodwork in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| Vanity counters; including countertop, forming of holes, front/side panels, drawers, hardware, finishes, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| To powder room REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed. | — | — | — | 0.00 | Needs review | |
| Veneered shelves; including finishes, fixings, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| To powder room REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed. | — | — | — | 0.00 | Needs review | |
| Cabinets with veneered open shelf; including concealed light (measured separately), front/side panels, hardware, finishes, fixings, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| To powder room REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed. | — | — | — | 0.00 | Needs review | |
| Wardrobes; comprising 18mm thick MDF shelving and glass shutter; including MDF backing, carcass, frames, supports, front/side/back panels, doors, shelves, drawers, concealed light (measured separately), hardware, finishes, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Thermal and Moisture Protection in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Doors and Windows in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | — | Needs review | |
| Double glazed vision panel screen; Type V1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | — | Needs review | |
| Double glazed vision panel screen; Type V2; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 8mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | — | Needs review | |
| Double glazed spandrel panel screen; Type S1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, plaster board, insulation, fixings, fittings, accessories and all ancillary works as per drawings and specifications REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | — | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Finishes in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Accessories in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Tempered mirror; type GL-101; 6mm thick clear mirror with metal frame; including, backing, supports, finishes, accessories and all ancillary works as necessary REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | 0.00 | Needs review | |
| Shower glass partition; fixed glass with doors; glass; 10mm thick; including ironmongery, fixings, accessories and all ancillary works as necessary REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | 0.00 | Needs review | |
| Clear Glass REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"Clear Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed. | 0 | — | — | 0.00 | Needs review | |
| Fluted Tinted Glass REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"Fluted Tinted Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed. | 0 | — | — | 0.00 | Needs review | |
| Precast Concrete kerb REVIEW"Precast Concrete kerb" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed. | 2,301 | m | 155.00 | 356,655.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Equipment in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Furnishings in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Conveying Systems in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Mechanical Engineering Installations in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Electrical Engineering Installations in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Site Works in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Concrete Works in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Metalwork in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Thermal and Moisture Protection in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Finishes in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Accessories in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Equipment in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Furnishing in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Special Construction in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Mechanical Engineering Installations in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Electrical Engineering Installations in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
POURED CONCRETE 0/3 clear443,352.00 Σ lines | ||||||
Reinforced concrete; concrete grade C50/60 ColumnsREVIEW2,734 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2,734 | m3 | — | 0.00 | Needs review | |
Reinforced concrete; concrete grade C56/70 Coupling beamsREVIEWReference sequence restarts at "A" on 2 - Main/6 without a heading change — a governing heading may have been missed above it. | 812 | m3 | 546.00 | 443,352.00 | Needs review | |
Reinforced concrete; concrete grade C70/85 Blade wall; 400mm thickREVIEW1,721 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1,721 | m3 | — | 0.00 | Needs review | |
REINFORCEMENT 0/1 clear0.00 Σ lines | ||||||
Reinforcing steel bars; high yield deformed; grade 60 Planter wallREVIEW8.88 t measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 8.88 | t | — | 0.00 | Needs review | |
PRESTRESSED CONCRETE 0/1 clear0.00 Σ lines | ||||||
Post tensioning (PT) system; comprise of design, approvals including prestressing steel, anchorages, plates, ducts, grouts, protection, accessories and all ancillary works as necessary PT system; to post tensioned slabREVIEWAmount column prints "Please refer ADD items" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 1,425.72 | t | — | —Please refer ADD items | Needs review | |
SUNDRIES 0/42 clear66,444.00 Σ lines | ||||||
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Dowelled control jointsREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Dowelled control joints (RATE ONLY)REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | m | — | —Rate Only | Needs review | |
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Isolation jointsREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Isolation joints (RATE ONLY)REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | m | — | —Rate Only | Needs review | |
| Allow for providing shop drawings, as built drawings and material submittal approvals REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for providing catalogues, operation and maintenance manuals REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for labeling, tagging of equipment with their related control panel and components as specified REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for testing and commissioning the complete installation REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for all connections to existing services mains REVIEWAmount column prints "Included within plot" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included within plot | Needs review | |
| Allow for providing spares for Mechanical Engineering Installations REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | — | Needs review | |
| Allow for all supports, fixings, anchors and insulating blocks where not included above or elsewhere REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for all identification including painting, marking and labeling REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed installation REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for providing spares for the Electrical Engineering Installation REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | — | Needs review | |
| Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for planting edging REVIEWUnit "Item" with quantity 0 and the amount 66,444.00 repeated in the Rate column — priced as a whole item, so quantity × rate is not applied. The amount stands as printed. REVIEW"Allow for planting edging" has no heading context while other items on 3 - Ext/4 do — a governing heading may have been missed. | 0 | Item | 66,444.00 | 66,444.00 | Needs review | |
| Allow for the provision of water only for maintenance purpose during defect liability period REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for all identification including painting, marking and labelling REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for inspection, testing and commissioning including all off-site and factory testing; inspections to demonstrate compliance with relevant specifications and standards; operating the completed installations; submitting all relevant test record sheets at the completion of the installations REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed installation REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for providing spares for the Mechanical Engineering Installation REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | — | Needs review | |
| Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Mechanical Engineering Installations Allow for planning and coordinating with relevant statutory authorities and with all other tradesREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Mechanical Engineering Installations Allow for liaison with obtaining approvals and attendance on approved Authorities, other statutory bodies and service providers as requiredREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Mechanical Engineering Installations Allow for supplying and fixing all brackets, clamps and other fixing devices including building in or cutting and pinning and all making goodREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Mechanical Engineering Installations Allow for training the Employer's Staff to operate and maintain the Mechanical Engineering InstallationsREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Mechanical Engineering Installations Allow for all incidental work to the Mechanical Engineering Installations where not included above or elsewhereREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for earthing and bonding as specified; in particular all metal containments shall be REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for all supports, fixings, anchors and insulating blocks where not included above or elsewhere REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for all identification including painting, marking and labeling REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed
installation REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
| Allow for providing spares for the Electrical Engineering Installation REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Electrical Engineering Installations Allow for planning and coordinating with relevant statutory authorities and with all other tradesREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Electrical Engineering Installations Allow for liaison with obtaining approvals and attendance on DEWA, other statutory bodies and service providers as requiredREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Electrical Engineering Installations Allow for marking the positions of and cutting or forming holes, mortices, chases or the like and all making goodREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Electrical Engineering Installations Allow for supplying and fixing all sleeves, frames and built-in fire stoppers for building into concrete structures and masonry wallsREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Electrical Engineering Installations Allow for supplying and fixing all brackets, clamps and other fixing devices including building in or cutting and pinning and all making goodREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Electrical Engineering Installations Allow for fire stopping all cables, conduit, trucking, cable tray and the like at penetrations through fire walls and other structures and making goodREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Electrical Engineering Installations Allow for all incidental work including factory finishing, fixing to all backgrounds by appropriate means and all making goodREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Electrical Engineering Installations Allow for training the Employer's Staff to operate and maintain the Electrical Engineering InstallationREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Work Incidental to Electrical Engineering Installations Allow for all incidental work to the Electrical Engineering Installation where not included above or elsewhereREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
NON-STRUCTURAL METALWORK 0/1 clear0.00 Σ lines | ||||||
Stainless steel ladders to water tanks; type AM-451; wall mounted stainless steel with safety cage; including finishes, frames, supports, fixings, accessories and all ancillary works as necessary Type 2; size 960 x 690 x 10300mm highREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
VARIANCE IN QUANTITY 0/7 clear-727,785.96 Σ lines | ||||||
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; UB 533 x 210 x 82REVIEWItem code "A" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -5.69 | t | 21,769.00 | -123,865.61 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; UC 203 x 203 x 60REVIEWItem code "B" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | 4.6 | t | 21,769.00 | 100,137.40 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; CHS 219 x 6.3REVIEWItem code "C" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -0.28 | t | 21,769.00 | -6,095.32 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; SHS 150 x 150 x 6.3REVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -0.44 | t | 21,769.00 | -9,578.36 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; SHS 120 x 120 x 6.3REVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -0.03 | t | 21,769.00 | -653.07 | Needs review | |
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications To ground floor and podium wallsREVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -64 | m2 | 1,133.00 | -72,512.00 | Needs review | |
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications To tower wallsREVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -543 | m2 | 1,133.00 | -615,219.00 | Needs review | |
CEILING FINISHES 0/2 clear0.00 Σ lines | ||||||
Gypsum board tile ceiling system; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories Extra over for access panelREVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Not Applicable | Needs review | |
Concealed grid aluminium tile ceiling system; demountable, perforated aluminium tiles; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories Extra over for access panelREVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Not Applicable | Needs review | |
TOILET ACCESSORIES 0/1 clear0.00 Σ lines | ||||||
Common Areas Type SAN-711; toilet paper holderREVIEW9 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 9 | Nr. | — | 0.00 | Needs review | |
SIGNAGE AND WAYFINDING 0/1 clear0.00 Σ lines | ||||||
Internal Signage Retail sign by othersREVIEWAmount column prints "By Others" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 6 | Nr. | — | —By Others | Needs review | |
PARKING ACCESSORIES 0/2 clear0.00 Σ lines | ||||||
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary Type EXH-301; 100mm highREVIEW2,969 m2 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2,969 | m2 | — | 0.00 | Needs review | |
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary 150mm high; to rampsREVIEW609 m measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 609 | m | — | 0.00 | Needs review | |
WHITE GOODS 0/9 clear0.00 Σ lines | ||||||
White goods; including accessories and all ancillary works as necessary Type WG-111; freestanding cookerREVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 30 | Nr. | — | 0.00 | Needs review | |
| loading more… 150 of 807 lines rendered | ||||||
| Item | Description | Qty | Unit | Rate | Amount | State |
|---|---|---|---|---|---|---|
Section 2/B · SECTION B - SITE WORKS · Page 2/B/1 - 2/B/4 0/1 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Site Work in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
Section 2/C · SECTION C - CONCRETE WORKS · Page 2/C/1 - 2/C/12 0/6 clear443,352.00 Σ lines | ||||||
Reinforced concrete; concrete grade C50/60 ColumnsREVIEW2,734 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2,734 | m3 | — | 0.00 | Needs review | |
Reinforced concrete; concrete grade C56/70 Coupling beamsREVIEWReference sequence restarts at "A" on 2 - Main/6 without a heading change — a governing heading may have been missed above it. | 812 | m3 | 546.00 | 443,352.00 | Needs review | |
Reinforced concrete; concrete grade C70/85 Blade wall; 400mm thickREVIEW1,721 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1,721 | m3 | — | 0.00 | Needs review | |
Reinforcing steel bars; high yield deformed; grade 60 Planter wallREVIEW8.88 t measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 8.88 | t | — | 0.00 | Needs review | |
Post tensioning (PT) system; comprise of design, approvals including prestressing steel, anchorages, plates, ducts, grouts, protection, accessories and all ancillary works as necessary PT system; to post tensioned slabREVIEWAmount column prints "Please refer ADD items" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 1,425.72 | t | — | —Please refer ADD items | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Concrete Work in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
Section 2/D · SECTION D - MASONRY · Page 2/D/1 - 2/D/4 0/5 clear0.00 Σ lines | ||||||
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Dowelled control jointsREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Dowelled control joints (RATE ONLY)REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | m | — | —Rate Only | Needs review | |
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Isolation jointsREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Included | Needs review | |
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like Isolation joints (RATE ONLY)REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | — | m | — | —Rate Only | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Masonry in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
Section 2/E · SECTION E - METALWORK · Page 2/E/1 - 2/E/12 0/10 clear9,881,318.76 Σ lines | ||||||
Stainless steel ladders to water tanks; type AM-451; wall mounted stainless steel with safety cage; including finishes, frames, supports, fixings, accessories and all ancillary works as necessary Type 2; size 960 x 690 x 10300mm highREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Metalwork in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | — | Needs review | |
| Primary Structural Steel (Non Fire Rated) to inaccessible areas on façade (Dummy Balconies) and Canopies Provisional Qty REVIEWItem code "ADD" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | 552.04 | t | 19,218.00 | 10,609,104.72 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; UB 533 x 210 x 82REVIEWItem code "A" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -5.69 | t | 21,769.00 | -123,865.61 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; UC 203 x 203 x 60REVIEWItem code "B" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | 4.6 | t | 21,769.00 | 100,137.40 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; CHS 219 x 6.3REVIEWItem code "C" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -0.28 | t | 21,769.00 | -6,095.32 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; SHS 150 x 150 x 6.3REVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -0.44 | t | 21,769.00 | -9,578.36 | Needs review | |
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary Columns; SHS 120 x 120 x 6.3REVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -0.03 | t | 21,769.00 | -653.07 | Needs review | |
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications To ground floor and podium wallsREVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -64 | m2 | 1,133.00 | -72,512.00 | Needs review | |
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications To tower wallsREVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering. | -543 | m2 | 1,133.00 | -615,219.00 | Needs review | |
Section 2/F · SECTION F - WOOD WORK · Page 2/F/1 - 2/F/25 0/9 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Woodwork in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| Vanity counters; including countertop, forming of holes, front/side panels, drawers, hardware, finishes, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| To powder room REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed. | — | — | — | 0.00 | Needs review | |
| Veneered shelves; including finishes, fixings, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| To powder room REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed. | — | — | — | 0.00 | Needs review | |
| Cabinets with veneered open shelf; including concealed light (measured separately), front/side panels, hardware, finishes, fixings, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
| To powder room REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed. | — | — | — | 0.00 | Needs review | |
| Wardrobes; comprising 18mm thick MDF shelving and glass shutter; including MDF backing, carcass, frames, supports, front/side/back panels, doors, shelves, drawers, concealed light (measured separately), hardware, finishes, accessories and all ancillary works as necessary REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | — | — | — | 0.00 | Needs review | |
Section 2/G · SECTION G - THERMAL AND MOISTURE PROTECTION · Page 2/G/1 - 2/G/5 0/1 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Thermal and Moisture Protection in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
Section 2/H · SECTION H - DOORS AND WINDOWS · Page 2/H/1 - 2/H/17 0/4 clear0.00 Σ lines | ||||||
| Allow for any other works which are not included above and which are required to complete the Doors and Windows in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | — | Needs review | |
| Double glazed vision panel screen; Type V1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | — | Needs review | |
| Double glazed vision panel screen; Type V2; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 8mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | — | Needs review | |
| Double glazed spandrel panel screen; Type S1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, plaster board, insulation, fixings, fittings, accessories and all ancillary works as per drawings and specifications REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | — | Needs review | |
Section 2/J · SECTION J - FINISHES · Page 2/J/1 - 2/J/18 0/3 clear0.00 Σ lines | ||||||
Gypsum board tile ceiling system; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories Extra over for access panelREVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Not Applicable | Needs review | |
Concealed grid aluminium tile ceiling system; demountable, perforated aluminium tiles; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories Extra over for access panelREVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 0 | Item | — | —Not Applicable | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Finishes in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
Section 2/K · SECTION K - ACCESSORIES · Page 2/K/1 - 2/K/14 0/10 clear356,655.00 Σ lines | ||||||
Common Areas Type SAN-711; toilet paper holderREVIEW9 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 9 | Nr. | — | 0.00 | Needs review | |
Internal Signage Retail sign by othersREVIEWAmount column prints "By Others" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 6 | Nr. | — | —By Others | Needs review | |
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary Type EXH-301; 100mm highREVIEW2,969 m2 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2,969 | m2 | — | 0.00 | Needs review | |
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary 150mm high; to rampsREVIEW609 m measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 609 | m | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Accessories in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Tempered mirror; type GL-101; 6mm thick clear mirror with metal frame; including, backing, supports, finishes, accessories and all ancillary works as necessary REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | 0.00 | Needs review | |
| Shower glass partition; fixed glass with doors; glass; 10mm thick; including ironmongery, fixings, accessories and all ancillary works as necessary REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | — | — | 0.00 | Needs review | |
| Clear Glass REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"Clear Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed. | 0 | — | — | 0.00 | Needs review | |
| Fluted Tinted Glass REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. REVIEW"Fluted Tinted Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed. | 0 | — | — | 0.00 | Needs review | |
| Precast Concrete kerb REVIEW"Precast Concrete kerb" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed. | 2,301 | m | 155.00 | 356,655.00 | Needs review | |
Section 2/L · SECTION L - EQUIPMENT · Page 2/L/1 - 2/L/7 0/42 clear50,850.00 Σ lines1 errors | ||||||
White goods; including accessories and all ancillary works as necessary Type WG-111; freestanding cookerREVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 30 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-112; freestanding fridgeREVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 30 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-113; freestanding freezerREVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 30 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-114; freestanding dishwasherREVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 30 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-116; coffee machineREVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-117; tv screenREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-118; tv screenREVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 5 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-119; water dispenserREVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 8 | Nr. | — | 0.00 | Needs review | |
White goods; including accessories and all ancillary works as necessary Type WG-120; tv screenREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
| Supply and installation by Others: Contractor to allow for Co-ordination, attendance and builders work ERRORNo item reference on 2 - Main/104. Every priced line carries a printed reference (A, B, C…) — either the reference was missed, or this row is not an item. | 1 | Item | 50,850.00 | 50,850.00 | Error | |
| Type EQ-101; run 19" excite live REVIEW7 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 7 | Nr. | — | 0.00 | Needs review | |
| Type EQ-102; climb 16" excite live REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-103; synchro ar 16" excite live REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-104; technogym bike REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-105; skillrow REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-106; lower back fitness bench REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
| Type EQ-107; yoga mat REVIEW9 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 9 | Nr. | — | 0.00 | Needs review | |
| Type EQ-108; crunch bench press REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-109; multi-power REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-110; adjustable bench REVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 5 | Nr. | — | 0.00 | Needs review | |
| Type EQ-111; two tier dumbbell rack REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-112; dumbbells (10 pairs) REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-113; dual leg curl/leg extension selection 700 REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-114; lat machine selection 700 REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-115; shoulder press-selection 700 REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-116; chest press-selection 700 REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-117; skill tools storage REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-118; universe wall 2 virtual REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 3 | Nr. | — | 0.00 | Needs review | |
| Type EQ-119; vario 16" excite live REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-120; skill up REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-121; skillmill REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-122; skillrun unity 7000 REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-123; plyobox REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-124; punching bag REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
| Type EQ-125; leg press selection 700 REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
Galvanized mild steel running track; including galvanized steel base plates, clip ears, stainless steel A4/80 u-bolts, high-strength grout, fixings; complete BMU tracks at 4000mm center to centerREVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule). | 183 | m | — | —Included | Needs review | |
Allow to detent pin BMU restraints; including painted restraint socket, fixings, brackets, accessories and all ancillary works as necessary To tower 1REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
Allow to detent pin BMU restraints; including painted restraint socket, fixings, brackets, accessories and all ancillary works as necessary To tower 2REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
Allow to detent pin BMU restraints; including painted restraint socket, fixings, brackets, accessories and all ancillary works as necessary To tower 3REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
Allow to detent pin BMU restraints; including painted restraint socket, fixings, brackets, accessories and all ancillary works as necessary To tower 4REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
Allow to detent pin BMU restraints; including painted restraint socket, fixings, brackets, accessories and all ancillary works as necessary Allow to mobile elevated work platform (MEWP) including accessories and all ancillary works as necessaryREVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
| Allow for any other works which are not included above and which are required to complete the Equipment in accordance with the Specification and the Drawings (Tenderer to list below): REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 0 | Item | — | 0.00 | Needs review | |
Section 2/M · SECTION M - FURNISHING · Page 2/M/1 - 2/M/7 0/101 clear0.00 Σ lines | ||||||
Case goods; including accessories and all ancillary works as necessary Type CG-101; coffee tableREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-102; side tableREVIEW6 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 6 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-103; side tableREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-104; console behind sofaREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-105; consoleREVIEW6 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 6 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-106; side tableREVIEW6 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 6 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-107; tableREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-108; consoleREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-109; coffee tableREVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-110; side table vintage bronzeREVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 8 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-111; side tableREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-112; side tableREVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 5 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-113; communal table travertineREVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-114; coffee tableREVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-115; coffee tableREVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-116; armchairs side tableREVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-117; sofa side tableREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-118; coffee tableREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-119; coffee tableREVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 8 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-120; dining tableREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-121; consoleREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-122; gaming area side tableREVIEW12 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 12 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-123; kids tableREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-124; pool tableREVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-125; foosball tableREVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
Case goods; including accessories and all ancillary works as necessary Type CG-126; shower benchREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Loose rugs; including accessories and all ancillary works as necessary Type LR-101; seating area loose rugREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Loose rugs; including accessories and all ancillary works as necessary Type LR-102; big table loose rugREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Loose rugs; including accessories and all ancillary works as necessary Type LR-103; rectangular loose rugREVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 5 | Nr. | — | 0.00 | Needs review | |
Loose rugs; including accessories and all ancillary works as necessary Type LR-104; rectangular loose rugREVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 1 | Nr. | — | 0.00 | Needs review | |
Loose rugs; including accessories and all ancillary works as necessary Type LR-105; loose rugREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
Loose rugs; including accessories and all ancillary works as necessary Type LR-106; loose rugREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
Loose rugs; including accessories and all ancillary works as necessary Type LR-107; loose rugREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-101; sheer curtainsREVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 8 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-102; plant potsREVIEW10 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 10 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-103; lift lobby entranceREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-104; artwork behind sofaREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-105; artwork above console- hand painted art paintingREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-106; artwork at table areaREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-107; artworkREVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-108; entrance lobby corridor artworkREVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 8 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-109; roller blindsREVIEW37 m measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 37 | m | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-110; accessoriesREVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 2 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-111; artworkREVIEW215 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 215 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-112; artworkREVIEW870 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 870 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-113; curtains manualREVIEW30 m measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 30 | m | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-114; plant potsREVIEW6 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 6 | Nr. | — | 0.00 | Needs review | |
Miscellaneous; including accessories and all ancillary works as necessary Type MI-115; sheer curtains-seating area and table area only (deleted)REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification. | 4 | Nr. | — | 0.00 | Needs review | |
| loading more… 150 of 807 lines rendered | ||||||
What the bidder did with the line
Read from the source. Every line sits in exactly one of these.| State | Lines | Measured | Money | |
|---|---|---|---|---|
| PricedA rate in the source and money in the amount. | 7,331 | 7,914,918.74 | 2,246,018,361.00 | |
| UnpricedNo rate given, nothing carried into the totals. | 209 | 91,900.88 | — | |
| Prints words, not a figure“By Others”, “Included” — counted as nil, as the bidder's own page total does. | 589 | 52,231.72 | — | |
| Priced as a wholeMoney on the line with no rate behind it — a lump or provisional sum. | 110 | — | 291,658,553.00 |
Where your review stands
Your review of those same lines — a line can be in more than one.| State | Lines | Measured | Money | |
|---|---|---|---|---|
| Still openCarries a question nobody has answered yet. | 807 | 147,189.8 | 10,798,619.76 | |
| ConfirmedYou checked it; the finding stands and left the queue. | 0 | — | — | |
| RuledA recorded determination answers it — reversible at any time. | 0 | — | — | |
| Does not reconcileAn error on the line itself, not on its block. | 1 | 1 | 50,850.00 |
Collection blocks
Σ of each block’s line amounts against the total the source itself prints.| Block | Section | Lines | Σ lines | Source prints | Ties |
|---|---|---|---|---|---|
| GR1/1 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 3 | 0.00 | 0.00 | ✓ |
| GR1/2 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 9 | 14,590,702.00 | 14,590,702.00 | ✓ |
| GR1/3 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 1 | 0.00 | 0.00 | ✓ |
| GR1/4 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 5 | 3,780,402.00 | 3,780,402.00 | ✓ |
| GR1/5 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 7 | 143,675,216.00 | 143,675,216.00 | ✓ |
| GR1/6 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 16 | 43,935,329.00 | 43,935,329.00 | ✓ |
| GR1/7 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 11 | 2,189,955.00 | 2,189,955.00 | ✓ |
| GR1/8 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 4 | 97,000.00 | 97,000.00 | ✓ |
| GR1/9 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 12 | 8,365,201.00 | 8,365,201.00 | ✓ |
| GR1/10 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 9 | 39,972,150.00 | 39,972,150.00 | ✓ |
| GR1/11 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 3 | 1,287,963.00 | 1,287,963.00 | ✓ |
| GR1/12 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 14 | 5,482,653.00 | 5,482,653.00 | ✓ |
| GR1/13 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 17 | 6,598,029.00 | 6,598,029.00 | ✓ |
| GR1/14 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 1 | 325,400.00 | 325,400.00 | ✓ |
| GR1/15 | GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS | 1 | 0.00 | 0.00 | ✓ |
| 2 - Main/1 | SITE PREPARATION | 6 | 3,860,035.48 | 3,860,035.48 | ✓ |
| 2 - Main/2 | BORED PILING | 6 | 2,395,497.00 | 2,395,497.00 | ✓ |
| 2 - Main/3 | VARIANCE IN QUANTITY | 7 | 1,250,203.00 | 1,250,203.00 | ✓ |
| 2 - Main/4 | POURED CONCRETE | 19 | 16,203,427.00 | 16,203,427.00 | ✓ |
| 2 - Main/5 | POURED CONCRETE | 20 | 32,621,748.00 | 32,621,748.00 | ✓ |
| 2 - Main/6 | POURED CONCRETE | 23 | 46,443,438.00 | 46,443,438.00 | ✓ |
| 2 - Main/7 | POURED CONCRETE | 6 | 407,176.00 | 407,176.00 | ✓ |
| 2 - Main/8 | REINFORCEMENT | 22 | 200,093,867.32 | 200,093,867.32 | ✓ |
| 2 - Main/9 | REINFORCEMENT | 6 | 1,262,147.85 | 1,262,147.85 | ✓ |
| 2 - Main/10 | SHUTTERING | 20 | 88,257,136.00 | 88,257,136.00 | ✓ |
| 2 - Main/11 | SHUTTERING | 4 | 1,838,266.00 | 1,838,266.00 | ✓ |
| 2 - Main/12 | PRESTRESSED CONCRETE | 4 | 88,831,972.37 | 88,831,972.37 | ✓ |
| 2 - Main/13 | SUNDRIES | 5 | 6,016,537.00 | 6,016,537.00 | ✓ |
| 2 - Main/14 | VARIANCE IN QUANTITY | 138 | 49,063,286.73 | 49,063,286.73 | ✓ |
| 2 - Main/15 | WALL AND PIERS | 11 | 38,176,342.00 | 38,176,342.00 | ✓ |
| 2 - Main/16 | SUNDRIES | 4 | 0.00 | 0.00 | ✓ |
| 2 - Main/17 | VARIANCE IN QUANTITY | 12 | 2,003,408.00 | 2,003,408.00 | ✓ |
| 2 - Main/18 | STRUCTURAL METALWORK | 18 | 3,859,643.70 | 3,859,643.70 | ✓ |
| 2 - Main/19 | STRUCTURAL METALWORK | 5 | 1,755,452.16 | 1,755,452.16 | ✓ |
| 2 - Main/20 | NON-STRUCTURAL METALWORK | 5 | 74,727,568.00 | 74,727,568.00 | ✓ |
| 2 - Main/21 | NON-STRUCTURAL METALWORK | 14 | 7,395,546.00 | 7,395,546.00 | ✓ |
| 2 - Main/22 | NON-STRUCTURAL METALWORK | 16 | 54,536,508.00 | 54,536,508.00 | ✓ |
| 2 - Main/23 | NON-STRUCTURAL METALWORK | 20 | 48,059,944.00 | 48,059,944.00 | ✓ |
| 2 - Main/24 | NON-STRUCTURAL METALWORK | 15 | 50,152,943.00 | 50,152,943.00 | ✓ |
| 2 - Main/25 | NON-STRUCTURAL METALWORK | 12 | 6,756,343.00 | 6,756,343.00 | ✓ |
| 2 - Main/26 | NON-STRUCTURAL METALWORK | 9 | 541,455.00 | 541,455.00 | ✓ |
| 2 - Main/27 | NON-STRUCTURAL METALWORK | 12 | 5,069,170.00 | 5,069,170.00 | ✓ |
| 2 - Main/28 | VARIANCE IN QUANTITY | 88 | 17,672,289.54 | 17,672,289.54 | ✓ |
| 2 - Main/29 | COMPOSITE ITEMS | 12 | 3,809,123.00 | 3,809,123.00 | ✓ |
| 2 - Main/30 | COMPOSITE ITEMS | 14 | 2,032,524.00 | 2,032,524.00 | ✓ |
| 2 - Main/31 | COMPOSITE ITEMS | 13 | 1,023,548.00 | 1,023,548.00 | ✓ |
| 2 - Main/32 | COMPOSITE ITEMS | 20 | 3,573,015.00 | 3,573,015.00 | ✓ |
| 2 - Main/33 | COMPOSITE ITEMS | 16 | 3,523,105.00 | 3,523,105.00 | ✓ |
| 2 - Main/34 | COMPOSITE ITEMS | 18 | 6,221,471.00 | 6,221,471.00 | ✓ |
| 2 - Main/35 | COMPOSITE ITEMS | 18 | 1,568,576.00 | 1,568,576.00 | ✓ |
| 2 - Main/36 | COMPOSITE ITEMS | 19 | 814,336.00 | 814,336.00 | ✓ |
| 2 - Main/37 | COMPOSITE ITEMS | 17 | 20,293,915.00 | 20,293,915.00 | ✓ |
| 2 - Main/38 | COMPOSITE ITEMS | 16 | 17,227,769.00 | 17,227,769.00 | ✓ |
| 2 - Main/39 | COMPOSITE ITEMS | 9 | 1,614,018.00 | 1,614,018.00 | ✓ |
| 2 - Main/40 | COMPOSITE ITEMS | 16 | 26,009,219.00 | 26,009,219.00 | ✓ |
| 2 - Main/41 | COMPOSITE ITEMS | 21 | 36,888,565.00 | 36,888,565.00 | ✓ |
| 2 - Main/42 | COMPOSITE ITEMS | 18 | 9,209,998.00 | 9,209,998.00 | ✓ |
| 2 - Main/43 | COMPOSITE ITEMS | 18 | 1,427,050.00 | 1,427,050.00 | ✓ |
| 2 - Main/44 | COMPOSITE ITEMS | 16 | 531,370.00 | 531,370.00 | ✓ |
| 2 - Main/45 | COMPOSITE ITEMS | 13 | 1,817,804.00 | 1,817,804.00 | ✓ |
| 2 - Main/46 | COMPOSITE ITEMS | 15 | 46,985.00 | 46,985.00 | ✓ |
| 2 - Main/47 | COMPOSITE ITEMS | 12 | 171,071.00 | 171,071.00 | ✓ |
| 2 - Main/48 | COMPOSITE ITEMS | 14 | 563,055.00 | 563,055.00 | ✓ |
| 2 - Main/49 | COMPOSITE ITEMS | 9 | 1,428,435.00 | 1,428,435.00 | ✓ |
| 2 - Main/50 | COMPOSITE ITEMS | 14 | 1,237,124.00 | 1,237,124.00 | ✓ |
| 2 - Main/51 | COMPOSITE ITEMS | 13 | 555,104.00 | 555,104.00 | ✓ |
| 2 - Main/52 | VARIANCE IN QUANTITY | 135 | -2,746,179.00 | -2,746,179.00 | ✓ |
| 2 - Main/53 | COVERS AND LININGS | 9 | 22,096,305.00 | 22,096,305.00 | ✓ |
| 2 - Main/54 | DAMP-PROOF COURSES | 4 | 1,087,678.89 | 1,087,678.89 | ✓ |
| 2 - Main/55 | INSULATION | 4 | 5,779,558.00 | 5,779,558.00 | ✓ |
| 2 - Main/56 | VARIANCE IN QUANTITY | 24 | 12,006,171.40 | 12,006,171.40 | ✓ |
| 2 - Main/57 | DOORS | 13 | 31,124,879.00 | 31,124,879.00 | ✓ |
| 2 - Main/58 | DOORS | 16 | 5,878,024.00 | 5,878,024.00 | ✓ |
| 2 - Main/59 | DOORS | 16 | 11,515,630.00 | 11,515,630.00 | ✓ |
| 2 - Main/60 | DOORS | 20 | 2,402,117.00 | 2,402,117.00 | ✓ |
| 2 - Main/61 | SCREENS | 16 | 1,663,318.00 | 1,663,318.00 | ✓ |
| 2 - Main/62 | EXTERNAL DOORS | 12 | 179,836.00 | 179,836.00 | ✓ |
| 2 - Main/63 | EXTERNAL DOORS | 12 | 1,326,232.00 | 1,326,232.00 | ✓ |
| 2 - Main/64 | SCREENS | 18 | 81,576,870.00 | 81,576,870.00 | ✓ |
| 2 - Main/65 | SCREENS | 18 | 2,483,049.00 | 2,483,049.00 | ✓ |
| 2 - Main/66 | SCREENS | 16 | 11,773,289.00 | 11,773,289.00 | ✓ |
| 2 - Main/67 | SCREENS | 13 | 2,530,444.00 | 2,530,444.00 | ✓ |
| 2 - Main/68 | SCREENS | 14 | 35,514,151.00 | 35,514,151.00 | ✓ |
| 2 - Main/69 | LOUVERS | 14 | 8,194,223.00 | 8,194,223.00 | ✓ |
| 2 - Main/70 | IRONMONGERY | 21 | 684,142.00 | 684,142.00 | ✓ |
| 2 - Main/71 | IRONMONGERY | 14 | 166,455.00 | 166,455.00 | ✓ |
| 2 - Main/72 | VARIANCE IN QUANTITY | 75 | 6,619,900.00 | 6,619,900.00 | ✓ |
| 2 - Main/73 | BACKGROUNDS | 17 | 47,354,408.00 | 47,354,408.00 | ✓ |
| 2 - Main/74 | BACKGROUNDS | 6 | 5,629,577.00 | 5,629,577.00 | ✓ |
| 2 - Main/75 | FLOOR FINISHES | 14 | 98,699,285.00 | 98,699,285.00 | ✓ |
| 2 - Main/76 | FLOOR FINISHES | 14 | 2,413,857.00 | 2,413,857.00 | ✓ |
| 2 - Main/77 | FLOOR FINISHES | 9 | 1,498,853.00 | 1,498,853.00 | ✓ |
| 2 - Main/78 | FLOOR FINISHES | 8 | 10,059,219.00 | 10,059,219.00 | ✓ |
| 2 - Main/79 | WALL FINISHES | 14 | 25,034,660.00 | 25,034,660.00 | ✓ |
| 2 - Main/80 | WALL FINISHES | 11 | 26,175,988.00 | 26,175,988.00 | ✓ |
| 2 - Main/81 | CEILING FINISHES | 6 | 3,092,350.00 | 3,092,350.00 | ✓ |
| 2 - Main/82 | SUNDRIES | 7 | 2,053,927.00 | 2,053,927.00 | ✓ |
| 2 - Main/83 | SUSPENDED CEILING | 16 | 15,696,749.00 | 15,696,749.00 | ✓ |
| 2 - Main/84 | SUSPENDED CEILING | 16 | 5,315,401.00 | 5,315,401.00 | ✓ |
| 2 - Main/85 | SUSPENDED CEILING | 18 | 4,947,504.00 | 4,947,504.00 | ✓ |
| 2 - Main/86 | DECORATIONS | 12 | 26,625,044.00 | 26,625,044.00 | ✓ |
| 2 - Main/87 | DECORATIONS | 12 | 12,560,108.00 | 12,560,108.00 | ✓ |
| 2 - Main/88 | SIGNWRITING | 14 | 3,237,070.00 | 3,237,070.00 | ✓ |
| 2 - Main/89 | VARIANCE IN QUANTITY | 184 | 20,410,008.00 | 20,410,008.00 | ✓ |
| 2 - Main/90 | TOILET ACCESSORIES | 20 | 338,991.00 | 338,991.00 | ✓ |
| 2 - Main/91 | TOILET ACCESSORIES | 21 | 4,777,421.00 | 4,777,421.00 | ✓ |
| 2 - Main/92 | KITCHEN ACCESSORIES | 7 | 2,713,505.00 | 2,713,505.00 | ✓ |
| 2 - Main/93 | SIGNAGE AND WAYFINDING | 20 | 1,399,437.00 | 1,399,437.00 | ✓ |
| 2 - Main/94 | SIGNAGE AND WAYFINDING | 22 | 1,918,912.00 | 1,918,912.00 | ✓ |
| 2 - Main/95 | PARKING ACCESSORIES | 13 | 973,697.00 | 973,697.00 | ✓ |
| 2 - Main/96 | PARKING ACCESSORIES | 3 | 715,629.00 | 715,629.00 | ✓ |
| 2 - Main/97 | PARTITIONS | 15 | 21,652,099.00 | 21,652,099.00 | ✓ |
| 2 - Main/98 | PARTITIONS | 12 | 5,115,954.00 | 5,115,954.00 | ✓ |
| 2 - Main/99 | TOILET PARTITION | 20 | 10,184,517.00 | 10,184,517.00 | ✓ |
| 2 - Main/100 | TOILET PARTITION | 12 | 5,494,517.00 | 5,494,517.00 | ✓ |
| 2 - Main/101 | WASTE CHUTES | 10 | 3,735,738.00 | 3,735,738.00 | ✓ |
| 2 - Main/102 | VARIANCE IN QUANTITY | 103 | 3,081,380.00 | 3,081,380.00 | ✓ |
| 2 - Main/103 | WHITE GOODS | 18 | 16,707,668.00 | 16,707,668.00 | ✓ |
| 2 - Main/104 | GYM EQUIPMENT | 26 | 50,850.00 | 50,850.00 | ✓ |
| 2 - Main/105 | BUILDING MANAGEMENT UNIT (BMU) | 3 | 4,433,866.00 | 4,433,866.00 | ✓ |
| 2 - Main/106 | BUILDING MANAGEMENT UNIT (BMU) | 8 | 1,329,654.00 | 1,329,654.00 | ✓ |
| 2 - Main/107 | BUILDING MANAGEMENT UNIT (BMU) | 8 | 113,994.00 | 113,994.00 | ✓ |
| 2 - Main/108 | GENERALLY | 1 | 0.00 | 0.00 | ✓ |
| 2 - Main/109 | LOOSE FF&E | 22 | 0.00 | 0.00 | ✓ |
| 2 - Main/110 | LOOSE FF&E | 21 | 0.00 | 0.00 | ✓ |
| 2 - Main/111 | LOOSE FF&E | 24 | 0.00 | 0.00 | ✓ |
| 2 - Main/112 | LOOSE FF&E | 20 | 0.00 | 0.00 | ✓ |
| 2 - Main/113 | LOOSE FF&E | 15 | 258,221.00 | 258,221.00 | ✓ |
| 2 - Main/114 | GENERALLY | 1 | 0.00 | 0.00 | ✓ |
| 2 - Main/115 | LIFTS | 8 | 577,868.00 | 577,868.00 | ✓ |
| 2 - Main/116 | LIFTS | 8 | 21,069,448.00 | 21,069,448.00 | ✓ |
| 2 - Main/117 | LIFTS | 6 | 23,135,368.00 | 23,135,368.00 | ✓ |
| 2 - Main/118 | LIFTS | 2 | 2,668,002.00 | 2,668,002.00 | ✓ |
| 2 - Main/119 | SUNDRIES | 4 | 0.00 | 0.00 | ✓ |
| 2 - Main/120 | BWIC | 6 | 0.00 | 0.00 | ✓ |
| 2 - Main/121 | VARIANCE IN QUANTITY | 7 | -1,612.00 | -1,612.00 | ✓ |
| 2 - Main/122 | SANITARY FIXTURES & FITTINGS | 16 | 2,126,910.00 | 2,126,910.00 | ✓ |
| 2 - Main/123 | SANITARY FIXTURES & FITTINGS | 16 | 9,418,806.00 | 9,418,806.00 | ✓ |
| 2 - Main/124 | SANITARY FIXTURES & FITTINGS | 15 | 2,581,521.00 | 2,581,521.00 | ✓ |
| 2 - Main/125 | SANITARY FIXTURES & FITTINGS | 12 | 3,633,247.00 | 3,633,247.00 | ✓ |
| 2 - Main/126 | SANITARY FIXTURES & FITTINGS | 8 | 444,555.00 | 444,555.00 | ✓ |
| 2 - Main/127 | DRAINAGE INSTALLATION | 18 | 9,922,860.00 | 9,922,860.00 | ✓ |
| 2 - Main/128 | DRAINAGE INSTALLATION | 16 | 1,788,732.00 | 1,788,732.00 | ✓ |
| 2 - Main/129 | DRAINAGE INSTALLATION | 9 | 1,239,872.00 | 1,239,872.00 | ✓ |
| 2 - Main/130 | DRAINAGE INSTALLATION | 17 | 1,638,017.00 | 1,638,017.00 | ✓ |
| 2 - Main/131 | DRAINAGE INSTALLATION | 15 | 10,324,346.00 | 10,324,346.00 | ✓ |
| 2 - Main/132 | DRAINAGE INSTALLATION | 17 | 5,072,471.00 | 5,072,471.00 | ✓ |
| 2 - Main/133 | DRAINAGE INSTALLATION | 15 | 2,219,969.00 | 2,219,969.00 | ✓ |
| 2 - Main/134 | DRAINAGE INSTALLATION | 10 | 160,401.00 | 160,401.00 | ✓ |
| 2 - Main/135 | DRAINAGE INSTALLATION | 10 | 303,129.00 | 303,129.00 | ✓ |
| 2 - Main/136 | DRAINAGE INSTALLATION | 11 | 319,712.00 | 319,712.00 | ✓ |
| 2 - Main/137 | DRAINAGE INSTALLATION | 2 | 121,982.00 | 121,982.00 | ✓ |
| 2 - Main/138 | WATER INSTALLATION | 19 | 11,331,510.00 | 11,331,510.00 | ✓ |
| 2 - Main/139 | WATER INSTALLATION | 15 | 6,572,649.00 | 6,572,649.00 | ✓ |
| 2 - Main/140 | WATER INSTALLATION | 12 | 3,542,932.00 | 3,542,932.00 | ✓ |
| 2 - Main/141 | WATER INSTALLATION | 18 | 986,815.00 | 986,815.00 | ✓ |
| 2 - Main/142 | WATER INSTALLATION | 16 | 290,515.00 | 290,515.00 | ✓ |
| 2 - Main/143 | WATER INSTALLATION | 15 | 3,145,210.00 | 3,145,210.00 | ✓ |
| 2 - Main/144 | WATER INSTALLATION | 8 | 2,767,282.00 | 2,767,282.00 | ✓ |
| 2 - Main/145 | WATER INSTALLATION | 7 | 712,884.00 | 712,884.00 | ✓ |
| 2 - Main/146 | WATER INSTALLATION | 8 | 552,317.00 | 552,317.00 | ✓ |
| 2 - Main/147 | WATER INSTALLATION | 5 | 0.00 | 0.00 | ✓ |
| 2 - Main/148 | FIRE PROTECTION SYSTEM | 5 | 8,160,904.00 | 8,160,904.00 | ✓ |
| 2 - Main/149 | FIRE PROTECTION SYSTEM | 17 | 14,730,632.00 | 14,730,632.00 | ✓ |
| 2 - Main/150 | FIRE PROTECTION SYSTEM | 21 | 3,201,240.00 | 3,201,240.00 | ✓ |
| 2 - Main/151 | FIRE PROTECTION SYSTEM | 11 | 1,501,874.00 | 1,501,874.00 | ✓ |
| 2 - Main/152 | FIRE PROTECTION SYSTEM | 7 | 4,731,233.00 | 4,731,233.00 | ✓ |
| 2 - Main/153 | FIRE PROTECTION SYSTEM | 10 | 2,052,130.00 | 2,052,130.00 | ✓ |
| 2 - Main/154 | FIRE PROTECTION SYSTEM | 9 | 0.00 | 0.00 | ✓ |
| 2 - Main/155 | FIRE PROTECTION SYSTEM | 10 | 2,251,841.00 | 2,251,841.00 | ✓ |
| 2 - Main/156 | FIRE PROTECTION SYSTEM | 5 | 116,772.00 | 116,772.00 | ✓ |
| 2 - Main/157 | HVAC INSTALLATION | 16 | 12,754,566.00 | 12,754,566.00 | ✓ |
| 2 - Main/158 | HVAC INSTALLATION | 16 | 9,108,483.00 | 9,108,483.00 | ✓ |
| 2 - Main/159 | HVAC INSTALLATION | 18 | 592,434.00 | 592,434.00 | ✓ |
| 2 - Main/160 | HVAC INSTALLATION | 13 | 4,543,571.00 | 4,543,571.00 | ✓ |
| 2 - Main/161 | HVAC INSTALLATION | 7 | 6,708,515.00 | 6,708,515.00 | ✓ |
| 2 - Main/162 | HVAC INSTALLATION | 7 | 939,725.00 | 939,725.00 | ✓ |
| 2 - Main/163 | HVAC INSTALLATION | 13 | 1,231,126.00 | 1,231,126.00 | ✓ |
| 2 - Main/164 | HVAC INSTALLATION | 9 | 10,442,776.00 | 10,442,776.00 | ✓ |
| 2 - Main/165 | HVAC INSTALLATION | 22 | 76,591.00 | 76,591.00 | ✓ |
| 2 - Main/166 | HVAC INSTALLATION | 21 | 96,924.00 | 96,924.00 | ✓ |
| 2 - Main/167 | HVAC INSTALLATION | 21 | 457,731.00 | 457,731.00 | ✓ |
| 2 - Main/168 | HVAC INSTALLATION | 22 | 157,838.00 | 157,838.00 | ✓ |
| 2 - Main/169 | HVAC INSTALLATION | 17 | 103,002.00 | 103,002.00 | ✓ |
| 2 - Main/170 | HVAC INSTALLATION | 21 | 293,208.00 | 293,208.00 | ✓ |
| 2 - Main/171 | HVAC INSTALLATION | 22 | 40,087.00 | 40,087.00 | ✓ |
| 2 - Main/172 | HVAC INSTALLATION | 20 | 96,387.00 | 96,387.00 | ✓ |
| 2 - Main/173 | HVAC INSTALLATION | 22 | 228,699.00 | 228,699.00 | ✓ |
| 2 - Main/174 | HVAC INSTALLATION | 22 | 24,429.00 | 24,429.00 | ✓ |
| 2 - Main/175 | HVAC INSTALLATION | 15 | 420,054.00 | 420,054.00 | ✓ |
| 2 - Main/176 | HVAC INSTALLATION | 21 | 499,528.00 | 499,528.00 | ✓ |
| 2 - Main/177 | HVAC INSTALLATION | 20 | 431,877.00 | 431,877.00 | ✓ |
| 2 - Main/178 | HVAC INSTALLATION | 14 | 278,480.00 | 278,480.00 | ✓ |
| 2 - Main/179 | HVAC INSTALLATION | 14 | 27,540.00 | 27,540.00 | ✓ |
| 2 - Main/180 | HVAC INSTALLATION | 14 | 33,123.00 | 33,123.00 | ✓ |
| 2 - Main/181 | HVAC INSTALLATION | 14 | 23,181.00 | 23,181.00 | ✓ |
| 2 - Main/182 | HVAC INSTALLATION | 14 | 25,557.00 | 25,557.00 | ✓ |
| 2 - Main/183 | HVAC INSTALLATION | 14 | 24,152.00 | 24,152.00 | ✓ |
| 2 - Main/184 | HVAC INSTALLATION | 14 | 235,219.00 | 235,219.00 | ✓ |
| 2 - Main/185 | HVAC INSTALLATION | 14 | 504,072.00 | 504,072.00 | ✓ |
| 2 - Main/186 | HVAC INSTALLATION | 14 | 135,348.00 | 135,348.00 | ✓ |
| 2 - Main/187 | HVAC INSTALLATION | 14 | 22,872.00 | 22,872.00 | ✓ |
| 2 - Main/188 | HVAC INSTALLATION | 14 | 21,806.00 | 21,806.00 | ✓ |
| 2 - Main/189 | HVAC INSTALLATION | 14 | 21,615.00 | 21,615.00 | ✓ |
| 2 - Main/190 | HVAC INSTALLATION | 14 | 291,474.00 | 291,474.00 | ✓ |
| 2 - Main/191 | HVAC INSTALLATION | 14 | 341,792.00 | 341,792.00 | ✓ |
| 2 - Main/192 | HVAC INSTALLATION | 14 | 22,912.00 | 22,912.00 | ✓ |
| 2 - Main/193 | HVAC INSTALLATION | 14 | 76,803.00 | 76,803.00 | ✓ |
| 2 - Main/194 | HVAC INSTALLATION | 14 | 69,668.00 | 69,668.00 | ✓ |
| 2 - Main/195 | HVAC INSTALLATION | 14 | 27,445.00 | 27,445.00 | ✓ |
| 2 - Main/196 | HVAC INSTALLATION | 14 | 47,041.00 | 47,041.00 | ✓ |
| 2 - Main/197 | HVAC INSTALLATION | 14 | 21,207.00 | 21,207.00 | ✓ |
| 2 - Main/198 | HVAC INSTALLATION | 14 | 24,683.00 | 24,683.00 | ✓ |
| 2 - Main/199 | HVAC INSTALLATION | 14 | 28,793.00 | 28,793.00 | ✓ |
| 2 - Main/200 | HVAC INSTALLATION | 14 | 28,526.00 | 28,526.00 | ✓ |
| 2 - Main/201 | HVAC INSTALLATION | 14 | 470,334.00 | 470,334.00 | ✓ |
| 2 - Main/202 | HVAC INSTALLATION | 14 | 439,954.00 | 439,954.00 | ✓ |
| 2 - Main/203 | HVAC INSTALLATION | 14 | 21,900.00 | 21,900.00 | ✓ |
| 2 - Main/204 | HVAC INSTALLATION | 14 | 22,312.00 | 22,312.00 | ✓ |
| 2 - Main/205 | HVAC INSTALLATION | 14 | 22,287.00 | 22,287.00 | ✓ |
| 2 - Main/206 | HVAC INSTALLATION | 14 | 24,848.00 | 24,848.00 | ✓ |
| 2 - Main/207 | HVAC INSTALLATION | 14 | 339,200.00 | 339,200.00 | ✓ |
| 2 - Main/208 | HVAC INSTALLATION | 14 | 221,888.00 | 221,888.00 | ✓ |
| 2 - Main/209 | HVAC INSTALLATION | 14 | 21,636.00 | 21,636.00 | ✓ |
| 2 - Main/210 | HVAC INSTALLATION | 14 | 20,787.00 | 20,787.00 | ✓ |
| 2 - Main/211 | HVAC INSTALLATION | 14 | 26,835.00 | 26,835.00 | ✓ |
| 2 - Main/212 | HVAC INSTALLATION | 14 | 27,640.00 | 27,640.00 | ✓ |
| 2 - Main/213 | HVAC INSTALLATION | 14 | 23,356.00 | 23,356.00 | ✓ |
| 2 - Main/214 | HVAC INSTALLATION | 14 | 21,540.00 | 21,540.00 | ✓ |
| 2 - Main/215 | HVAC INSTALLATION | 14 | 24,520.00 | 24,520.00 | ✓ |
| 2 - Main/216 | HVAC INSTALLATION | 14 | 23,042.00 | 23,042.00 | ✓ |
| 2 - Main/217 | HVAC INSTALLATION | 14 | 25,993.00 | 25,993.00 | ✓ |
| 2 - Main/218 | HVAC INSTALLATION | 14 | 25,434.00 | 25,434.00 | ✓ |
| 2 - Main/219 | HVAC INSTALLATION | 14 | 28,382.00 | 28,382.00 | ✓ |
| 2 - Main/220 | HVAC INSTALLATION | 14 | 30,396.00 | 30,396.00 | ✓ |
| 2 - Main/221 | HVAC INSTALLATION | 14 | 120,029.00 | 120,029.00 | ✓ |
| 2 - Main/222 | HVAC INSTALLATION | 14 | 28,605.00 | 28,605.00 | ✓ |
| 2 - Main/223 | HVAC INSTALLATION | 14 | 21,946.00 | 21,946.00 | ✓ |
| 2 - Main/224 | HVAC INSTALLATION | 14 | 23,379.00 | 23,379.00 | ✓ |
| 2 - Main/225 | HVAC INSTALLATION | 14 | 30,200.00 | 30,200.00 | ✓ |
| 2 - Main/226 | HVAC INSTALLATION | 14 | 22,510.00 | 22,510.00 | ✓ |
| 2 - Main/227 | HVAC INSTALLATION | 14 | 452,659.00 | 452,659.00 | ✓ |
| 2 - Main/228 | HVAC INSTALLATION | 14 | 392,318.00 | 392,318.00 | ✓ |
| 2 - Main/229 | HVAC INSTALLATION | 14 | 21,706.00 | 21,706.00 | ✓ |
| 2 - Main/230 | HVAC INSTALLATION | 14 | 20,788.00 | 20,788.00 | ✓ |
| 2 - Main/231 | HVAC INSTALLATION | 14 | 21,320.00 | 21,320.00 | ✓ |
| 2 - Main/232 | HVAC INSTALLATION | 14 | 19,825.00 | 19,825.00 | ✓ |
| 2 - Main/233 | HVAC INSTALLATION | 14 | 319,831.00 | 319,831.00 | ✓ |
| 2 - Main/234 | HVAC INSTALLATION | 14 | 469,465.00 | 469,465.00 | ✓ |
| 2 - Main/235 | HVAC INSTALLATION | 14 | 30,832.00 | 30,832.00 | ✓ |
| 2 - Main/236 | HVAC INSTALLATION | 14 | 20,638.00 | 20,638.00 | ✓ |
| 2 - Main/237 | HVAC INSTALLATION | 14 | 24,276.00 | 24,276.00 | ✓ |
| 2 - Main/238 | HVAC INSTALLATION | 14 | 23,090.00 | 23,090.00 | ✓ |
| 2 - Main/239 | HVAC INSTALLATION | 14 | 32,393.00 | 32,393.00 | ✓ |
| 2 - Main/240 | HVAC INSTALLATION | 14 | 23,162.00 | 23,162.00 | ✓ |
| 2 - Main/241 | HVAC INSTALLATION | 14 | 26,211.00 | 26,211.00 | ✓ |
| 2 - Main/242 | HVAC INSTALLATION | 14 | 24,751.00 | 24,751.00 | ✓ |
| 2 - Main/243 | HVAC INSTALLATION | 14 | 26,615.00 | 26,615.00 | ✓ |
| 2 - Main/244 | HVAC INSTALLATION | 14 | 23,471.00 | 23,471.00 | ✓ |
| 2 - Main/245 | HVAC INSTALLATION | 14 | 247,329.00 | 247,329.00 | ✓ |
| 2 - Main/246 | HVAC INSTALLATION | 14 | 531,312.00 | 531,312.00 | ✓ |
| 2 - Main/247 | HVAC INSTALLATION | 14 | 156,105.00 | 156,105.00 | ✓ |
| 2 - Main/248 | HVAC INSTALLATION | 14 | 131,952.00 | 131,952.00 | ✓ |
| 2 - Main/249 | HVAC INSTALLATION | 14 | 18,538.00 | 18,538.00 | ✓ |
| 2 - Main/250 | HVAC INSTALLATION | 14 | 24,342.00 | 24,342.00 | ✓ |
| 2 - Main/251 | HVAC INSTALLATION | 14 | 158,933.00 | 158,933.00 | ✓ |
| 2 - Main/252 | HVAC INSTALLATION | 14 | 324,448.00 | 324,448.00 | ✓ |
| 2 - Main/253 | HVAC INSTALLATION | 14 | 64,569.00 | 64,569.00 | ✓ |
| 2 - Main/254 | HVAC INSTALLATION | 14 | 20,235.00 | 20,235.00 | ✓ |
| 2 - Main/255 | HVAC INSTALLATION | 14 | 24,999.00 | 24,999.00 | ✓ |
| 2 - Main/256 | HVAC INSTALLATION | 14 | 22,993.00 | 22,993.00 | ✓ |
| 2 - Main/257 | HVAC INSTALLATION | 14 | 23,670.00 | 23,670.00 | ✓ |
| 2 - Main/258 | HVAC INSTALLATION | 14 | 26,978.00 | 26,978.00 | ✓ |
| 2 - Main/259 | HVAC INSTALLATION | 14 | 26,017.00 | 26,017.00 | ✓ |
| 2 - Main/260 | HVAC INSTALLATION | 11 | 775,835.00 | 775,835.00 | ✓ |
| 2 - Main/261 | HVAC INSTALLATION | 12 | 10,802,888.00 | 10,802,888.00 | ✓ |
| 2 - Main/262 | HVAC INSTALLATION | 18 | 214,566.00 | 214,566.00 | ✓ |
| 2 - Main/263 | HVAC INSTALLATION | 22 | 16,470.00 | 16,470.00 | ✓ |
| 2 - Main/264 | HVAC INSTALLATION | 22 | 18,179.00 | 18,179.00 | ✓ |
| 2 - Main/265 | HVAC INSTALLATION | 22 | 14,672.00 | 14,672.00 | ✓ |
| 2 - Main/266 | HVAC INSTALLATION | 21 | 89,623.00 | 89,623.00 | ✓ |
| 2 - Main/267 | HVAC INSTALLATION | 22 | 15,098.00 | 15,098.00 | ✓ |
| 2 - Main/268 | HVAC INSTALLATION | 22 | 14,051.00 | 14,051.00 | ✓ |
| 2 - Main/269 | HVAC INSTALLATION | 22 | 13,534.00 | 13,534.00 | ✓ |
| 2 - Main/270 | HVAC INSTALLATION | 20 | 13,419.00 | 13,419.00 | ✓ |
| 2 - Main/271 | HVAC INSTALLATION | 17 | 150,318.00 | 150,318.00 | ✓ |
| 2 - Main/272 | HVAC INSTALLATION | 20 | 28,313.00 | 28,313.00 | ✓ |
| 2 - Main/273 | HVAC INSTALLATION | 18 | 3,826.00 | 3,826.00 | ✓ |
| 2 - Main/274 | HVAC INSTALLATION | 5 | 7,079.00 | 7,079.00 | ✓ |
| 2 - Main/275 | HVAC INSTALLATION | 8 | 64,467.00 | 64,467.00 | ✓ |
| 2 - Main/276 | HVAC INSTALLATION | 15 | 14,636,106.00 | 14,636,106.00 | ✓ |
| 2 - Main/277 | HVAC INSTALLATION | 20 | 314,415.00 | 314,415.00 | ✓ |
| 2 - Main/278 | HVAC INSTALLATION | 21 | 248,905.00 | 248,905.00 | ✓ |
| 2 - Main/279 | HVAC INSTALLATION | 22 | 86,982.00 | 86,982.00 | ✓ |
| 2 - Main/280 | HVAC INSTALLATION | 20 | 169,694.00 | 169,694.00 | ✓ |
| 2 - Main/281 | HVAC INSTALLATION | 14 | 615,346.00 | 615,346.00 | ✓ |
| 2 - Main/282 | HVAC INSTALLATION | 17 | 94,916.00 | 94,916.00 | ✓ |
| 2 - Main/283 | HVAC INSTALLATION | 12 | 806,741.00 | 806,741.00 | ✓ |
| 2 - Main/284 | HVAC INSTALLATION | 13 | 1,602,928.00 | 1,602,928.00 | ✓ |
| 2 - Main/285 | HVAC INSTALLATION | 13 | 1,634,623.00 | 1,634,623.00 | ✓ |
| 2 - Main/286 | HVAC INSTALLATION | 11 | 379,482.00 | 379,482.00 | ✓ |
| 2 - Main/287 | HVAC INSTALLATION | 13 | 127,755.00 | 127,755.00 | ✓ |
| 2 - Main/288 | HVAC INSTALLATION | 14 | 140,228.00 | 140,228.00 | ✓ |
| 2 - Main/289 | HVAC INSTALLATION | 12 | 117,277.00 | 117,277.00 | ✓ |
| 2 - Main/290 | HVAC INSTALLATION | 7 | 90,165.00 | 90,165.00 | ✓ |
| 2 - Main/291 | LPG INSTALLATION | 1 | 0.00 | 0.00 | ✓ |
| 2 - Main/292 | LPG INSTALLATION | 10 | 0.00 | 0.00 | ✓ |
| 2 - Main/293 | LPG INSTALLATION | 14 | 5,458,814.00 | 5,458,814.00 | ✓ |
| 2 - Main/294 | LPG INSTALLATION | 5 | 0.00 | 0.00 | ✓ |
| 2 - Main/295 | SUNDRIES | 9 | 5,182,909.00 | 5,182,909.00 | ✓ |
| 2 - Main/296 | SUNDRIES | 1 | 83,902.00 | 83,902.00 | ✓ |
| 2 - Main/297 | WORK INCIDENTAL AND BWIC | 9 | 314,631.00 | 314,631.00 | ✓ |
| 2 - Main/298 | WORK INCIDENTAL AND BWIC | 3 | 4,901,091.00 | 4,901,091.00 | ✓ |
| 2 - Main/299 | GENERALLY | 13 | 15,232,423.00 | 15,232,423.00 | ✓ |
| 2 - Main/300 | POWER INSTALLATION | 6 | 34,134.00 | 34,134.00 | ✓ |
| 2 - Main/301 | POWER INSTALLATION | 16 | 77,096.00 | 77,096.00 | ✓ |
| 2 - Main/302 | POWER INSTALLATION | 13 | 71,800.00 | 71,800.00 | ✓ |
| 2 - Main/303 | POWER INSTALLATION | 15 | 281,333.00 | 281,333.00 | ✓ |
| 2 - Main/304 | POWER INSTALLATION | 16 | 383,435.00 | 383,435.00 | ✓ |
| 2 - Main/305 | POWER INSTALLATION | 10 | 90,279.00 | 90,279.00 | ✓ |
| 2 - Main/306 | POWER INSTALLATION | 10 | 195,070.00 | 195,070.00 | ✓ |
| 2 - Main/307 | POWER INSTALLATION | 13 | 454,776.00 | 454,776.00 | ✓ |
| 2 - Main/308 | POWER INSTALLATION | 11 | 274,336.00 | 274,336.00 | ✓ |
| 2 - Main/309 | POWER INSTALLATION | 14 | 14,160.00 | 14,160.00 | ✓ |
| 2 - Main/310 | POWER INSTALLATION | 12 | 19,422.00 | 19,422.00 | ✓ |
| 2 - Main/311 | POWER INSTALLATION | 15 | 48,144.00 | 48,144.00 | ✓ |
| 2 - Main/312 | POWER INSTALLATION | 21 | 67,543.00 | 67,543.00 | ✓ |
| 2 - Main/313 | POWER INSTALLATION | 22 | 44,933.00 | 44,933.00 | ✓ |
| 2 - Main/314 | POWER INSTALLATION | 22 | 56,889.00 | 56,889.00 | ✓ |
| 2 - Main/315 | POWER INSTALLATION | 22 | 32,683.00 | 32,683.00 | ✓ |
| 2 - Main/316 | POWER INSTALLATION | 21 | 82,124.00 | 82,124.00 | ✓ |
| 2 - Main/317 | POWER INSTALLATION | 14 | 244,755.00 | 244,755.00 | ✓ |
| 2 - Main/318 | POWER INSTALLATION | 15 | 58,506.00 | 58,506.00 | ✓ |
| 2 - Main/319 | POWER INSTALLATION | 17 | 130,928.00 | 130,928.00 | ✓ |
| 2 - Main/320 | POWER INSTALLATION | 17 | 169,687.00 | 169,687.00 | ✓ |
| 2 - Main/321 | POWER INSTALLATION | 15 | 212,268.00 | 212,268.00 | ✓ |
| 2 - Main/322 | POWER INSTALLATION | 15 | 146,853.00 | 146,853.00 | ✓ |
| 2 - Main/323 | POWER INSTALLATION | 16 | 95,844.00 | 95,844.00 | ✓ |
| 2 - Main/324 | POWER INSTALLATION | 16 | 176,449.00 | 176,449.00 | ✓ |
| 2 - Main/325 | POWER INSTALLATION | 19 | 81,389.00 | 81,389.00 | ✓ |
| 2 - Main/326 | POWER INSTALLATION | 14 | 225,645.00 | 225,645.00 | ✓ |
| 2 - Main/327 | POWER INSTALLATION | 17 | 94,521.00 | 94,521.00 | ✓ |
| 2 - Main/328 | POWER INSTALLATION | 16 | 113,484.00 | 113,484.00 | ✓ |
| 2 - Main/329 | POWER INSTALLATION | 14 | 200,459.00 | 200,459.00 | ✓ |
| 2 - Main/330 | POWER INSTALLATION | 18 | 76,440.00 | 76,440.00 | ✓ |
| 2 - Main/331 | POWER INSTALLATION | 14 | 202,027.00 | 202,027.00 | ✓ |
| 2 - Main/332 | POWER INSTALLATION | 18 | 154,056.00 | 154,056.00 | ✓ |
| 2 - Main/333 | POWER INSTALLATION | 16 | 195,314.00 | 195,314.00 | ✓ |
| 2 - Main/334 | POWER INSTALLATION | 14 | 112,716.00 | 112,716.00 | ✓ |
| 2 - Main/335 | POWER INSTALLATION | 14 | 80,727.00 | 80,727.00 | ✓ |
| 2 - Main/336 | POWER INSTALLATION | 12 | 68,693.00 | 68,693.00 | ✓ |
| 2 - Main/337 | POWER INSTALLATION | 11 | 110,902.00 | 110,902.00 | ✓ |
| 2 - Main/338 | POWER INSTALLATION | 13 | 101,452.00 | 101,452.00 | ✓ |
| 2 - Main/339 | POWER INSTALLATION | 14 | 82,431.00 | 82,431.00 | ✓ |
| 2 - Main/340 | POWER INSTALLATION | 14 | 69,651.00 | 69,651.00 | ✓ |
| 2 - Main/341 | POWER INSTALLATION | 15 | 92,577.00 | 92,577.00 | ✓ |
| 2 - Main/342 | POWER INSTALLATION | 15 | 95,254.00 | 95,254.00 | ✓ |
| 2 - Main/343 | POWER INSTALLATION | 13 | 129,990.00 | 129,990.00 | ✓ |
| 2 - Main/344 | POWER INSTALLATION | 14 | 120,660.00 | 120,660.00 | ✓ |
| 2 - Main/345 | POWER INSTALLATION | 13 | 331,800.00 | 331,800.00 | ✓ |
| 2 - Main/346 | POWER INSTALLATION | 14 | 283,624.00 | 283,624.00 | ✓ |
| 2 - Main/347 | POWER INSTALLATION | 11 | 425,611.00 | 425,611.00 | ✓ |
| 2 - Main/348 | POWER INSTALLATION | 14 | 35,345.00 | 35,345.00 | ✓ |
| 2 - Main/349 | POWER INSTALLATION | 14 | 25,959.00 | 25,959.00 | ✓ |
| 2 - Main/350 | POWER INSTALLATION | 14 | 30,549.00 | 30,549.00 | ✓ |
| 2 - Main/351 | POWER INSTALLATION | 17 | 326,417.00 | 326,417.00 | ✓ |
| 2 - Main/352 | POWER INSTALLATION | 21 | 44,472.00 | 44,472.00 | ✓ |
| 2 - Main/353 | POWER INSTALLATION | 20 | 71,468.00 | 71,468.00 | ✓ |
| 2 - Main/354 | POWER INSTALLATION | 20 | 88,468.00 | 88,468.00 | ✓ |
| 2 - Main/355 | POWER INSTALLATION | 20 | 86,224.00 | 86,224.00 | ✓ |
| 2 - Main/356 | POWER INSTALLATION | 16 | 62,879.00 | 62,879.00 | ✓ |
| 2 - Main/357 | POWER INSTALLATION | 19 | 160,611.00 | 160,611.00 | ✓ |
| 2 - Main/358 | POWER INSTALLATION | 13 | 109,474.00 | 109,474.00 | ✓ |
| 2 - Main/359 | POWER INSTALLATION | 15 | 112,395.00 | 112,395.00 | ✓ |
| 2 - Main/360 | POWER INSTALLATION | 14 | 382,786.00 | 382,786.00 | ✓ |
| 2 - Main/361 | POWER INSTALLATION | 13 | 751,774.00 | 751,774.00 | ✓ |
| 2 - Main/362 | POWER INSTALLATION | 10 | 1,036,919.00 | 1,036,919.00 | ✓ |
| 2 - Main/363 | POWER INSTALLATION | 10 | 4,738,764.00 | 4,738,764.00 | ✓ |
| 2 - Main/364 | POWER INSTALLATION | 15 | 2,203,059.00 | 2,203,059.00 | ✓ |
| 2 - Main/365 | POWER INSTALLATION | 22 | 9,916.00 | 9,916.00 | ✓ |
| 2 - Main/366 | POWER INSTALLATION | 17 | 0.00 | 0.00 | ✓ |
| 2 - Main/367 | POWER INSTALLATION | 17 | 0.00 | 0.00 | ✓ |
| 2 - Main/368 | POWER INSTALLATION | 16 | 0.00 | 0.00 | ✓ |
| 2 - Main/369 | POWER INSTALLATION | 16 | 0.00 | 0.00 | ✓ |
| 2 - Main/370 | POWER INSTALLATION | 18 | 0.00 | 0.00 | ✓ |
| 2 - Main/371 | POWER INSTALLATION | 15 | 509,830.00 | 509,830.00 | ✓ |
| 2 - Main/372 | POWER INSTALLATION | 14 | 9,326,877.00 | 9,326,877.00 | ✓ |
| 2 - Main/373 | POWER INSTALLATION | 16 | 9,271,261.00 | 9,271,261.00 | ✓ |
| 2 - Main/374 | POWER INSTALLATION | 18 | 3,772,209.00 | 3,772,209.00 | ✓ |
| 2 - Main/375 | POWER INSTALLATION | 22 | 317,108.00 | 317,108.00 | ✓ |
| 2 - Main/376 | POWER INSTALLATION | 22 | 304,893.00 | 304,893.00 | ✓ |
| 2 - Main/377 | POWER INSTALLATION | 22 | 359,914.00 | 359,914.00 | ✓ |
| 2 - Main/378 | POWER INSTALLATION | 22 | 304,865.00 | 304,865.00 | ✓ |
| 2 - Main/379 | POWER INSTALLATION | 22 | 281,377.00 | 281,377.00 | ✓ |
| 2 - Main/380 | POWER INSTALLATION | 22 | 396,445.00 | 396,445.00 | ✓ |
| 2 - Main/381 | POWER INSTALLATION | 20 | 288,280.00 | 288,280.00 | ✓ |
| 2 - Main/382 | POWER INSTALLATION | 22 | 311,685.00 | 311,685.00 | ✓ |
| 2 - Main/383 | POWER INSTALLATION | 22 | 320,519.00 | 320,519.00 | ✓ |
| 2 - Main/384 | POWER INSTALLATION | 22 | 317,108.00 | 317,108.00 | ✓ |
| 2 - Main/385 | POWER INSTALLATION | 22 | 307,886.00 | 307,886.00 | ✓ |
| 533 blocks | 2,537,676,914.00 | ||||
Source verification
Independent checks of the imported result against the raw workbook.✓ item count
Independent re-count matches on all 4 sheets (8256 items).
✓ qty integrity
Quantity sums match the raw cells on every sheet.
✓ amount integrity
Amount sums match the raw cells on every sheet.
✓ row coverage
Every money-bearing row accounted for: items, block totals, 495 summary re-statements (excluded — would double-count), 2 post-summary annex rows (recorded, outside the bill's money story).
✓ mirror
Cell-for-cell fidelity: descriptions, codes, and the number/text/empty state of every qty, rate and amount match the raw cells (33024 cells compared).
✓ summary map
2 summary sheets, 2 entries: 2 matched to imported totals · imported but absent from every summary: 2 - Main, 3 - Ext
✓ summary self check
The workbook's own summaries are internally consistent (6 checks across 3 sheets).
✓ section tie
25/27 declared sections tie to the cent · declared but not in this import: 1/GR “GENERAL REQUIREMENTS FOR THE WHOLE OF TH” declared 270300000.00; 4/PS “PROVISIONAL SUMS” declared 4950000.00 · 117 lines carry no section reference
✓ zone tie
band identified arithmetically as BASEMENTS · GF & PODIUM · TOWER 1 · TOWER 2 · TOWER 3 · TOWER 4 (the identity held on 386/388 sampled priced rows) · 150/150 declared zone cells tie · the bidder keeps their own check on 8133 rows: we agree on 7570, differ on 0 (557 not comparable because the Amount cell prints words — their formula compares a number against text, which Excel makes FALSE whatever the arithmetic; 6 because a zone cell prints words) · 54 of 7960 priced rows do not add across their zones
✓ tender tie
The tender figure 2537676914.00 equals this import exactly.
✓ amount in words
The tender figure written in words reads back to 2537676914.00 — the same number the sheet prints.
✓ summary echo
4/4 sheet totals re-stated verbatim by the workbook's own summary sheets — the source confirms our totals.