BOQAgent
AED · ADDRESS RESIDENCES ZABEEL

BOQ T3 — GR1, 2 - Main, 3 - Ext, Bill 4

BOQ T3 — GR1, 2 - Main, 3 - Ext, Bill 4.xlsxNeeds review
Bill total
2,537,676,914.00
+0.01 vs qty×rate
Needs review
807
90%
1 error · 806 to acknowledge
Reconciliation
Totals reconcile
LINEPAGESECTIONZONEBILLSUMMARY
Source verification
12/12
independent proofs against the raw file
Size
8,256
533 collection blocks · 4 sheets

1 line carries no item reference, though every other line on its page does

error

Either the reference was missed in the source, or the row is not an item.

  • Supply and installation by Others: Contractor to allow for Co-ordination, attendance and builders work
1 unit measured50,850.00 carriedlargest: 50,850.00 2/L/2

586 lines print words where a figure belongs

to answer

Accept the wording as a class, or put it to the bidder.

  • Where any item, clause or sub-clause of the General Requirements has not been priced, it will be deemed that the value of such item, clause or sub-clause is included in the rates for measured items elsewhere in the Bills of Quantities.
  • The rates and prices in these Bills of Quantities are fixed for the duration of the Contract and shall not be subject to any adjustment in respect of rise or fall in the cost of labour, materials, plant, equipment, transport or any other matters affecting the cost of execution of the Contract.
  • References hereunder to the Schedule of Project Requirements (SOPR) are intended solely to direct the Contractor to the specific requirements of the Schedule of Project Requirements in respect of a particular item and do not in any way limit the scope of such item to the requirements of the Schedule of Project Requirements.
52,231.72 units measuredlargest: 13,522 m 2/Q/173 A

209 lines carry no rate, so nothing reaches the totals

to answer

Say why the bidder left them unpriced, or ask them to price them.

  • Any items that may not be covered elsewhere in the Bills of Quantities which the Tenderer deemed to be necessary in order to carry out the works in full compliance with the SOPR must be itemised and price below
  • Allow for any other works which are not included above and which are required to complete the Site Work in accordance with the Specification and the Drawings (Tenderer to list below):
  • Columns
91,900.88 units measuredlargest: 25,649 m2 3/R/1 B

8 lines repeat an item letter already used under the same heading

to answer

Kept exactly as printed — confirm which line the bidder meant.

  • Primary Structural Steel (Non Fire Rated) to inaccessible areas on façade (Dummy Balconies) and Canopies Provisional Qty
  • Columns; UB 533 x 210 x 82
  • Columns; UC 203 x 203 x 60
9,881,318.76 carriedlargest: 10,609,104.72 2/E/11 ADD

7 lines have no heading above them while their neighbours do

to answer

A governing heading may have been missed when the page was read.

  • To powder room
  • To powder room
  • To powder room
2,301 units measured423,099.00 carriedlargest: 356,655.00 2/K/13 ADD

1 line restarts its lettering without a new heading

to answer

Usually a heading the page prints that was not picked up.

  • Coupling beams
812 units measured443,352.00 carriedlargest: 443,352.00 2/C/3 A
ItemDescriptionQtyUnitRateAmountState
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/1
0/3 clear
0.00 Σ lines 0.00 printed
Generally
Where any item, clause or sub-clause of the General Requirements has not been priced, it will be deemed that the value of such item, clause or sub-clause is included in the rates for measured items elsewhere in the Bills of Quantities.
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
Generally
The rates and prices in these Bills of Quantities are fixed for the duration of the Contract and shall not be subject to any adjustment in respect of rise or fall in the cost of labour, materials, plant, equipment, transport or any other matters affecting the cost of execution of the Contract.
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
Generally
References hereunder to the Schedule of Project Requirements (SOPR) are intended solely to direct the Contractor to the specific requirements of the Schedule of Project Requirements in respect of a particular item and do not in any way limit the scope of such item to the requirements of the Schedule of Project Requirements.
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/2
0/5 clear
0.00 Σ lines
A1.1- Schedule of Clauses
4 Contractor's All Risk Policy
REVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemBy EmployerNeeds review
A1.1- Schedule of Clauses
6 Professional Indemnity insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
7 Third Party liability insurance
REVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemBy EmployerNeeds review
A1.1- Schedule of Clauses
8 Plant and Contractor's Equipment Insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
9 Motor Vehicle Third Party and Passenger Liability Insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/3
0/1 clear
0.00 Σ lines 0.00 printed
A1.1- Schedule of Clauses
The Contractor shall price hereunder any special requirements related to the specification clauses
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/4
0/2 clear
0.00 Σ lines
A3 - Restrictions
4 The Maintenance of existing services on, under or over the Site
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemExcludedNeeds review
A3 - Restrictions
5 The Execution of the Works in the required specific order, sections or phases
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/5
0/4 clear
0.00 Σ lines
1 Office for the Contract administrators
i. Establishment
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
1 Office for the Contract administrators
ii. Maintenance
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
1 Office for the Contract administrators
iii. Removal
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
1 Office for the Contract administrators
5 Transport of workpeople
REVIEWAmount column prints "Included in A5.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A5.1Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/9
0/3 clear
0.00 Σ lines
3 Screens and guardrails
i. Establishment (Fixed Charges)
REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A4.1Needs review
3 Screens and guardrails
ii. Maintenance (Time Related Charges)
REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A4.1Needs review
3 Screens and guardrails
iii. Removal (Fixed Charges)
REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A4.1Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/11
0/1 clear
0.00 Σ lines
A8.1 An item shall be given for temporary works including design, which shall include:
3 Pumping
REVIEWAmount column prints "Included in Site Works (Bill Nr 2)" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in Site Works (Bill Nr 2)Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/12
0/5 clear
0.00 Σ lines
A9.1 An item shall be given for temporary works, which shall include:
5 - Traffic regulations
REVIEWAmount column prints "Included in A8.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A8.1Needs review
A9.1 An item shall be given for temporary works, which shall include:
7 - Drying the Works
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
A9.1 An item shall be given for temporary works, which shall include:
8 - Control of noise and pollution
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
A9.1 An item shall be given for temporary works, which shall include:
9 - All Statutory obligations
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
4 - Off site storage
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/13
0/8 clear
0.00 Σ lines
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
6 - Specialist Third Party Testing, Commissioning and Certification
REVIEWAmount column prints "Included in A9.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A9.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
12 - Internet connection requirements on site
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
13 - Precautions against Fire
REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A4.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
15 - Project Health, Safety, Environment and Security Guidelines
REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A4.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
16 - General cleaning and waste disposal during construction
REVIEWAmount column prints "Included in A9.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A9.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
19 - Contract Spares/Attic stock
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemExcludedNeeds review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
20 - As-built drawings
REVIEWAmount column prints "Included in BIM" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in BIMNeeds review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
22 - Warranties
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS · GR1/15
0/1 clear
0.00 Σ lines 0.00 printed
Additional Items
Any items that may not be covered elsewhere in the Bills of Quantities which the Tenderer deemed to be necessary in order to carry out the works in full compliance with the SOPR must be itemised and price below
REVIEWThe source prints neither a quantity nor a rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
ItemNeeds review
2/B · 2/B/3 · VARIANCE IN QUANTITY · 2 - Main/3
0/1 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Site Work in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
2/C · 2/C/2 · POURED CONCRETE · 2 - Main/5
0/1 clear
0.00 Σ lines
Reinforced concrete; concrete grade C50/60
Columns
REVIEW2,734 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2,734m30.00Needs review
2/C · 2/C/3 · POURED CONCRETE · 2 - Main/6
0/2 clear
443,352.00 Σ lines
Reinforced concrete; concrete grade C56/70
Coupling beams
REVIEWReference sequence restarts at "A" on 2 - Main/6 without a heading change — a governing heading may have been missed above it.
812m3546.00443,352.00Needs review
Reinforced concrete; concrete grade C70/85
Blade wall; 400mm thick
REVIEW1,721 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1,721m30.00Needs review
2/C · 2/C/6 · REINFORCEMENT · 2 - Main/9
0/1 clear
0.00 Σ lines
Reinforcing steel bars; high yield deformed; grade 60
Planter wall
REVIEW8.88 t measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
8.88t0.00Needs review
2/C · 2/C/9 · PRESTRESSED CONCRETE · 2 - Main/12
0/1 clear
0.00 Σ lines
Post tensioning (PT) system; comprise of design, approvals including prestressing steel, anchorages, plates, ducts, grouts, protection, accessories and all ancillary works as necessary
PT system; to post tensioned slab
REVIEWAmount column prints "Please refer ADD items" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1,425.72tPlease refer ADD itemsNeeds review
2/C · 2/C/11 · VARIANCE IN QUANTITY · 2 - Main/14
0/1 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Concrete Work in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
2/D · 2/D/2 · SUNDRIES · 2 - Main/16
0/4 clear
0.00 Σ lines 0.00 printed
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Dowelled control joints
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Dowelled control joints (RATE ONLY)
REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
mRate OnlyNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Isolation joints
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Isolation joints (RATE ONLY)
REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
mRate OnlyNeeds review
2/D · 2/D/3 · VARIANCE IN QUANTITY · 2 - Main/17
0/1 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Masonry in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
2/E · 2/E/9 · NON-STRUCTURAL METALWORK · 2 - Main/26
0/1 clear
0.00 Σ lines
Stainless steel ladders to water tanks; type AM-451; wall mounted stainless steel with safety cage; including finishes, frames, supports, fixings, accessories and all ancillary works as necessary
Type 2; size 960 x 690 x 10300mm high
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
2/E · 2/E/11 · VARIANCE IN QUANTITY · 2 - Main/28
0/9 clear
9,881,318.76 Σ lines
Allow for any other works which are not included above and which are required to complete the Metalwork in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0ItemNeeds review
Primary Structural Steel (Non Fire Rated) to inaccessible areas on façade (Dummy Balconies) and Canopies Provisional Qty
REVIEWItem code "ADD" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
552.04t19,218.0010,609,104.72Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; UB 533 x 210 x 82
REVIEWItem code "A" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-5.69t21,769.00-123,865.61Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; UC 203 x 203 x 60
REVIEWItem code "B" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
4.6t21,769.00100,137.40Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; CHS 219 x 6.3
REVIEWItem code "C" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-0.28t21,769.00-6,095.32Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; SHS 150 x 150 x 6.3
REVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-0.44t21,769.00-9,578.36Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; SHS 120 x 120 x 6.3
REVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-0.03t21,769.00-653.07Needs review
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications
To ground floor and podium walls
REVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-64m21,133.00-72,512.00Needs review
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications
To tower walls
REVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-543m21,133.00-615,219.00Needs review
2/F · 2/F/24 · VARIANCE IN QUANTITY · 2 - Main/52
0/9 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Woodwork in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
Vanity counters; including countertop, forming of holes, front/side panels, drawers, hardware, finishes, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
To powder room
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed.
0.00Needs review
Veneered shelves; including finishes, fixings, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
To powder room
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed.
0.00Needs review
Cabinets with veneered open shelf; including concealed light (measured separately), front/side panels, hardware, finishes, fixings, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
To powder room
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed.
0.00Needs review
Wardrobes; comprising 18mm thick MDF shelving and glass shutter; including MDF backing, carcass, frames, supports, front/side/back panels, doors, shelves, drawers, concealed light (measured separately), hardware, finishes, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
2/G · 2/G/4 · VARIANCE IN QUANTITY · 2 - Main/56
0/1 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Thermal and Moisture Protection in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
2/H · 2/H/16 · VARIANCE IN QUANTITY · 2 - Main/72
0/4 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Doors and Windows in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0ItemNeeds review
Double glazed vision panel screen; Type V1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications
REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Needs review
Double glazed vision panel screen; Type V2; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 8mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications
REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Needs review
Double glazed spandrel panel screen; Type S1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, plaster board, insulation, fixings, fittings, accessories and all ancillary works as per drawings and specifications
REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Needs review
2/J · 2/J/9 · CEILING FINISHES · 2 - Main/81
0/2 clear
0.00 Σ lines
Gypsum board tile ceiling system; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories
Extra over for access panel
REVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemNot ApplicableNeeds review
Concealed grid aluminium tile ceiling system; demountable, perforated aluminium tiles; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories
Extra over for access panel
REVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemNot ApplicableNeeds review
2/J · 2/J/17 · VARIANCE IN QUANTITY · 2 - Main/89
0/1 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Finishes in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
2/K · 2/K/1 · TOILET ACCESSORIES · 2 - Main/90
0/1 clear
0.00 Σ lines
Common Areas
Type SAN-711; toilet paper holder
REVIEW9 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
9Nr.0.00Needs review
2/K · 2/K/5 · SIGNAGE AND WAYFINDING · 2 - Main/94
0/1 clear
0.00 Σ lines
Internal Signage
Retail sign by others
REVIEWAmount column prints "By Others" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
6Nr.By OthersNeeds review
2/K · 2/K/6 · PARKING ACCESSORIES · 2 - Main/95
0/2 clear
0.00 Σ lines
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary
Type EXH-301; 100mm high
REVIEW2,969 m2 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2,969m20.00Needs review
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary
150mm high; to ramps
REVIEW609 m measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
609m0.00Needs review
2/K · 2/K/13 · VARIANCE IN QUANTITY · 2 - Main/102
0/6 clear
356,655.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Accessories in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Tempered mirror; type GL-101; 6mm thick clear mirror with metal frame; including, backing, supports, finishes, accessories and all ancillary works as necessary
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
00.00Needs review
Shower glass partition; fixed glass with doors; glass; 10mm thick; including ironmongery, fixings, accessories and all ancillary works as necessary
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
00.00Needs review
Clear Glass
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"Clear Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed.
00.00Needs review
Fluted Tinted Glass
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"Fluted Tinted Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed.
00.00Needs review
Precast Concrete kerb
REVIEW"Precast Concrete kerb" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed.
2,301m155.00356,655.00Needs review
2/L · 2/L/1 · WHITE GOODS · 2 - Main/103
0/9 clear
0.00 Σ lines
White goods; including accessories and all ancillary works as necessary
Type WG-111; freestanding cooker
REVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
30Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-112; freestanding fridge
REVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
30Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-113; freestanding freezer
REVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
30Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-114; freestanding dishwasher
REVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
30Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-116; coffee machine
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-117; tv screen
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-118; tv screen
REVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
5Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-119; water dispenser
REVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
8Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-120; tv screen
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
2/L · 2/L/2 · GYM EQUIPMENT · 2 - Main/104
0/26 clear
50,850.00 Σ lines 50,850.00 printed1 errors
Supply and installation by Others: Contractor to allow for Co-ordination, attendance and builders work
ERRORNo item reference on 2 - Main/104. Every priced line carries a printed reference (A, B, C…) — either the reference was missed, or this row is not an item.
1Item50,850.0050,850.00Error
Type EQ-101; run 19" excite live
REVIEW7 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
7Nr.0.00Needs review
Type EQ-102; climb 16" excite live
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-103; synchro ar 16" excite live
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-104; technogym bike
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-105; skillrow
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-106; lower back fitness bench
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Type EQ-107; yoga mat
REVIEW9 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
9Nr.0.00Needs review
Type EQ-108; crunch bench press
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-109; multi-power
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-110; adjustable bench
REVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
5Nr.0.00Needs review
Type EQ-111; two tier dumbbell rack
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-112; dumbbells (10 pairs)
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-113; dual leg curl/leg extension selection 700
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-114; lat machine selection 700
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-115; shoulder press-selection 700
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-116; chest press-selection 700
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-117; skill tools storage
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-118; universe wall 2 virtual
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-119; vario 16" excite live
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-120; skill up
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-121; skillmill
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-122; skillrun unity 7000
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-123; plyobox
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-124; punching bag
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-125; leg press selection 700
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
2/L · 2/L/3 · BUILDING MANAGEMENT UNIT (BMU) · 2 - Main/105
0/1 clear
0.00 Σ lines
Galvanized mild steel running track; including galvanized steel base plates, clip ears, stainless steel A4/80 u-bolts, high-strength grout, fixings; complete
BMU tracks at 4000mm center to center
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
183mIncludedNeeds review
loading more… 150 of 807 lines rendered
ItemDescriptionQtyUnitRateAmountState
GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS
0/33 clear
0.00 Σ lines
Generally
Where any item, clause or sub-clause of the General Requirements has not been priced, it will be deemed that the value of such item, clause or sub-clause is included in the rates for measured items elsewhere in the Bills of Quantities.
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
Generally
The rates and prices in these Bills of Quantities are fixed for the duration of the Contract and shall not be subject to any adjustment in respect of rise or fall in the cost of labour, materials, plant, equipment, transport or any other matters affecting the cost of execution of the Contract.
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
Generally
References hereunder to the Schedule of Project Requirements (SOPR) are intended solely to direct the Contractor to the specific requirements of the Schedule of Project Requirements in respect of a particular item and do not in any way limit the scope of such item to the requirements of the Schedule of Project Requirements.
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
4 Contractor's All Risk Policy
REVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemBy EmployerNeeds review
A1.1- Schedule of Clauses
6 Professional Indemnity insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
7 Third Party liability insurance
REVIEWAmount column prints "By Employer" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemBy EmployerNeeds review
A1.1- Schedule of Clauses
8 Plant and Contractor's Equipment Insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
9 Motor Vehicle Third Party and Passenger Liability Insurance
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A1.1- Schedule of Clauses
The Contractor shall price hereunder any special requirements related to the specification clauses
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
A3 - Restrictions
4 The Maintenance of existing services on, under or over the Site
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemExcludedNeeds review
A3 - Restrictions
5 The Execution of the Works in the required specific order, sections or phases
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
1 Office for the Contract administrators
i. Establishment
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
1 Office for the Contract administrators
ii. Maintenance
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
1 Office for the Contract administrators
iii. Removal
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
1 Office for the Contract administrators
5 Transport of workpeople
REVIEWAmount column prints "Included in A5.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A5.1Needs review
3 Screens and guardrails
i. Establishment (Fixed Charges)
REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A4.1Needs review
3 Screens and guardrails
ii. Maintenance (Time Related Charges)
REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A4.1Needs review
3 Screens and guardrails
iii. Removal (Fixed Charges)
REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A4.1Needs review
A8.1 An item shall be given for temporary works including design, which shall include:
3 Pumping
REVIEWAmount column prints "Included in Site Works (Bill Nr 2)" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in Site Works (Bill Nr 2)Needs review
A9.1 An item shall be given for temporary works, which shall include:
5 - Traffic regulations
REVIEWAmount column prints "Included in A8.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A8.1Needs review
A9.1 An item shall be given for temporary works, which shall include:
7 - Drying the Works
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
A9.1 An item shall be given for temporary works, which shall include:
8 - Control of noise and pollution
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
A9.1 An item shall be given for temporary works, which shall include:
9 - All Statutory obligations
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
4 - Off site storage
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
6 - Specialist Third Party Testing, Commissioning and Certification
REVIEWAmount column prints "Included in A9.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A9.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
12 - Internet connection requirements on site
REVIEWAmount column prints "Included in A7.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A7.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
13 - Precautions against Fire
REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A4.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
15 - Project Health, Safety, Environment and Security Guidelines
REVIEWAmount column prints "Included in A4.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A4.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
16 - General cleaning and waste disposal during construction
REVIEWAmount column prints "Included in A9.1" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in A9.1Needs review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
19 - Contract Spares/Attic stock
REVIEWAmount column prints "Excluded" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemExcludedNeeds review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
20 - As-built drawings
REVIEWAmount column prints "Included in BIM" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncluded in BIMNeeds review
A9.2 Particulars shall be given where the nature or extent of the sundry items is not at the discretion of the Contractor.
22 - Warranties
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
ItemIncludedNeeds review
Additional Items
Any items that may not be covered elsewhere in the Bills of Quantities which the Tenderer deemed to be necessary in order to carry out the works in full compliance with the SOPR must be itemised and price below
REVIEWThe source prints neither a quantity nor a rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
ItemNeeds review
GENERALLY
0/42 clear
10,965,759.72 Σ lines
Allow for any other works which are not included above and which are required to complete the Site Work in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Concrete Work in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Masonry in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Metalwork in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0ItemNeeds review
Primary Structural Steel (Non Fire Rated) to inaccessible areas on façade (Dummy Balconies) and Canopies Provisional Qty
REVIEWItem code "ADD" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
552.04t19,218.0010,609,104.72Needs review
Allow for any other works which are not included above and which are required to complete the Woodwork in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
Vanity counters; including countertop, forming of holes, front/side panels, drawers, hardware, finishes, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
To powder room
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed.
0.00Needs review
Veneered shelves; including finishes, fixings, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
To powder room
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed.
0.00Needs review
Cabinets with veneered open shelf; including concealed light (measured separately), front/side panels, hardware, finishes, fixings, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
To powder room
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed.
0.00Needs review
Wardrobes; comprising 18mm thick MDF shelving and glass shutter; including MDF backing, carcass, frames, supports, front/side/back panels, doors, shelves, drawers, concealed light (measured separately), hardware, finishes, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
Allow for any other works which are not included above and which are required to complete the Thermal and Moisture Protection in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Doors and Windows in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0ItemNeeds review
Double glazed vision panel screen; Type V1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications
REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Needs review
Double glazed vision panel screen; Type V2; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 8mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications
REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Needs review
Double glazed spandrel panel screen; Type S1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, plaster board, insulation, fixings, fittings, accessories and all ancillary works as per drawings and specifications
REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Needs review
Allow for any other works which are not included above and which are required to complete the Finishes in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Accessories in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Tempered mirror; type GL-101; 6mm thick clear mirror with metal frame; including, backing, supports, finishes, accessories and all ancillary works as necessary
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
00.00Needs review
Shower glass partition; fixed glass with doors; glass; 10mm thick; including ironmongery, fixings, accessories and all ancillary works as necessary
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
00.00Needs review
Clear Glass
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"Clear Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed.
00.00Needs review
Fluted Tinted Glass
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"Fluted Tinted Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed.
00.00Needs review
Precast Concrete kerb
REVIEW"Precast Concrete kerb" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed.
2,301m155.00356,655.00Needs review
Allow for any other works which are not included above and which are required to complete the Equipment in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Furnishings in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Conveying Systems in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Mechanical Engineering Installations in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Electrical Engineering Installations in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Site Works in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Concrete Works in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Metalwork in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Thermal and Moisture Protection in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Finishes in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Accessories in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Equipment in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Furnishing in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Special Construction in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Mechanical Engineering Installations in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Electrical Engineering Installations in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
POURED CONCRETE
0/3 clear
443,352.00 Σ lines
Reinforced concrete; concrete grade C50/60
Columns
REVIEW2,734 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2,734m30.00Needs review
Reinforced concrete; concrete grade C56/70
Coupling beams
REVIEWReference sequence restarts at "A" on 2 - Main/6 without a heading change — a governing heading may have been missed above it.
812m3546.00443,352.00Needs review
Reinforced concrete; concrete grade C70/85
Blade wall; 400mm thick
REVIEW1,721 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1,721m30.00Needs review
REINFORCEMENT
0/1 clear
0.00 Σ lines
Reinforcing steel bars; high yield deformed; grade 60
Planter wall
REVIEW8.88 t measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
8.88t0.00Needs review
PRESTRESSED CONCRETE
0/1 clear
0.00 Σ lines
Post tensioning (PT) system; comprise of design, approvals including prestressing steel, anchorages, plates, ducts, grouts, protection, accessories and all ancillary works as necessary
PT system; to post tensioned slab
REVIEWAmount column prints "Please refer ADD items" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1,425.72tPlease refer ADD itemsNeeds review
SUNDRIES
0/42 clear
66,444.00 Σ lines
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Dowelled control joints
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Dowelled control joints (RATE ONLY)
REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
mRate OnlyNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Isolation joints
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Isolation joints (RATE ONLY)
REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
mRate OnlyNeeds review
Allow for providing shop drawings, as built drawings and material submittal approvals
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for providing catalogues, operation and maintenance manuals
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for labeling, tagging of equipment with their related control panel and components as specified
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for testing and commissioning the complete installation
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for all connections to existing services mains
REVIEWAmount column prints "Included within plot" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncluded within plotNeeds review
Allow for providing spares for Mechanical Engineering Installations
REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0ItemNeeds review
Allow for all supports, fixings, anchors and insulating blocks where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for all identification including painting, marking and labeling
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed installation
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for providing spares for the Electrical Engineering Installation
REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0ItemNeeds review
Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for planting edging
REVIEWUnit "Item" with quantity 0 and the amount 66,444.00 repeated in the Rate column — priced as a whole item, so quantity × rate is not applied. The amount stands as printed.
REVIEW"Allow for planting edging" has no heading context while other items on 3 - Ext/4 do — a governing heading may have been missed.
0Item66,444.0066,444.00Needs review
Allow for the provision of water only for maintenance purpose during defect liability period
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for all identification including painting, marking and labelling
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for inspection, testing and commissioning including all off-site and factory testing; inspections to demonstrate compliance with relevant specifications and standards; operating the completed installations; submitting all relevant test record sheets at the completion of the installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed installation
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for providing spares for the Mechanical Engineering Installation
REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0ItemNeeds review
Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for planning and coordinating with relevant statutory authorities and with all other trades
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for liaison with obtaining approvals and attendance on approved Authorities, other statutory bodies and service providers as required
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for supplying and fixing all brackets, clamps and other fixing devices including building in or cutting and pinning and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for training the Employer's Staff to operate and maintain the Mechanical Engineering Installations
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Mechanical Engineering Installations
Allow for all incidental work to the Mechanical Engineering Installations where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for earthing and bonding as specified; in particular all metal containments shall be
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for all supports, fixings, anchors and insulating blocks where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for all identification including painting, marking and labeling
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for providing in suitable quantities all special tools, operating handles and keys or other equipment necessary for installation, maintenance or operation of the completed installation
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Allow for providing spares for the Electrical Engineering Installation
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for providing comprehensive equipment documentation including operating instructions and maintenance manuals, record documents, warranties, guarantees, drawings and the like
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Electrical Engineering Installations
Allow for planning and coordinating with relevant statutory authorities and with all other trades
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Electrical Engineering Installations
Allow for liaison with obtaining approvals and attendance on DEWA, other statutory bodies and service providers as required
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Electrical Engineering Installations
Allow for marking the positions of and cutting or forming holes, mortices, chases or the like and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Electrical Engineering Installations
Allow for supplying and fixing all sleeves, frames and built-in fire stoppers for building into concrete structures and masonry walls
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Electrical Engineering Installations
Allow for supplying and fixing all brackets, clamps and other fixing devices including building in or cutting and pinning and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Electrical Engineering Installations
Allow for fire stopping all cables, conduit, trucking, cable tray and the like at penetrations through fire walls and other structures and making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Electrical Engineering Installations
Allow for all incidental work including factory finishing, fixing to all backgrounds by appropriate means and all making good
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Electrical Engineering Installations
Allow for training the Employer's Staff to operate and maintain the Electrical Engineering Installation
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Work Incidental to Electrical Engineering Installations
Allow for all incidental work to the Electrical Engineering Installation where not included above or elsewhere
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
NON-STRUCTURAL METALWORK
0/1 clear
0.00 Σ lines
Stainless steel ladders to water tanks; type AM-451; wall mounted stainless steel with safety cage; including finishes, frames, supports, fixings, accessories and all ancillary works as necessary
Type 2; size 960 x 690 x 10300mm high
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
VARIANCE IN QUANTITY
0/7 clear
-727,785.96 Σ lines
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; UB 533 x 210 x 82
REVIEWItem code "A" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-5.69t21,769.00-123,865.61Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; UC 203 x 203 x 60
REVIEWItem code "B" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
4.6t21,769.00100,137.40Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; CHS 219 x 6.3
REVIEWItem code "C" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-0.28t21,769.00-6,095.32Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; SHS 150 x 150 x 6.3
REVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-0.44t21,769.00-9,578.36Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; SHS 120 x 120 x 6.3
REVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-0.03t21,769.00-653.07Needs review
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications
To ground floor and podium walls
REVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-64m21,133.00-72,512.00Needs review
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications
To tower walls
REVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-543m21,133.00-615,219.00Needs review
CEILING FINISHES
0/2 clear
0.00 Σ lines
Gypsum board tile ceiling system; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories
Extra over for access panel
REVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemNot ApplicableNeeds review
Concealed grid aluminium tile ceiling system; demountable, perforated aluminium tiles; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories
Extra over for access panel
REVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemNot ApplicableNeeds review
TOILET ACCESSORIES
0/1 clear
0.00 Σ lines
Common Areas
Type SAN-711; toilet paper holder
REVIEW9 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
9Nr.0.00Needs review
SIGNAGE AND WAYFINDING
0/1 clear
0.00 Σ lines
Internal Signage
Retail sign by others
REVIEWAmount column prints "By Others" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
6Nr.By OthersNeeds review
PARKING ACCESSORIES
0/2 clear
0.00 Σ lines
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary
Type EXH-301; 100mm high
REVIEW2,969 m2 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2,969m20.00Needs review
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary
150mm high; to ramps
REVIEW609 m measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
609m0.00Needs review
WHITE GOODS
0/9 clear
0.00 Σ lines
White goods; including accessories and all ancillary works as necessary
Type WG-111; freestanding cooker
REVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
30Nr.0.00Needs review
loading more… 150 of 807 lines rendered
ItemDescriptionQtyUnitRateAmountState
Section 2/B · SECTION B - SITE WORKS · Page 2/B/1 - 2/B/4
0/1 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Site Work in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Section 2/C · SECTION C - CONCRETE WORKS · Page 2/C/1 - 2/C/12
0/6 clear
443,352.00 Σ lines
Reinforced concrete; concrete grade C50/60
Columns
REVIEW2,734 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2,734m30.00Needs review
Reinforced concrete; concrete grade C56/70
Coupling beams
REVIEWReference sequence restarts at "A" on 2 - Main/6 without a heading change — a governing heading may have been missed above it.
812m3546.00443,352.00Needs review
Reinforced concrete; concrete grade C70/85
Blade wall; 400mm thick
REVIEW1,721 m3 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1,721m30.00Needs review
Reinforcing steel bars; high yield deformed; grade 60
Planter wall
REVIEW8.88 t measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
8.88t0.00Needs review
Post tensioning (PT) system; comprise of design, approvals including prestressing steel, anchorages, plates, ducts, grouts, protection, accessories and all ancillary works as necessary
PT system; to post tensioned slab
REVIEWAmount column prints "Please refer ADD items" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
1,425.72tPlease refer ADD itemsNeeds review
Allow for any other works which are not included above and which are required to complete the Concrete Work in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Section 2/D · SECTION D - MASONRY · Page 2/D/1 - 2/D/4
0/5 clear
0.00 Σ lines
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Dowelled control joints
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Dowelled control joints (RATE ONLY)
REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
mRate OnlyNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Isolation joints
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemIncludedNeeds review
Joints in masonry; including fire resistant compressible joint filler, sealant, angle head restraints, telescopic, sleeved and/or debonded ties and the like
Isolation joints (RATE ONLY)
REVIEWAmount column prints "Rate Only" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
mRate OnlyNeeds review
Allow for any other works which are not included above and which are required to complete the Masonry in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Section 2/E · SECTION E - METALWORK · Page 2/E/1 - 2/E/12
0/10 clear
9,881,318.76 Σ lines
Stainless steel ladders to water tanks; type AM-451; wall mounted stainless steel with safety cage; including finishes, frames, supports, fixings, accessories and all ancillary works as necessary
Type 2; size 960 x 690 x 10300mm high
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Allow for any other works which are not included above and which are required to complete the Metalwork in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0ItemNeeds review
Primary Structural Steel (Non Fire Rated) to inaccessible areas on façade (Dummy Balconies) and Canopies Provisional Qty
REVIEWItem code "ADD" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
552.04t19,218.0010,609,104.72Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; UB 533 x 210 x 82
REVIEWItem code "A" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-5.69t21,769.00-123,865.61Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; UC 203 x 203 x 60
REVIEWItem code "B" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
4.6t21,769.00100,137.40Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; CHS 219 x 6.3
REVIEWItem code "C" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-0.28t21,769.00-6,095.32Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; SHS 150 x 150 x 6.3
REVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-0.44t21,769.00-9,578.36Needs review
Structural steel frame; with grade S275/355; conforming to BS 5950 and BS EN 10025; including teflon, stiffeners, fixings, supports, surface treatment, protective coatings, accessories and all ancillary works as necessary
Columns; SHS 120 x 120 x 6.3
REVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-0.03t21,769.00-653.07Needs review
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications
To ground floor and podium walls
REVIEWItem code "D" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-64m21,133.00-72,512.00Needs review
Type AL-03; 3mm thick solid core aluminium cladding panels;PVDF coated; colour RAL 050 50 10 (Teakwood Brown - Light Brown, Matte finish, Smooth textured), including secondary support framing system and thermal insulation; water proofing where required; including all fixings, fittings, accessories and all ancillary works as per drawings and specifications
To tower walls
REVIEWItem code "E" is used more than once on 2 - Main/28. Kept as printed — confirm the numbering.
-543m21,133.00-615,219.00Needs review
Section 2/F · SECTION F - WOOD WORK · Page 2/F/1 - 2/F/25
0/9 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Woodwork in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Kitchen cabinets; to show kitchen; including countertop, forming of holes, frames, carcass, supports, front/back/side panels, doors, shelves, drawers, concealed light (measured separately), skirting, hardware, finishes, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
Vanity counters; including countertop, forming of holes, front/side panels, drawers, hardware, finishes, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
To powder room
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed.
0.00Needs review
Veneered shelves; including finishes, fixings, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
To powder room
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed.
0.00Needs review
Cabinets with veneered open shelf; including concealed light (measured separately), front/side panels, hardware, finishes, fixings, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
To powder room
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"To powder room" has no heading context while other items on 2 - Main/52 do — a governing heading may have been missed.
0.00Needs review
Wardrobes; comprising 18mm thick MDF shelving and glass shutter; including MDF backing, carcass, frames, supports, front/side/back panels, doors, shelves, drawers, concealed light (measured separately), hardware, finishes, accessories and all ancillary works as necessary
REVIEWThe source prints neither a quantity nor a rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0.00Needs review
Section 2/G · SECTION G - THERMAL AND MOISTURE PROTECTION · Page 2/G/1 - 2/G/5
0/1 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Thermal and Moisture Protection in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Section 2/H · SECTION H - DOORS AND WINDOWS · Page 2/H/1 - 2/H/17
0/4 clear
0.00 Σ lines
Allow for any other works which are not included above and which are required to complete the Doors and Windows in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0ItemNeeds review
Double glazed vision panel screen; Type V1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications
REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Needs review
Double glazed vision panel screen; Type V2; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 8mm FT; U-value = 1.7W/m²K; Shading coefficient 0.25 max.; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, insulation, plaster board, fixings, fittings, accessories and all ancillary works as per drawings and specifications
REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Needs review
Double glazed spandrel panel screen; Type S1; light smokey grey; Buildup: IGU; Outer lite: 8mm FT, Low E coating on surface #2 + 16mm AS + Inner lite: 6mm FT; including frames, sub-frame, door system, finishes, joint, gasket, toggle clip, sealant, plaster board, insulation, fixings, fittings, accessories and all ancillary works as per drawings and specifications
REVIEW0 measured, but the source prints no rate and the Amount cell is empty — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Needs review
Section 2/J · SECTION J - FINISHES · Page 2/J/1 - 2/J/18
0/3 clear
0.00 Σ lines
Gypsum board tile ceiling system; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories
Extra over for access panel
REVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemNot ApplicableNeeds review
Concealed grid aluminium tile ceiling system; demountable, perforated aluminium tiles; including finishes, suspended metal support framing system, brackets, fastenings, accessories and all necessary fixings and accessories
Extra over for access panel
REVIEWAmount column prints "Not Applicable" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
0ItemNot ApplicableNeeds review
Allow for any other works which are not included above and which are required to complete the Finishes in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Section 2/K · SECTION K - ACCESSORIES · Page 2/K/1 - 2/K/14
0/10 clear
356,655.00 Σ lines
Common Areas
Type SAN-711; toilet paper holder
REVIEW9 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
9Nr.0.00Needs review
Internal Signage
Retail sign by others
REVIEWAmount column prints "By Others" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
6Nr.By OthersNeeds review
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary
Type EXH-301; 100mm high
REVIEW2,969 m2 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2,969m20.00Needs review
Kerbs; precast concrete fixed to floor slab; including fixings, finishes, accessories and all ancillary works as necessary
150mm high; to ramps
REVIEW609 m measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
609m0.00Needs review
Allow for any other works which are not included above and which are required to complete the Accessories in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Tempered mirror; type GL-101; 6mm thick clear mirror with metal frame; including, backing, supports, finishes, accessories and all ancillary works as necessary
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
00.00Needs review
Shower glass partition; fixed glass with doors; glass; 10mm thick; including ironmongery, fixings, accessories and all ancillary works as necessary
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
00.00Needs review
Clear Glass
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"Clear Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed.
00.00Needs review
Fluted Tinted Glass
REVIEW0 measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
REVIEW"Fluted Tinted Glass" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed.
00.00Needs review
Precast Concrete kerb
REVIEW"Precast Concrete kerb" has no heading context while other items on 2 - Main/102 do — a governing heading may have been missed.
2,301m155.00356,655.00Needs review
Section 2/L · SECTION L - EQUIPMENT · Page 2/L/1 - 2/L/7
0/42 clear
50,850.00 Σ lines1 errors
White goods; including accessories and all ancillary works as necessary
Type WG-111; freestanding cooker
REVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
30Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-112; freestanding fridge
REVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
30Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-113; freestanding freezer
REVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
30Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-114; freestanding dishwasher
REVIEW30 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
30Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-116; coffee machine
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-117; tv screen
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-118; tv screen
REVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
5Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-119; water dispenser
REVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
8Nr.0.00Needs review
White goods; including accessories and all ancillary works as necessary
Type WG-120; tv screen
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Supply and installation by Others: Contractor to allow for Co-ordination, attendance and builders work
ERRORNo item reference on 2 - Main/104. Every priced line carries a printed reference (A, B, C…) — either the reference was missed, or this row is not an item.
1Item50,850.0050,850.00Error
Type EQ-101; run 19" excite live
REVIEW7 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
7Nr.0.00Needs review
Type EQ-102; climb 16" excite live
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-103; synchro ar 16" excite live
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-104; technogym bike
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-105; skillrow
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-106; lower back fitness bench
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Type EQ-107; yoga mat
REVIEW9 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
9Nr.0.00Needs review
Type EQ-108; crunch bench press
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-109; multi-power
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-110; adjustable bench
REVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
5Nr.0.00Needs review
Type EQ-111; two tier dumbbell rack
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-112; dumbbells (10 pairs)
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-113; dual leg curl/leg extension selection 700
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-114; lat machine selection 700
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-115; shoulder press-selection 700
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-116; chest press-selection 700
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-117; skill tools storage
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-118; universe wall 2 virtual
REVIEW3 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
3Nr.0.00Needs review
Type EQ-119; vario 16" excite live
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-120; skill up
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-121; skillmill
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-122; skillrun unity 7000
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-123; plyobox
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-124; punching bag
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Type EQ-125; leg press selection 700
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Galvanized mild steel running track; including galvanized steel base plates, clip ears, stainless steel A4/80 u-bolts, high-strength grout, fixings; complete
BMU tracks at 4000mm center to center
REVIEWAmount column prints "Included" — counted as 0.00 in the totals, exactly as the source's own page total does. Confirm this is intended (e.g. a RATE ONLY schedule).
183mIncludedNeeds review
Allow to detent pin BMU restraints; including painted restraint socket, fixings, brackets, accessories and all ancillary works as necessary
To tower 1
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow to detent pin BMU restraints; including painted restraint socket, fixings, brackets, accessories and all ancillary works as necessary
To tower 2
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow to detent pin BMU restraints; including painted restraint socket, fixings, brackets, accessories and all ancillary works as necessary
To tower 3
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow to detent pin BMU restraints; including painted restraint socket, fixings, brackets, accessories and all ancillary works as necessary
To tower 4
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow to detent pin BMU restraints; including painted restraint socket, fixings, brackets, accessories and all ancillary works as necessary
Allow to mobile elevated work platform (MEWP) including accessories and all ancillary works as necessary
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Allow for any other works which are not included above and which are required to complete the Equipment in accordance with the Specification and the Drawings (Tenderer to list below):
REVIEW0 Item measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
0Item0.00Needs review
Section 2/M · SECTION M - FURNISHING · Page 2/M/1 - 2/M/7
0/101 clear
0.00 Σ lines
Case goods; including accessories and all ancillary works as necessary
Type CG-101; coffee table
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-102; side table
REVIEW6 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
6Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-103; side table
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-104; console behind sofa
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-105; console
REVIEW6 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
6Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-106; side table
REVIEW6 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
6Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-107; table
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-108; console
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-109; coffee table
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-110; side table vintage bronze
REVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
8Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-111; side table
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-112; side table
REVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
5Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-113; communal table travertine
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-114; coffee table
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-115; coffee table
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-116; armchairs side table
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-117; sofa side table
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-118; coffee table
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-119; coffee table
REVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
8Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-120; dining table
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-121; console
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-122; gaming area side table
REVIEW12 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
12Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-123; kids table
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-124; pool table
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-125; foosball table
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Case goods; including accessories and all ancillary works as necessary
Type CG-126; shower bench
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Loose rugs; including accessories and all ancillary works as necessary
Type LR-101; seating area loose rug
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Loose rugs; including accessories and all ancillary works as necessary
Type LR-102; big table loose rug
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Loose rugs; including accessories and all ancillary works as necessary
Type LR-103; rectangular loose rug
REVIEW5 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
5Nr.0.00Needs review
Loose rugs; including accessories and all ancillary works as necessary
Type LR-104; rectangular loose rug
REVIEW1 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
1Nr.0.00Needs review
Loose rugs; including accessories and all ancillary works as necessary
Type LR-105; loose rug
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Loose rugs; including accessories and all ancillary works as necessary
Type LR-106; loose rug
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Loose rugs; including accessories and all ancillary works as necessary
Type LR-107; loose rug
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-101; sheer curtains
REVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
8Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-102; plant pots
REVIEW10 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
10Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-103; lift lobby entrance
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-104; artwork behind sofa
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-105; artwork above console- hand painted art painting
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-106; artwork at table area
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-107; artwork
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-108; entrance lobby corridor artwork
REVIEW8 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
8Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-109; roller blinds
REVIEW37 m measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
37m0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-110; accessories
REVIEW2 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
2Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-111; artwork
REVIEW215 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
215Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-112; artwork
REVIEW870 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
870Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-113; curtains manual
REVIEW30 m measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
30m0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-114; plant pots
REVIEW6 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
6Nr.0.00Needs review
Miscellaneous; including accessories and all ancillary works as necessary
Type MI-115; sheer curtains-seating area and table area only (deleted)
REVIEW4 Nr. measured, but the source prints no rate and the Amount cell holds 0.00 — this line carries no money into the totals. An empty rate is not a rate of zero: confirm the bidder meant to leave it unpriced (covered elsewhere), or put it to them as a clarification.
4Nr.0.00Needs review
loading more… 150 of 807 lines rendered

What the bidder did with the line

Read from the source. Every line sits in exactly one of these.
StateLinesMeasuredMoney
PricedA rate in the source and money in the amount.7,3317,914,918.742,246,018,361.00
UnpricedNo rate given, nothing carried into the totals.20991,900.88
Prints words, not a figure“By Others”, “Included” — counted as nil, as the bidder's own page total does.58952,231.72
Priced as a wholeMoney on the line with no rate behind it — a lump or provisional sum.110291,658,553.00

Where your review stands

Your review of those same lines — a line can be in more than one.
StateLinesMeasuredMoney
Still openCarries a question nobody has answered yet.807147,189.810,798,619.76
ConfirmedYou checked it; the finding stands and left the queue.0
RuledA recorded determination answers it — reversible at any time.0
Does not reconcileAn error on the line itself, not on its block.1150,850.00

Collection blocks

Σ of each block’s line amounts against the total the source itself prints.
BlockSectionLinesΣ linesSource printsTies
GR1/1GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS30.000.00
GR1/2GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS914,590,702.0014,590,702.00
GR1/3GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS10.000.00
GR1/4GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS53,780,402.003,780,402.00
GR1/5GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS7143,675,216.00143,675,216.00
GR1/6GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS1643,935,329.0043,935,329.00
GR1/7GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS112,189,955.002,189,955.00
GR1/8GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS497,000.0097,000.00
GR1/9GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS128,365,201.008,365,201.00
GR1/10GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS939,972,150.0039,972,150.00
GR1/11GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS31,287,963.001,287,963.00
GR1/12GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS145,482,653.005,482,653.00
GR1/13GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS176,598,029.006,598,029.00
GR1/14GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS1325,400.00325,400.00
GR1/15GENERAL REQUIREMENTS FOR THE WHOLE OF THE WORKS10.000.00
2 - Main/1SITE PREPARATION63,860,035.483,860,035.48
2 - Main/2BORED PILING62,395,497.002,395,497.00
2 - Main/3VARIANCE IN QUANTITY71,250,203.001,250,203.00
2 - Main/4POURED CONCRETE1916,203,427.0016,203,427.00
2 - Main/5POURED CONCRETE2032,621,748.0032,621,748.00
2 - Main/6POURED CONCRETE2346,443,438.0046,443,438.00
2 - Main/7POURED CONCRETE6407,176.00407,176.00
2 - Main/8REINFORCEMENT22200,093,867.32200,093,867.32
2 - Main/9REINFORCEMENT61,262,147.851,262,147.85
2 - Main/10SHUTTERING2088,257,136.0088,257,136.00
2 - Main/11SHUTTERING41,838,266.001,838,266.00
2 - Main/12PRESTRESSED CONCRETE488,831,972.3788,831,972.37
2 - Main/13SUNDRIES56,016,537.006,016,537.00
2 - Main/14VARIANCE IN QUANTITY13849,063,286.7349,063,286.73
2 - Main/15WALL AND PIERS1138,176,342.0038,176,342.00
2 - Main/16SUNDRIES40.000.00
2 - Main/17VARIANCE IN QUANTITY122,003,408.002,003,408.00
2 - Main/18STRUCTURAL METALWORK183,859,643.703,859,643.70
2 - Main/19STRUCTURAL METALWORK51,755,452.161,755,452.16
2 - Main/20NON-STRUCTURAL METALWORK574,727,568.0074,727,568.00
2 - Main/21NON-STRUCTURAL METALWORK147,395,546.007,395,546.00
2 - Main/22NON-STRUCTURAL METALWORK1654,536,508.0054,536,508.00
2 - Main/23NON-STRUCTURAL METALWORK2048,059,944.0048,059,944.00
2 - Main/24NON-STRUCTURAL METALWORK1550,152,943.0050,152,943.00
2 - Main/25NON-STRUCTURAL METALWORK126,756,343.006,756,343.00
2 - Main/26NON-STRUCTURAL METALWORK9541,455.00541,455.00
2 - Main/27NON-STRUCTURAL METALWORK125,069,170.005,069,170.00
2 - Main/28VARIANCE IN QUANTITY8817,672,289.5417,672,289.54
2 - Main/29COMPOSITE ITEMS123,809,123.003,809,123.00
2 - Main/30COMPOSITE ITEMS142,032,524.002,032,524.00
2 - Main/31COMPOSITE ITEMS131,023,548.001,023,548.00
2 - Main/32COMPOSITE ITEMS203,573,015.003,573,015.00
2 - Main/33COMPOSITE ITEMS163,523,105.003,523,105.00
2 - Main/34COMPOSITE ITEMS186,221,471.006,221,471.00
2 - Main/35COMPOSITE ITEMS181,568,576.001,568,576.00
2 - Main/36COMPOSITE ITEMS19814,336.00814,336.00
2 - Main/37COMPOSITE ITEMS1720,293,915.0020,293,915.00
2 - Main/38COMPOSITE ITEMS1617,227,769.0017,227,769.00
2 - Main/39COMPOSITE ITEMS91,614,018.001,614,018.00
2 - Main/40COMPOSITE ITEMS1626,009,219.0026,009,219.00
2 - Main/41COMPOSITE ITEMS2136,888,565.0036,888,565.00
2 - Main/42COMPOSITE ITEMS189,209,998.009,209,998.00
2 - Main/43COMPOSITE ITEMS181,427,050.001,427,050.00
2 - Main/44COMPOSITE ITEMS16531,370.00531,370.00
2 - Main/45COMPOSITE ITEMS131,817,804.001,817,804.00
2 - Main/46COMPOSITE ITEMS1546,985.0046,985.00
2 - Main/47COMPOSITE ITEMS12171,071.00171,071.00
2 - Main/48COMPOSITE ITEMS14563,055.00563,055.00
2 - Main/49COMPOSITE ITEMS91,428,435.001,428,435.00
2 - Main/50COMPOSITE ITEMS141,237,124.001,237,124.00
2 - Main/51COMPOSITE ITEMS13555,104.00555,104.00
2 - Main/52VARIANCE IN QUANTITY135-2,746,179.00-2,746,179.00
2 - Main/53COVERS AND LININGS922,096,305.0022,096,305.00
2 - Main/54DAMP-PROOF COURSES41,087,678.891,087,678.89
2 - Main/55INSULATION45,779,558.005,779,558.00
2 - Main/56VARIANCE IN QUANTITY2412,006,171.4012,006,171.40
2 - Main/57DOORS1331,124,879.0031,124,879.00
2 - Main/58DOORS165,878,024.005,878,024.00
2 - Main/59DOORS1611,515,630.0011,515,630.00
2 - Main/60DOORS202,402,117.002,402,117.00
2 - Main/61SCREENS161,663,318.001,663,318.00
2 - Main/62EXTERNAL DOORS12179,836.00179,836.00
2 - Main/63EXTERNAL DOORS121,326,232.001,326,232.00
2 - Main/64SCREENS1881,576,870.0081,576,870.00
2 - Main/65SCREENS182,483,049.002,483,049.00
2 - Main/66SCREENS1611,773,289.0011,773,289.00
2 - Main/67SCREENS132,530,444.002,530,444.00
2 - Main/68SCREENS1435,514,151.0035,514,151.00
2 - Main/69LOUVERS148,194,223.008,194,223.00
2 - Main/70IRONMONGERY21684,142.00684,142.00
2 - Main/71IRONMONGERY14166,455.00166,455.00
2 - Main/72VARIANCE IN QUANTITY756,619,900.006,619,900.00
2 - Main/73BACKGROUNDS1747,354,408.0047,354,408.00
2 - Main/74BACKGROUNDS65,629,577.005,629,577.00
2 - Main/75FLOOR FINISHES1498,699,285.0098,699,285.00
2 - Main/76FLOOR FINISHES142,413,857.002,413,857.00
2 - Main/77FLOOR FINISHES91,498,853.001,498,853.00
2 - Main/78FLOOR FINISHES810,059,219.0010,059,219.00
2 - Main/79WALL FINISHES1425,034,660.0025,034,660.00
2 - Main/80WALL FINISHES1126,175,988.0026,175,988.00
2 - Main/81CEILING FINISHES63,092,350.003,092,350.00
2 - Main/82SUNDRIES72,053,927.002,053,927.00
2 - Main/83SUSPENDED CEILING1615,696,749.0015,696,749.00
2 - Main/84SUSPENDED CEILING165,315,401.005,315,401.00
2 - Main/85SUSPENDED CEILING184,947,504.004,947,504.00
2 - Main/86DECORATIONS1226,625,044.0026,625,044.00
2 - Main/87DECORATIONS1212,560,108.0012,560,108.00
2 - Main/88SIGNWRITING143,237,070.003,237,070.00
2 - Main/89VARIANCE IN QUANTITY18420,410,008.0020,410,008.00
2 - Main/90TOILET ACCESSORIES20338,991.00338,991.00
2 - Main/91TOILET ACCESSORIES214,777,421.004,777,421.00
2 - Main/92KITCHEN ACCESSORIES72,713,505.002,713,505.00
2 - Main/93SIGNAGE AND WAYFINDING201,399,437.001,399,437.00
2 - Main/94SIGNAGE AND WAYFINDING221,918,912.001,918,912.00
2 - Main/95PARKING ACCESSORIES13973,697.00973,697.00
2 - Main/96PARKING ACCESSORIES3715,629.00715,629.00
2 - Main/97PARTITIONS1521,652,099.0021,652,099.00
2 - Main/98PARTITIONS125,115,954.005,115,954.00
2 - Main/99TOILET PARTITION2010,184,517.0010,184,517.00
2 - Main/100TOILET PARTITION125,494,517.005,494,517.00
2 - Main/101WASTE CHUTES103,735,738.003,735,738.00
2 - Main/102VARIANCE IN QUANTITY1033,081,380.003,081,380.00
2 - Main/103WHITE GOODS1816,707,668.0016,707,668.00
2 - Main/104GYM EQUIPMENT2650,850.0050,850.00
2 - Main/105BUILDING MANAGEMENT UNIT (BMU)34,433,866.004,433,866.00
2 - Main/106BUILDING MANAGEMENT UNIT (BMU)81,329,654.001,329,654.00
2 - Main/107BUILDING MANAGEMENT UNIT (BMU)8113,994.00113,994.00
2 - Main/108GENERALLY10.000.00
2 - Main/109LOOSE FF&E220.000.00
2 - Main/110LOOSE FF&E210.000.00
2 - Main/111LOOSE FF&E240.000.00
2 - Main/112LOOSE FF&E200.000.00
2 - Main/113LOOSE FF&E15258,221.00258,221.00
2 - Main/114GENERALLY10.000.00
2 - Main/115LIFTS8577,868.00577,868.00
2 - Main/116LIFTS821,069,448.0021,069,448.00
2 - Main/117LIFTS623,135,368.0023,135,368.00
2 - Main/118LIFTS22,668,002.002,668,002.00
2 - Main/119SUNDRIES40.000.00
2 - Main/120BWIC60.000.00
2 - Main/121VARIANCE IN QUANTITY7-1,612.00-1,612.00
2 - Main/122SANITARY FIXTURES & FITTINGS162,126,910.002,126,910.00
2 - Main/123SANITARY FIXTURES & FITTINGS169,418,806.009,418,806.00
2 - Main/124SANITARY FIXTURES & FITTINGS152,581,521.002,581,521.00
2 - Main/125SANITARY FIXTURES & FITTINGS123,633,247.003,633,247.00
2 - Main/126SANITARY FIXTURES & FITTINGS8444,555.00444,555.00
2 - Main/127DRAINAGE INSTALLATION189,922,860.009,922,860.00
2 - Main/128DRAINAGE INSTALLATION161,788,732.001,788,732.00
2 - Main/129DRAINAGE INSTALLATION91,239,872.001,239,872.00
2 - Main/130DRAINAGE INSTALLATION171,638,017.001,638,017.00
2 - Main/131DRAINAGE INSTALLATION1510,324,346.0010,324,346.00
2 - Main/132DRAINAGE INSTALLATION175,072,471.005,072,471.00
2 - Main/133DRAINAGE INSTALLATION152,219,969.002,219,969.00
2 - Main/134DRAINAGE INSTALLATION10160,401.00160,401.00
2 - Main/135DRAINAGE INSTALLATION10303,129.00303,129.00
2 - Main/136DRAINAGE INSTALLATION11319,712.00319,712.00
2 - Main/137DRAINAGE INSTALLATION2121,982.00121,982.00
2 - Main/138WATER INSTALLATION1911,331,510.0011,331,510.00
2 - Main/139WATER INSTALLATION156,572,649.006,572,649.00
2 - Main/140WATER INSTALLATION123,542,932.003,542,932.00
2 - Main/141WATER INSTALLATION18986,815.00986,815.00
2 - Main/142WATER INSTALLATION16290,515.00290,515.00
2 - Main/143WATER INSTALLATION153,145,210.003,145,210.00
2 - Main/144WATER INSTALLATION82,767,282.002,767,282.00
2 - Main/145WATER INSTALLATION7712,884.00712,884.00
2 - Main/146WATER INSTALLATION8552,317.00552,317.00
2 - Main/147WATER INSTALLATION50.000.00
2 - Main/148FIRE PROTECTION SYSTEM58,160,904.008,160,904.00
2 - Main/149FIRE PROTECTION SYSTEM1714,730,632.0014,730,632.00
2 - Main/150FIRE PROTECTION SYSTEM213,201,240.003,201,240.00
2 - Main/151FIRE PROTECTION SYSTEM111,501,874.001,501,874.00
2 - Main/152FIRE PROTECTION SYSTEM74,731,233.004,731,233.00
2 - Main/153FIRE PROTECTION SYSTEM102,052,130.002,052,130.00
2 - Main/154FIRE PROTECTION SYSTEM90.000.00
2 - Main/155FIRE PROTECTION SYSTEM102,251,841.002,251,841.00
2 - Main/156FIRE PROTECTION SYSTEM5116,772.00116,772.00
2 - Main/157HVAC INSTALLATION1612,754,566.0012,754,566.00
2 - Main/158HVAC INSTALLATION169,108,483.009,108,483.00
2 - Main/159HVAC INSTALLATION18592,434.00592,434.00
2 - Main/160HVAC INSTALLATION134,543,571.004,543,571.00
2 - Main/161HVAC INSTALLATION76,708,515.006,708,515.00
2 - Main/162HVAC INSTALLATION7939,725.00939,725.00
2 - Main/163HVAC INSTALLATION131,231,126.001,231,126.00
2 - Main/164HVAC INSTALLATION910,442,776.0010,442,776.00
2 - Main/165HVAC INSTALLATION2276,591.0076,591.00
2 - Main/166HVAC INSTALLATION2196,924.0096,924.00
2 - Main/167HVAC INSTALLATION21457,731.00457,731.00
2 - Main/168HVAC INSTALLATION22157,838.00157,838.00
2 - Main/169HVAC INSTALLATION17103,002.00103,002.00
2 - Main/170HVAC INSTALLATION21293,208.00293,208.00
2 - Main/171HVAC INSTALLATION2240,087.0040,087.00
2 - Main/172HVAC INSTALLATION2096,387.0096,387.00
2 - Main/173HVAC INSTALLATION22228,699.00228,699.00
2 - Main/174HVAC INSTALLATION2224,429.0024,429.00
2 - Main/175HVAC INSTALLATION15420,054.00420,054.00
2 - Main/176HVAC INSTALLATION21499,528.00499,528.00
2 - Main/177HVAC INSTALLATION20431,877.00431,877.00
2 - Main/178HVAC INSTALLATION14278,480.00278,480.00
2 - Main/179HVAC INSTALLATION1427,540.0027,540.00
2 - Main/180HVAC INSTALLATION1433,123.0033,123.00
2 - Main/181HVAC INSTALLATION1423,181.0023,181.00
2 - Main/182HVAC INSTALLATION1425,557.0025,557.00
2 - Main/183HVAC INSTALLATION1424,152.0024,152.00
2 - Main/184HVAC INSTALLATION14235,219.00235,219.00
2 - Main/185HVAC INSTALLATION14504,072.00504,072.00
2 - Main/186HVAC INSTALLATION14135,348.00135,348.00
2 - Main/187HVAC INSTALLATION1422,872.0022,872.00
2 - Main/188HVAC INSTALLATION1421,806.0021,806.00
2 - Main/189HVAC INSTALLATION1421,615.0021,615.00
2 - Main/190HVAC INSTALLATION14291,474.00291,474.00
2 - Main/191HVAC INSTALLATION14341,792.00341,792.00
2 - Main/192HVAC INSTALLATION1422,912.0022,912.00
2 - Main/193HVAC INSTALLATION1476,803.0076,803.00
2 - Main/194HVAC INSTALLATION1469,668.0069,668.00
2 - Main/195HVAC INSTALLATION1427,445.0027,445.00
2 - Main/196HVAC INSTALLATION1447,041.0047,041.00
2 - Main/197HVAC INSTALLATION1421,207.0021,207.00
2 - Main/198HVAC INSTALLATION1424,683.0024,683.00
2 - Main/199HVAC INSTALLATION1428,793.0028,793.00
2 - Main/200HVAC INSTALLATION1428,526.0028,526.00
2 - Main/201HVAC INSTALLATION14470,334.00470,334.00
2 - Main/202HVAC INSTALLATION14439,954.00439,954.00
2 - Main/203HVAC INSTALLATION1421,900.0021,900.00
2 - Main/204HVAC INSTALLATION1422,312.0022,312.00
2 - Main/205HVAC INSTALLATION1422,287.0022,287.00
2 - Main/206HVAC INSTALLATION1424,848.0024,848.00
2 - Main/207HVAC INSTALLATION14339,200.00339,200.00
2 - Main/208HVAC INSTALLATION14221,888.00221,888.00
2 - Main/209HVAC INSTALLATION1421,636.0021,636.00
2 - Main/210HVAC INSTALLATION1420,787.0020,787.00
2 - Main/211HVAC INSTALLATION1426,835.0026,835.00
2 - Main/212HVAC INSTALLATION1427,640.0027,640.00
2 - Main/213HVAC INSTALLATION1423,356.0023,356.00
2 - Main/214HVAC INSTALLATION1421,540.0021,540.00
2 - Main/215HVAC INSTALLATION1424,520.0024,520.00
2 - Main/216HVAC INSTALLATION1423,042.0023,042.00
2 - Main/217HVAC INSTALLATION1425,993.0025,993.00
2 - Main/218HVAC INSTALLATION1425,434.0025,434.00
2 - Main/219HVAC INSTALLATION1428,382.0028,382.00
2 - Main/220HVAC INSTALLATION1430,396.0030,396.00
2 - Main/221HVAC INSTALLATION14120,029.00120,029.00
2 - Main/222HVAC INSTALLATION1428,605.0028,605.00
2 - Main/223HVAC INSTALLATION1421,946.0021,946.00
2 - Main/224HVAC INSTALLATION1423,379.0023,379.00
2 - Main/225HVAC INSTALLATION1430,200.0030,200.00
2 - Main/226HVAC INSTALLATION1422,510.0022,510.00
2 - Main/227HVAC INSTALLATION14452,659.00452,659.00
2 - Main/228HVAC INSTALLATION14392,318.00392,318.00
2 - Main/229HVAC INSTALLATION1421,706.0021,706.00
2 - Main/230HVAC INSTALLATION1420,788.0020,788.00
2 - Main/231HVAC INSTALLATION1421,320.0021,320.00
2 - Main/232HVAC INSTALLATION1419,825.0019,825.00
2 - Main/233HVAC INSTALLATION14319,831.00319,831.00
2 - Main/234HVAC INSTALLATION14469,465.00469,465.00
2 - Main/235HVAC INSTALLATION1430,832.0030,832.00
2 - Main/236HVAC INSTALLATION1420,638.0020,638.00
2 - Main/237HVAC INSTALLATION1424,276.0024,276.00
2 - Main/238HVAC INSTALLATION1423,090.0023,090.00
2 - Main/239HVAC INSTALLATION1432,393.0032,393.00
2 - Main/240HVAC INSTALLATION1423,162.0023,162.00
2 - Main/241HVAC INSTALLATION1426,211.0026,211.00
2 - Main/242HVAC INSTALLATION1424,751.0024,751.00
2 - Main/243HVAC INSTALLATION1426,615.0026,615.00
2 - Main/244HVAC INSTALLATION1423,471.0023,471.00
2 - Main/245HVAC INSTALLATION14247,329.00247,329.00
2 - Main/246HVAC INSTALLATION14531,312.00531,312.00
2 - Main/247HVAC INSTALLATION14156,105.00156,105.00
2 - Main/248HVAC INSTALLATION14131,952.00131,952.00
2 - Main/249HVAC INSTALLATION1418,538.0018,538.00
2 - Main/250HVAC INSTALLATION1424,342.0024,342.00
2 - Main/251HVAC INSTALLATION14158,933.00158,933.00
2 - Main/252HVAC INSTALLATION14324,448.00324,448.00
2 - Main/253HVAC INSTALLATION1464,569.0064,569.00
2 - Main/254HVAC INSTALLATION1420,235.0020,235.00
2 - Main/255HVAC INSTALLATION1424,999.0024,999.00
2 - Main/256HVAC INSTALLATION1422,993.0022,993.00
2 - Main/257HVAC INSTALLATION1423,670.0023,670.00
2 - Main/258HVAC INSTALLATION1426,978.0026,978.00
2 - Main/259HVAC INSTALLATION1426,017.0026,017.00
2 - Main/260HVAC INSTALLATION11775,835.00775,835.00
2 - Main/261HVAC INSTALLATION1210,802,888.0010,802,888.00
2 - Main/262HVAC INSTALLATION18214,566.00214,566.00
2 - Main/263HVAC INSTALLATION2216,470.0016,470.00
2 - Main/264HVAC INSTALLATION2218,179.0018,179.00
2 - Main/265HVAC INSTALLATION2214,672.0014,672.00
2 - Main/266HVAC INSTALLATION2189,623.0089,623.00
2 - Main/267HVAC INSTALLATION2215,098.0015,098.00
2 - Main/268HVAC INSTALLATION2214,051.0014,051.00
2 - Main/269HVAC INSTALLATION2213,534.0013,534.00
2 - Main/270HVAC INSTALLATION2013,419.0013,419.00
2 - Main/271HVAC INSTALLATION17150,318.00150,318.00
2 - Main/272HVAC INSTALLATION2028,313.0028,313.00
2 - Main/273HVAC INSTALLATION183,826.003,826.00
2 - Main/274HVAC INSTALLATION57,079.007,079.00
2 - Main/275HVAC INSTALLATION864,467.0064,467.00
2 - Main/276HVAC INSTALLATION1514,636,106.0014,636,106.00
2 - Main/277HVAC INSTALLATION20314,415.00314,415.00
2 - Main/278HVAC INSTALLATION21248,905.00248,905.00
2 - Main/279HVAC INSTALLATION2286,982.0086,982.00
2 - Main/280HVAC INSTALLATION20169,694.00169,694.00
2 - Main/281HVAC INSTALLATION14615,346.00615,346.00
2 - Main/282HVAC INSTALLATION1794,916.0094,916.00
2 - Main/283HVAC INSTALLATION12806,741.00806,741.00
2 - Main/284HVAC INSTALLATION131,602,928.001,602,928.00
2 - Main/285HVAC INSTALLATION131,634,623.001,634,623.00
2 - Main/286HVAC INSTALLATION11379,482.00379,482.00
2 - Main/287HVAC INSTALLATION13127,755.00127,755.00
2 - Main/288HVAC INSTALLATION14140,228.00140,228.00
2 - Main/289HVAC INSTALLATION12117,277.00117,277.00
2 - Main/290HVAC INSTALLATION790,165.0090,165.00
2 - Main/291LPG INSTALLATION10.000.00
2 - Main/292LPG INSTALLATION100.000.00
2 - Main/293LPG INSTALLATION145,458,814.005,458,814.00
2 - Main/294LPG INSTALLATION50.000.00
2 - Main/295SUNDRIES95,182,909.005,182,909.00
2 - Main/296SUNDRIES183,902.0083,902.00
2 - Main/297WORK INCIDENTAL AND BWIC9314,631.00314,631.00
2 - Main/298WORK INCIDENTAL AND BWIC34,901,091.004,901,091.00
2 - Main/299GENERALLY1315,232,423.0015,232,423.00
2 - Main/300POWER INSTALLATION634,134.0034,134.00
2 - Main/301POWER INSTALLATION1677,096.0077,096.00
2 - Main/302POWER INSTALLATION1371,800.0071,800.00
2 - Main/303POWER INSTALLATION15281,333.00281,333.00
2 - Main/304POWER INSTALLATION16383,435.00383,435.00
2 - Main/305POWER INSTALLATION1090,279.0090,279.00
2 - Main/306POWER INSTALLATION10195,070.00195,070.00
2 - Main/307POWER INSTALLATION13454,776.00454,776.00
2 - Main/308POWER INSTALLATION11274,336.00274,336.00
2 - Main/309POWER INSTALLATION1414,160.0014,160.00
2 - Main/310POWER INSTALLATION1219,422.0019,422.00
2 - Main/311POWER INSTALLATION1548,144.0048,144.00
2 - Main/312POWER INSTALLATION2167,543.0067,543.00
2 - Main/313POWER INSTALLATION2244,933.0044,933.00
2 - Main/314POWER INSTALLATION2256,889.0056,889.00
2 - Main/315POWER INSTALLATION2232,683.0032,683.00
2 - Main/316POWER INSTALLATION2182,124.0082,124.00
2 - Main/317POWER INSTALLATION14244,755.00244,755.00
2 - Main/318POWER INSTALLATION1558,506.0058,506.00
2 - Main/319POWER INSTALLATION17130,928.00130,928.00
2 - Main/320POWER INSTALLATION17169,687.00169,687.00
2 - Main/321POWER INSTALLATION15212,268.00212,268.00
2 - Main/322POWER INSTALLATION15146,853.00146,853.00
2 - Main/323POWER INSTALLATION1695,844.0095,844.00
2 - Main/324POWER INSTALLATION16176,449.00176,449.00
2 - Main/325POWER INSTALLATION1981,389.0081,389.00
2 - Main/326POWER INSTALLATION14225,645.00225,645.00
2 - Main/327POWER INSTALLATION1794,521.0094,521.00
2 - Main/328POWER INSTALLATION16113,484.00113,484.00
2 - Main/329POWER INSTALLATION14200,459.00200,459.00
2 - Main/330POWER INSTALLATION1876,440.0076,440.00
2 - Main/331POWER INSTALLATION14202,027.00202,027.00
2 - Main/332POWER INSTALLATION18154,056.00154,056.00
2 - Main/333POWER INSTALLATION16195,314.00195,314.00
2 - Main/334POWER INSTALLATION14112,716.00112,716.00
2 - Main/335POWER INSTALLATION1480,727.0080,727.00
2 - Main/336POWER INSTALLATION1268,693.0068,693.00
2 - Main/337POWER INSTALLATION11110,902.00110,902.00
2 - Main/338POWER INSTALLATION13101,452.00101,452.00
2 - Main/339POWER INSTALLATION1482,431.0082,431.00
2 - Main/340POWER INSTALLATION1469,651.0069,651.00
2 - Main/341POWER INSTALLATION1592,577.0092,577.00
2 - Main/342POWER INSTALLATION1595,254.0095,254.00
2 - Main/343POWER INSTALLATION13129,990.00129,990.00
2 - Main/344POWER INSTALLATION14120,660.00120,660.00
2 - Main/345POWER INSTALLATION13331,800.00331,800.00
2 - Main/346POWER INSTALLATION14283,624.00283,624.00
2 - Main/347POWER INSTALLATION11425,611.00425,611.00
2 - Main/348POWER INSTALLATION1435,345.0035,345.00
2 - Main/349POWER INSTALLATION1425,959.0025,959.00
2 - Main/350POWER INSTALLATION1430,549.0030,549.00
2 - Main/351POWER INSTALLATION17326,417.00326,417.00
2 - Main/352POWER INSTALLATION2144,472.0044,472.00
2 - Main/353POWER INSTALLATION2071,468.0071,468.00
2 - Main/354POWER INSTALLATION2088,468.0088,468.00
2 - Main/355POWER INSTALLATION2086,224.0086,224.00
2 - Main/356POWER INSTALLATION1662,879.0062,879.00
2 - Main/357POWER INSTALLATION19160,611.00160,611.00
2 - Main/358POWER INSTALLATION13109,474.00109,474.00
2 - Main/359POWER INSTALLATION15112,395.00112,395.00
2 - Main/360POWER INSTALLATION14382,786.00382,786.00
2 - Main/361POWER INSTALLATION13751,774.00751,774.00
2 - Main/362POWER INSTALLATION101,036,919.001,036,919.00
2 - Main/363POWER INSTALLATION104,738,764.004,738,764.00
2 - Main/364POWER INSTALLATION152,203,059.002,203,059.00
2 - Main/365POWER INSTALLATION229,916.009,916.00
2 - Main/366POWER INSTALLATION170.000.00
2 - Main/367POWER INSTALLATION170.000.00
2 - Main/368POWER INSTALLATION160.000.00
2 - Main/369POWER INSTALLATION160.000.00
2 - Main/370POWER INSTALLATION180.000.00
2 - Main/371POWER INSTALLATION15509,830.00509,830.00
2 - Main/372POWER INSTALLATION149,326,877.009,326,877.00
2 - Main/373POWER INSTALLATION169,271,261.009,271,261.00
2 - Main/374POWER INSTALLATION183,772,209.003,772,209.00
2 - Main/375POWER INSTALLATION22317,108.00317,108.00
2 - Main/376POWER INSTALLATION22304,893.00304,893.00
2 - Main/377POWER INSTALLATION22359,914.00359,914.00
2 - Main/378POWER INSTALLATION22304,865.00304,865.00
2 - Main/379POWER INSTALLATION22281,377.00281,377.00
2 - Main/380POWER INSTALLATION22396,445.00396,445.00
2 - Main/381POWER INSTALLATION20288,280.00288,280.00
2 - Main/382POWER INSTALLATION22311,685.00311,685.00
2 - Main/383POWER INSTALLATION22320,519.00320,519.00
2 - Main/384POWER INSTALLATION22317,108.00317,108.00
2 - Main/385POWER INSTALLATION22307,886.00307,886.00
533 blocks2,537,676,914.00

Source verification

Independent checks of the imported result against the raw workbook.
item count
Independent re-count matches on all 4 sheets (8256 items).
qty integrity
Quantity sums match the raw cells on every sheet.
amount integrity
Amount sums match the raw cells on every sheet.
row coverage
Every money-bearing row accounted for: items, block totals, 495 summary re-statements (excluded — would double-count), 2 post-summary annex rows (recorded, outside the bill's money story).
mirror
Cell-for-cell fidelity: descriptions, codes, and the number/text/empty state of every qty, rate and amount match the raw cells (33024 cells compared).
summary map
2 summary sheets, 2 entries: 2 matched to imported totals · imported but absent from every summary: 2 - Main, 3 - Ext
summary self check
The workbook's own summaries are internally consistent (6 checks across 3 sheets).
section tie
25/27 declared sections tie to the cent · declared but not in this import: 1/GR “GENERAL REQUIREMENTS FOR THE WHOLE OF TH” declared 270300000.00; 4/PS “PROVISIONAL SUMS” declared 4950000.00 · 117 lines carry no section reference
zone tie
band identified arithmetically as BASEMENTS · GF & PODIUM · TOWER 1 · TOWER 2 · TOWER 3 · TOWER 4 (the identity held on 386/388 sampled priced rows) · 150/150 declared zone cells tie · the bidder keeps their own check on 8133 rows: we agree on 7570, differ on 0 (557 not comparable because the Amount cell prints words — their formula compares a number against text, which Excel makes FALSE whatever the arithmetic; 6 because a zone cell prints words) · 54 of 7960 priced rows do not add across their zones
tender tie
The tender figure 2537676914.00 equals this import exactly.
amount in words
The tender figure written in words reads back to 2537676914.00 — the same number the sheet prints.
summary echo
4/4 sheet totals re-stated verbatim by the workbook's own summary sheets — the source confirms our totals.
1 unresolved error8,256 lines · 533 blocks · 2,537,676,914.00 AED
/ find move editEsc close